<?xml version="1.0" encoding="UTF-8" standalone="yes"?>
<Project xmlns="http://schemas.microsoft.com/project">
  <SaveVersion>14</SaveVersion>
  <Name>Office building construction</Name>
  <Title>Office building construction</Title>
  <ScheduleFromStart>1</ScheduleFromStart>
  <StartDate>2027-01-04T08:00:00</StartDate>
  <FinishDate>2027-06-03T17:00:00</FinishDate>
  <CalendarUID>1</CalendarUID>
  <DefaultStartTime>08:00:00</DefaultStartTime>
  <DefaultFinishTime>17:00:00</DefaultFinishTime>
  <DurationFormat>7</DurationFormat>
  <StatusDate>2027-03-09T17:00:00</StatusDate>
  <NewTasksAreManual>0</NewTasksAreManual>
  <ProjectExternallyEdited>0</ProjectExternallyEdited>
  <ExtendedAttributes>
    <ExtendedAttribute>
      <FieldID>188743783</FieldID>
      <FieldName>Duration1</FieldName>
      <Alias>Optimistic Duration</Alias>
    </ExtendedAttribute>
    <ExtendedAttribute>
      <FieldID>188743785</FieldID>
      <FieldName>Duration3</FieldName>
      <Alias>Pessimistic Duration</Alias>
    </ExtendedAttribute>
  </ExtendedAttributes>
  <Calendars>
    <Calendar>
      <UID>1</UID>
      <Name>Standard</Name>
      <IsBaseCalendar>1</IsBaseCalendar>
      <BaseCalendarUID>-1</BaseCalendarUID>
      <WeekDays>
        <WeekDay>
          <DayType>1</DayType>
          <DayWorking>0</DayWorking>
        </WeekDay>
        <WeekDay>
          <DayType>2</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>3</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>4</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>5</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>6</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>7</DayType>
          <DayWorking>0</DayWorking>
        </WeekDay>
      </WeekDays>
    </Calendar>
  </Calendars>
  <Tasks>
    <Task>
      <UID>0</UID>
      <ID>0</ID>
      <Name>Office building construction</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>0</OutlineNumber>
      <OutlineLevel>0</OutlineLevel>
      <Start>2027-01-04T08:00:00</Start>
      <Finish>2027-06-03T17:00:00</Finish>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-06-03T17:00:00</Finish>
        <Work>PT2740H0M0S</Work>
        <Cost>16882800</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-01-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-05T08:00:00</Start>
        <Finish>2027-01-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-06T08:00:00</Start>
        <Finish>2027-01-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-07T08:00:00</Start>
        <Finish>2027-01-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-08T08:00:00</Start>
        <Finish>2027-01-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-11T08:00:00</Start>
        <Finish>2027-01-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-12T08:00:00</Start>
        <Finish>2027-01-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-13T08:00:00</Start>
        <Finish>2027-01-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-14T08:00:00</Start>
        <Finish>2027-01-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-15T08:00:00</Start>
        <Finish>2027-01-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-18T08:00:00</Start>
        <Finish>2027-01-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT13H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-19T08:00:00</Start>
        <Finish>2027-01-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT13H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-20T08:00:00</Start>
        <Finish>2027-01-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT13H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-21T08:00:00</Start>
        <Finish>2027-01-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT13H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-22T08:00:00</Start>
        <Finish>2027-01-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT13H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-01-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT17H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-26T08:00:00</Start>
        <Finish>2027-01-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT17H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-01-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT17H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-28T08:00:00</Start>
        <Finish>2027-01-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT17H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-29T08:00:00</Start>
        <Finish>2027-01-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT17H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-01T08:00:00</Start>
        <Finish>2027-02-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT17H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-02T08:00:00</Start>
        <Finish>2027-02-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT17H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-03T08:00:00</Start>
        <Finish>2027-02-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT17H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-04T08:00:00</Start>
        <Finish>2027-02-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT17H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-05T08:00:00</Start>
        <Finish>2027-02-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT17H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-08T08:00:00</Start>
        <Finish>2027-02-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT9H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-09T08:00:00</Start>
        <Finish>2027-02-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT9H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-10T08:00:00</Start>
        <Finish>2027-02-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT9H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT9H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-12T08:00:00</Start>
        <Finish>2027-02-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT17H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-15T08:00:00</Start>
        <Finish>2027-02-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-16T08:00:00</Start>
        <Finish>2027-02-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-17T08:00:00</Start>
        <Finish>2027-02-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-18T08:00:00</Start>
        <Finish>2027-02-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-19T08:00:00</Start>
        <Finish>2027-02-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-22T08:00:00</Start>
        <Finish>2027-02-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-23T08:00:00</Start>
        <Finish>2027-02-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-24T08:00:00</Start>
        <Finish>2027-02-25T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-25T08:00:00</Start>
        <Finish>2027-02-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-26T08:00:00</Start>
        <Finish>2027-02-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-01T08:00:00</Start>
        <Finish>2027-03-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-02T08:00:00</Start>
        <Finish>2027-03-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-03T08:00:00</Start>
        <Finish>2027-03-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-04T08:00:00</Start>
        <Finish>2027-03-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-05T08:00:00</Start>
        <Finish>2027-03-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-08T08:00:00</Start>
        <Finish>2027-03-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-09T08:00:00</Start>
        <Finish>2027-03-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-10T08:00:00</Start>
        <Finish>2027-03-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-11T08:00:00</Start>
        <Finish>2027-03-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-12T08:00:00</Start>
        <Finish>2027-03-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-15T08:00:00</Start>
        <Finish>2027-03-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-16T08:00:00</Start>
        <Finish>2027-03-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-17T08:00:00</Start>
        <Finish>2027-03-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-18T08:00:00</Start>
        <Finish>2027-03-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-19T08:00:00</Start>
        <Finish>2027-03-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-22T08:00:00</Start>
        <Finish>2027-03-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-23T08:00:00</Start>
        <Finish>2027-03-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-24T08:00:00</Start>
        <Finish>2027-03-25T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-25T08:00:00</Start>
        <Finish>2027-03-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-26T08:00:00</Start>
        <Finish>2027-03-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-29T08:00:00</Start>
        <Finish>2027-03-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-30T08:00:00</Start>
        <Finish>2027-03-31T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-31T08:00:00</Start>
        <Finish>2027-04-01T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-01T08:00:00</Start>
        <Finish>2027-04-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-02T08:00:00</Start>
        <Finish>2027-04-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-05T08:00:00</Start>
        <Finish>2027-04-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-06T08:00:00</Start>
        <Finish>2027-04-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT52H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-07T08:00:00</Start>
        <Finish>2027-04-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT52H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-08T08:00:00</Start>
        <Finish>2027-04-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT52H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-09T08:00:00</Start>
        <Finish>2027-04-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT52H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-12T08:00:00</Start>
        <Finish>2027-04-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT52H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-13T08:00:00</Start>
        <Finish>2027-04-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT52H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-14T08:00:00</Start>
        <Finish>2027-04-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT52H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-15T08:00:00</Start>
        <Finish>2027-04-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT60H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-16T08:00:00</Start>
        <Finish>2027-04-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT40H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-19T08:00:00</Start>
        <Finish>2027-04-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT40H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-20T08:00:00</Start>
        <Finish>2027-04-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-21T08:00:00</Start>
        <Finish>2027-04-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-22T08:00:00</Start>
        <Finish>2027-04-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-23T08:00:00</Start>
        <Finish>2027-04-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-26T08:00:00</Start>
        <Finish>2027-04-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-27T08:00:00</Start>
        <Finish>2027-04-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-28T08:00:00</Start>
        <Finish>2027-04-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-29T08:00:00</Start>
        <Finish>2027-04-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-30T08:00:00</Start>
        <Finish>2027-05-01T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-05-03T08:00:00</Start>
        <Finish>2027-05-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-05-04T08:00:00</Start>
        <Finish>2027-05-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-05-05T08:00:00</Start>
        <Finish>2027-05-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-05-06T08:00:00</Start>
        <Finish>2027-05-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-05-07T08:00:00</Start>
        <Finish>2027-05-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-05-10T08:00:00</Start>
        <Finish>2027-05-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-05-11T08:00:00</Start>
        <Finish>2027-05-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-05-12T08:00:00</Start>
        <Finish>2027-05-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT48H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-05-13T08:00:00</Start>
        <Finish>2027-05-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT48H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-05-14T08:00:00</Start>
        <Finish>2027-05-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT40H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-05-17T08:00:00</Start>
        <Finish>2027-05-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT40H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-05-18T08:00:00</Start>
        <Finish>2027-05-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT40H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-05-19T08:00:00</Start>
        <Finish>2027-05-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT40H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-05-20T08:00:00</Start>
        <Finish>2027-05-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-05-21T08:00:00</Start>
        <Finish>2027-05-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-05-24T08:00:00</Start>
        <Finish>2027-05-25T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-05-25T08:00:00</Start>
        <Finish>2027-05-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-05-26T08:00:00</Start>
        <Finish>2027-05-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-05-27T08:00:00</Start>
        <Finish>2027-05-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-05-28T08:00:00</Start>
        <Finish>2027-05-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-05-31T08:00:00</Start>
        <Finish>2027-06-01T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-06-01T08:00:00</Start>
        <Finish>2027-06-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-06-02T08:00:00</Start>
        <Finish>2027-06-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-06-03T08:00:00</Start>
        <Finish>2027-06-03T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-01-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>90000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-05T08:00:00</Start>
        <Finish>2027-01-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>90000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-06T08:00:00</Start>
        <Finish>2027-01-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>90000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-07T08:00:00</Start>
        <Finish>2027-01-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>90000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-08T08:00:00</Start>
        <Finish>2027-01-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>112000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-11T08:00:00</Start>
        <Finish>2027-01-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>112000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-12T08:00:00</Start>
        <Finish>2027-01-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>112000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-13T08:00:00</Start>
        <Finish>2027-01-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>68000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-14T08:00:00</Start>
        <Finish>2027-01-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>68000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-15T08:00:00</Start>
        <Finish>2027-01-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>68000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-18T08:00:00</Start>
        <Finish>2027-01-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>91600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-19T08:00:00</Start>
        <Finish>2027-01-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>91600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-20T08:00:00</Start>
        <Finish>2027-01-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>91600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-21T08:00:00</Start>
        <Finish>2027-01-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>91600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-22T08:00:00</Start>
        <Finish>2027-01-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>91600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-01-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>101600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-26T08:00:00</Start>
        <Finish>2027-01-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>101600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-01-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>101600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-28T08:00:00</Start>
        <Finish>2027-01-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>101600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-29T08:00:00</Start>
        <Finish>2027-01-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>101600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-01T08:00:00</Start>
        <Finish>2027-02-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>101600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-02T08:00:00</Start>
        <Finish>2027-02-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>105600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-03T08:00:00</Start>
        <Finish>2027-02-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>105600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-04T08:00:00</Start>
        <Finish>2027-02-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>105600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-05T08:00:00</Start>
        <Finish>2027-02-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>105600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-08T08:00:00</Start>
        <Finish>2027-02-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>61600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-09T08:00:00</Start>
        <Finish>2027-02-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>61600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-10T08:00:00</Start>
        <Finish>2027-02-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>61600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>61600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-12T08:00:00</Start>
        <Finish>2027-02-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>109600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-15T08:00:00</Start>
        <Finish>2027-02-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>102800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-16T08:00:00</Start>
        <Finish>2027-02-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>102800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-17T08:00:00</Start>
        <Finish>2027-02-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>102800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-18T08:00:00</Start>
        <Finish>2027-02-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>102800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-19T08:00:00</Start>
        <Finish>2027-02-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>102800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-22T08:00:00</Start>
        <Finish>2027-02-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>150800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-23T08:00:00</Start>
        <Finish>2027-02-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>150800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-24T08:00:00</Start>
        <Finish>2027-02-25T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>150800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-25T08:00:00</Start>
        <Finish>2027-02-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>270800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-26T08:00:00</Start>
        <Finish>2027-02-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>270800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-01T08:00:00</Start>
        <Finish>2027-03-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>270800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-02T08:00:00</Start>
        <Finish>2027-03-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>270800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-03T08:00:00</Start>
        <Finish>2027-03-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>270800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-04T08:00:00</Start>
        <Finish>2027-03-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>270800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-05T08:00:00</Start>
        <Finish>2027-03-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>270800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-08T08:00:00</Start>
        <Finish>2027-03-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>270800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-09T08:00:00</Start>
        <Finish>2027-03-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>270800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-10T08:00:00</Start>
        <Finish>2027-03-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>270800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-11T08:00:00</Start>
        <Finish>2027-03-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>270800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-12T08:00:00</Start>
        <Finish>2027-03-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>270800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-15T08:00:00</Start>
        <Finish>2027-03-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>176000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-16T08:00:00</Start>
        <Finish>2027-03-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>176000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-17T08:00:00</Start>
        <Finish>2027-03-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>176000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-18T08:00:00</Start>
        <Finish>2027-03-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>176000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-19T08:00:00</Start>
        <Finish>2027-03-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>176000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-22T08:00:00</Start>
        <Finish>2027-03-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>160000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-23T08:00:00</Start>
        <Finish>2027-03-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>160000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-24T08:00:00</Start>
        <Finish>2027-03-25T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>160000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-25T08:00:00</Start>
        <Finish>2027-03-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>160000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-26T08:00:00</Start>
        <Finish>2027-03-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>160000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-29T08:00:00</Start>
        <Finish>2027-03-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>92800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-30T08:00:00</Start>
        <Finish>2027-03-31T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>92800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-31T08:00:00</Start>
        <Finish>2027-04-01T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>92800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-01T08:00:00</Start>
        <Finish>2027-04-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>92800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-02T08:00:00</Start>
        <Finish>2027-04-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>92800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-05T08:00:00</Start>
        <Finish>2027-04-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>92800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-06T08:00:00</Start>
        <Finish>2027-04-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>328800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-07T08:00:00</Start>
        <Finish>2027-04-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>328800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-08T08:00:00</Start>
        <Finish>2027-04-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>328800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-09T08:00:00</Start>
        <Finish>2027-04-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>328800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-12T08:00:00</Start>
        <Finish>2027-04-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>328800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-13T08:00:00</Start>
        <Finish>2027-04-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>328800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-14T08:00:00</Start>
        <Finish>2027-04-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>328800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-15T08:00:00</Start>
        <Finish>2027-04-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>352800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-16T08:00:00</Start>
        <Finish>2027-04-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>228800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-19T08:00:00</Start>
        <Finish>2027-04-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>228800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-20T08:00:00</Start>
        <Finish>2027-04-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>120000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-21T08:00:00</Start>
        <Finish>2027-04-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>120000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-22T08:00:00</Start>
        <Finish>2027-04-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>120000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-23T08:00:00</Start>
        <Finish>2027-04-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>120000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-26T08:00:00</Start>
        <Finish>2027-04-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>120000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-27T08:00:00</Start>
        <Finish>2027-04-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>120000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-28T08:00:00</Start>
        <Finish>2027-04-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>120000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-29T08:00:00</Start>
        <Finish>2027-04-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>80000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-30T08:00:00</Start>
        <Finish>2027-05-01T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>80000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-05-03T08:00:00</Start>
        <Finish>2027-05-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>80000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-05-04T08:00:00</Start>
        <Finish>2027-05-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>80000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-05-05T08:00:00</Start>
        <Finish>2027-05-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>80000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-05-06T08:00:00</Start>
        <Finish>2027-05-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>72000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-05-07T08:00:00</Start>
        <Finish>2027-05-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>144000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-05-10T08:00:00</Start>
        <Finish>2027-05-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>144000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-05-11T08:00:00</Start>
        <Finish>2027-05-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>144000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-05-12T08:00:00</Start>
        <Finish>2027-05-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>232000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-05-13T08:00:00</Start>
        <Finish>2027-05-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>232000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-05-14T08:00:00</Start>
        <Finish>2027-05-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>235200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-05-17T08:00:00</Start>
        <Finish>2027-05-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>235200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-05-18T08:00:00</Start>
        <Finish>2027-05-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>235200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-05-19T08:00:00</Start>
        <Finish>2027-05-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>235200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-05-20T08:00:00</Start>
        <Finish>2027-05-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>187200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-05-21T08:00:00</Start>
        <Finish>2027-05-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>192000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-05-24T08:00:00</Start>
        <Finish>2027-05-25T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>104000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-05-25T08:00:00</Start>
        <Finish>2027-05-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>104000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-05-26T08:00:00</Start>
        <Finish>2027-05-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>104000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-05-27T08:00:00</Start>
        <Finish>2027-05-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>104000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-05-28T08:00:00</Start>
        <Finish>2027-05-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>140000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-05-31T08:00:00</Start>
        <Finish>2027-06-01T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>140000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-06-01T08:00:00</Start>
        <Finish>2027-06-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>140000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-06-02T08:00:00</Start>
        <Finish>2027-06-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>140000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-06-03T08:00:00</Start>
        <Finish>2027-06-03T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>68000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>1</UID>
      <ID>1</ID>
      <Name>Preconstruction</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-04T08:00:00</Start>
      <Finish>2027-01-22T17:00:00</Finish>
      <Duration>PT120H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>100</PercentComplete>
      <Cost>1290000</Cost>
      <ActualCost>1290000</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-01-22T17:00:00</Finish>
        <Duration>PT120H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT180H0M0S</Work>
        <Cost>1290000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-01-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-05T08:00:00</Start>
        <Finish>2027-01-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-06T08:00:00</Start>
        <Finish>2027-01-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-07T08:00:00</Start>
        <Finish>2027-01-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-08T08:00:00</Start>
        <Finish>2027-01-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-11T08:00:00</Start>
        <Finish>2027-01-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-12T08:00:00</Start>
        <Finish>2027-01-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-13T08:00:00</Start>
        <Finish>2027-01-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-14T08:00:00</Start>
        <Finish>2027-01-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-15T08:00:00</Start>
        <Finish>2027-01-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-18T08:00:00</Start>
        <Finish>2027-01-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-19T08:00:00</Start>
        <Finish>2027-01-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-20T08:00:00</Start>
        <Finish>2027-01-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-21T08:00:00</Start>
        <Finish>2027-01-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-22T08:00:00</Start>
        <Finish>2027-01-22T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-01-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>90000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-05T08:00:00</Start>
        <Finish>2027-01-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>90000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-06T08:00:00</Start>
        <Finish>2027-01-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>90000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-07T08:00:00</Start>
        <Finish>2027-01-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>90000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-08T08:00:00</Start>
        <Finish>2027-01-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>112000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-11T08:00:00</Start>
        <Finish>2027-01-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>112000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-12T08:00:00</Start>
        <Finish>2027-01-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>112000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-13T08:00:00</Start>
        <Finish>2027-01-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>68000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-14T08:00:00</Start>
        <Finish>2027-01-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>68000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-15T08:00:00</Start>
        <Finish>2027-01-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>68000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-18T08:00:00</Start>
        <Finish>2027-01-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>78000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-19T08:00:00</Start>
        <Finish>2027-01-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>78000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-20T08:00:00</Start>
        <Finish>2027-01-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>78000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-21T08:00:00</Start>
        <Finish>2027-01-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>78000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-22T08:00:00</Start>
        <Finish>2027-01-22T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>78000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>2</UID>
      <ID>2</ID>
      <Name>Notice to proceed</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-04T08:00:00</Start>
      <Finish>2027-01-04T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>100</PercentComplete>
      <ActualStart>2027-01-04T08:00:00</ActualStart>
      <ActualFinish>2027-01-04T08:00:00</ActualFinish>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-01-04T08:00:00</Finish>
        <Duration>PT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
      </Baseline>
    </Task>
    <Task>
      <UID>3</UID>
      <ID>3</ID>
      <Name>Permits and surveys</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-04T08:00:00</Start>
      <Finish>2027-01-15T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>100</PercentComplete>
      <Cost>900000</Cost>
      <ActualCost>900000</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-01-15T17:00:00</Finish>
        <Duration>PT80H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT120H0M0S</Work>
        <Cost>900000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-01-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-05T08:00:00</Start>
        <Finish>2027-01-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-06T08:00:00</Start>
        <Finish>2027-01-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-07T08:00:00</Start>
        <Finish>2027-01-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-08T08:00:00</Start>
        <Finish>2027-01-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-11T08:00:00</Start>
        <Finish>2027-01-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-12T08:00:00</Start>
        <Finish>2027-01-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-13T08:00:00</Start>
        <Finish>2027-01-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-14T08:00:00</Start>
        <Finish>2027-01-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-15T08:00:00</Start>
        <Finish>2027-01-15T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-01-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>90000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-05T08:00:00</Start>
        <Finish>2027-01-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>90000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-06T08:00:00</Start>
        <Finish>2027-01-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>90000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-07T08:00:00</Start>
        <Finish>2027-01-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>90000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-08T08:00:00</Start>
        <Finish>2027-01-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>112000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-11T08:00:00</Start>
        <Finish>2027-01-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>112000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-12T08:00:00</Start>
        <Finish>2027-01-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>112000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-13T08:00:00</Start>
        <Finish>2027-01-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>68000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-14T08:00:00</Start>
        <Finish>2027-01-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>68000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-15T08:00:00</Start>
        <Finish>2027-01-15T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>68000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>4</UID>
      <ID>4</ID>
      <Name>Building permit and discharge of conditions</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.2.1</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-04T08:00:00</Start>
      <Finish>2027-01-15T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT80H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>100</PercentComplete>
      <PercentWorkComplete>100</PercentWorkComplete>
      <Cost>680000</Cost>
      <ActualStart>2027-01-04T08:00:00</ActualStart>
      <ActualFinish>2027-01-15T17:00:00</ActualFinish>
      <ActualCost>680000</ActualCost>
      <ActualWork>PT80H0M0S</ActualWork>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>2</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-01-15T17:00:00</Finish>
        <Duration>PT80H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT80H0M0S</Work>
        <Cost>680000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>4</UID>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-01-15T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT80H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>4</UID>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-01-15T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>680000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>5</UID>
      <ID>5</ID>
      <Name>Site survey and setting out</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.2.2</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-04T08:00:00</Start>
      <Finish>2027-01-07T17:00:00</Finish>
      <Duration>PT32H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT16H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>14400</TotalSlack>
      <PercentComplete>100</PercentComplete>
      <PercentWorkComplete>100</PercentWorkComplete>
      <Cost>88000</Cost>
      <ActualStart>2027-01-04T08:00:00</ActualStart>
      <ActualFinish>2027-01-07T17:00:00</ActualFinish>
      <ActualCost>88000</ActualCost>
      <ActualWork>PT16H0M0S</ActualWork>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>2</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-01-07T17:00:00</Finish>
        <Duration>PT32H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT16H0M0S</Work>
        <Cost>88000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>5</UID>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-01-07T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>5</UID>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-01-07T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>88000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>6</UID>
      <ID>6</ID>
      <Name>Utility search and trial holes</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.2.3</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-08T08:00:00</Start>
      <Finish>2027-01-12T17:00:00</Finish>
      <Duration>PT24H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT24H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>14400</TotalSlack>
      <PercentComplete>100</PercentComplete>
      <PercentWorkComplete>100</PercentWorkComplete>
      <Cost>132000</Cost>
      <ActualStart>2027-01-08T08:00:00</ActualStart>
      <ActualFinish>2027-01-12T17:00:00</ActualFinish>
      <ActualCost>132000</ActualCost>
      <ActualWork>PT24H0M0S</ActualWork>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>5</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-08T08:00:00</Start>
        <Finish>2027-01-12T17:00:00</Finish>
        <Duration>PT24H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT24H0M0S</Work>
        <Cost>132000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>6</UID>
        <Start>2027-01-08T08:00:00</Start>
        <Finish>2027-01-12T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>6</UID>
        <Start>2027-01-08T08:00:00</Start>
        <Finish>2027-01-12T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>132000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>7</UID>
      <ID>7</ID>
      <Name>Site set-up and hoarding</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-18T08:00:00</Start>
      <Finish>2027-01-22T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT60H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>100</PercentComplete>
      <PercentWorkComplete>100</PercentWorkComplete>
      <Cost>390000</Cost>
      <ActualStart>2027-01-18T08:00:00</ActualStart>
      <ActualFinish>2027-01-22T17:00:00</ActualFinish>
      <ActualCost>390000</ActualCost>
      <ActualWork>PT60H0M0S</ActualWork>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>4</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>6</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-18T08:00:00</Start>
        <Finish>2027-01-22T17:00:00</Finish>
        <Duration>PT40H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT60H0M0S</Work>
        <Cost>390000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-01-18T08:00:00</Start>
        <Finish>2027-01-22T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT60H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-01-18T08:00:00</Start>
        <Finish>2027-01-22T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>390000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>8</UID>
      <ID>8</ID>
      <Name>Substructure</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-25T08:00:00</Start>
      <Finish>2027-02-24T17:00:00</Finish>
      <Duration>PT184H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>100</PercentComplete>
      <Cost>2096000</Cost>
      <ActualCost>2096000</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-02-24T17:00:00</Finish>
        <Duration>PT184H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT360H0M0S</Work>
        <Cost>2096000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>8</UID>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-01-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>8</UID>
        <Start>2027-01-26T08:00:00</Start>
        <Finish>2027-01-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>8</UID>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-01-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>8</UID>
        <Start>2027-01-28T08:00:00</Start>
        <Finish>2027-01-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>8</UID>
        <Start>2027-01-29T08:00:00</Start>
        <Finish>2027-01-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>8</UID>
        <Start>2027-02-01T08:00:00</Start>
        <Finish>2027-02-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>8</UID>
        <Start>2027-02-02T08:00:00</Start>
        <Finish>2027-02-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>8</UID>
        <Start>2027-02-03T08:00:00</Start>
        <Finish>2027-02-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>8</UID>
        <Start>2027-02-04T08:00:00</Start>
        <Finish>2027-02-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>8</UID>
        <Start>2027-02-05T08:00:00</Start>
        <Finish>2027-02-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>8</UID>
        <Start>2027-02-08T08:00:00</Start>
        <Finish>2027-02-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>8</UID>
        <Start>2027-02-09T08:00:00</Start>
        <Finish>2027-02-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>8</UID>
        <Start>2027-02-10T08:00:00</Start>
        <Finish>2027-02-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>8</UID>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>8</UID>
        <Start>2027-02-12T08:00:00</Start>
        <Finish>2027-02-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>8</UID>
        <Start>2027-02-15T08:00:00</Start>
        <Finish>2027-02-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>8</UID>
        <Start>2027-02-16T08:00:00</Start>
        <Finish>2027-02-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>8</UID>
        <Start>2027-02-17T08:00:00</Start>
        <Finish>2027-02-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>8</UID>
        <Start>2027-02-18T08:00:00</Start>
        <Finish>2027-02-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>8</UID>
        <Start>2027-02-19T08:00:00</Start>
        <Finish>2027-02-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>8</UID>
        <Start>2027-02-22T08:00:00</Start>
        <Finish>2027-02-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>8</UID>
        <Start>2027-02-23T08:00:00</Start>
        <Finish>2027-02-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>8</UID>
        <Start>2027-02-24T08:00:00</Start>
        <Finish>2027-02-24T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>8</UID>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-01-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>8</UID>
        <Start>2027-01-26T08:00:00</Start>
        <Finish>2027-01-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>8</UID>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-01-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>8</UID>
        <Start>2027-01-28T08:00:00</Start>
        <Finish>2027-01-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>8</UID>
        <Start>2027-01-29T08:00:00</Start>
        <Finish>2027-01-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>8</UID>
        <Start>2027-02-01T08:00:00</Start>
        <Finish>2027-02-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>8</UID>
        <Start>2027-02-02T08:00:00</Start>
        <Finish>2027-02-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>92000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>8</UID>
        <Start>2027-02-03T08:00:00</Start>
        <Finish>2027-02-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>92000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>8</UID>
        <Start>2027-02-04T08:00:00</Start>
        <Finish>2027-02-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>92000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>8</UID>
        <Start>2027-02-05T08:00:00</Start>
        <Finish>2027-02-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>92000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>8</UID>
        <Start>2027-02-08T08:00:00</Start>
        <Finish>2027-02-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>48000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>8</UID>
        <Start>2027-02-09T08:00:00</Start>
        <Finish>2027-02-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>48000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>8</UID>
        <Start>2027-02-10T08:00:00</Start>
        <Finish>2027-02-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>48000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>8</UID>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>48000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>8</UID>
        <Start>2027-02-12T08:00:00</Start>
        <Finish>2027-02-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>96000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>8</UID>
        <Start>2027-02-15T08:00:00</Start>
        <Finish>2027-02-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>96000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>8</UID>
        <Start>2027-02-16T08:00:00</Start>
        <Finish>2027-02-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>96000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>8</UID>
        <Start>2027-02-17T08:00:00</Start>
        <Finish>2027-02-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>96000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>8</UID>
        <Start>2027-02-18T08:00:00</Start>
        <Finish>2027-02-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>96000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>8</UID>
        <Start>2027-02-19T08:00:00</Start>
        <Finish>2027-02-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>96000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>8</UID>
        <Start>2027-02-22T08:00:00</Start>
        <Finish>2027-02-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>144000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>8</UID>
        <Start>2027-02-23T08:00:00</Start>
        <Finish>2027-02-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>144000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>8</UID>
        <Start>2027-02-24T08:00:00</Start>
        <Finish>2027-02-24T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>144000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>9</UID>
      <ID>9</ID>
      <Name>Groundworks</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-25T08:00:00</Start>
      <Finish>2027-02-11T17:00:00</Finish>
      <Duration>PT112H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>100</PercentComplete>
      <Cost>1088000</Cost>
      <ActualCost>1088000</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-02-11T17:00:00</Finish>
        <Duration>PT112H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT192H0M0S</Work>
        <Cost>1088000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>9</UID>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-01-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>9</UID>
        <Start>2027-01-26T08:00:00</Start>
        <Finish>2027-01-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>9</UID>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-01-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>9</UID>
        <Start>2027-01-28T08:00:00</Start>
        <Finish>2027-01-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>9</UID>
        <Start>2027-01-29T08:00:00</Start>
        <Finish>2027-01-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>9</UID>
        <Start>2027-02-01T08:00:00</Start>
        <Finish>2027-02-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>9</UID>
        <Start>2027-02-02T08:00:00</Start>
        <Finish>2027-02-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>9</UID>
        <Start>2027-02-03T08:00:00</Start>
        <Finish>2027-02-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>9</UID>
        <Start>2027-02-04T08:00:00</Start>
        <Finish>2027-02-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>9</UID>
        <Start>2027-02-05T08:00:00</Start>
        <Finish>2027-02-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>9</UID>
        <Start>2027-02-08T08:00:00</Start>
        <Finish>2027-02-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>9</UID>
        <Start>2027-02-09T08:00:00</Start>
        <Finish>2027-02-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>9</UID>
        <Start>2027-02-10T08:00:00</Start>
        <Finish>2027-02-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>9</UID>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-11T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>9</UID>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-01-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>9</UID>
        <Start>2027-01-26T08:00:00</Start>
        <Finish>2027-01-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>9</UID>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-01-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>9</UID>
        <Start>2027-01-28T08:00:00</Start>
        <Finish>2027-01-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>9</UID>
        <Start>2027-01-29T08:00:00</Start>
        <Finish>2027-01-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>9</UID>
        <Start>2027-02-01T08:00:00</Start>
        <Finish>2027-02-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>9</UID>
        <Start>2027-02-02T08:00:00</Start>
        <Finish>2027-02-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>92000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>9</UID>
        <Start>2027-02-03T08:00:00</Start>
        <Finish>2027-02-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>92000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>9</UID>
        <Start>2027-02-04T08:00:00</Start>
        <Finish>2027-02-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>92000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>9</UID>
        <Start>2027-02-05T08:00:00</Start>
        <Finish>2027-02-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>92000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>9</UID>
        <Start>2027-02-08T08:00:00</Start>
        <Finish>2027-02-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>48000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>9</UID>
        <Start>2027-02-09T08:00:00</Start>
        <Finish>2027-02-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>48000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>9</UID>
        <Start>2027-02-10T08:00:00</Start>
        <Finish>2027-02-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>48000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>9</UID>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-11T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>48000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>10</UID>
      <ID>10</ID>
      <Name>Bulk excavation</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.1.1</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-25T08:00:00</Start>
      <Finish>2027-02-01T17:00:00</Finish>
      <Duration>PT48H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT96H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>100</PercentComplete>
      <PercentWorkComplete>100</PercentWorkComplete>
      <Cost>528000</Cost>
      <ActualStart>2027-01-25T08:00:00</ActualStart>
      <ActualFinish>2027-02-01T17:00:00</ActualFinish>
      <ActualCost>528000</ActualCost>
      <ActualWork>PT96H0M0S</ActualWork>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>7</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-02-01T17:00:00</Finish>
        <Duration>PT48H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT96H0M0S</Work>
        <Cost>528000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>10</UID>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-02-01T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT96H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>10</UID>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-02-01T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>528000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>11</UID>
      <ID>11</ID>
      <Name>Piling</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.1.2</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-02T08:00:00</Start>
      <Finish>2027-02-11T17:00:00</Finish>
      <Duration>PT64H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT64H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>100</PercentComplete>
      <PercentWorkComplete>100</PercentWorkComplete>
      <Cost>384000</Cost>
      <ActualStart>2027-02-02T08:00:00</ActualStart>
      <ActualFinish>2027-02-11T17:00:00</ActualFinish>
      <ActualCost>384000</ActualCost>
      <ActualWork>PT64H0M0S</ActualWork>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>10</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-02-02T08:00:00</Start>
        <Finish>2027-02-11T17:00:00</Finish>
        <Duration>PT64H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT64H0M0S</Work>
        <Cost>384000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-02-02T08:00:00</Start>
        <Finish>2027-02-11T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT64H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-02-02T08:00:00</Start>
        <Finish>2027-02-11T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>384000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>12</UID>
      <ID>12</ID>
      <Name>Below-ground drainage</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.1.3</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-02T08:00:00</Start>
      <Finish>2027-02-05T17:00:00</Finish>
      <Duration>PT32H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT32H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>48000</TotalSlack>
      <PercentComplete>100</PercentComplete>
      <PercentWorkComplete>100</PercentWorkComplete>
      <Cost>176000</Cost>
      <ActualStart>2027-02-02T08:00:00</ActualStart>
      <ActualFinish>2027-02-05T17:00:00</ActualFinish>
      <ActualCost>176000</ActualCost>
      <ActualWork>PT32H0M0S</ActualWork>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>10</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-02-02T08:00:00</Start>
        <Finish>2027-02-05T17:00:00</Finish>
        <Duration>PT32H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT32H0M0S</Work>
        <Cost>176000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>12</UID>
        <Start>2027-02-02T08:00:00</Start>
        <Finish>2027-02-05T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>12</UID>
        <Start>2027-02-02T08:00:00</Start>
        <Finish>2027-02-05T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>176000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>13</UID>
      <ID>13</ID>
      <Name>Foundations</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-12T08:00:00</Start>
      <Finish>2027-02-24T17:00:00</Finish>
      <Duration>PT72H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>100</PercentComplete>
      <Cost>1008000</Cost>
      <ActualCost>1008000</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-02-12T08:00:00</Start>
        <Finish>2027-02-24T17:00:00</Finish>
        <Duration>PT72H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT168H0M0S</Work>
        <Cost>1008000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>13</UID>
        <Start>2027-02-12T08:00:00</Start>
        <Finish>2027-02-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>13</UID>
        <Start>2027-02-15T08:00:00</Start>
        <Finish>2027-02-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>13</UID>
        <Start>2027-02-16T08:00:00</Start>
        <Finish>2027-02-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>13</UID>
        <Start>2027-02-17T08:00:00</Start>
        <Finish>2027-02-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>13</UID>
        <Start>2027-02-18T08:00:00</Start>
        <Finish>2027-02-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>13</UID>
        <Start>2027-02-19T08:00:00</Start>
        <Finish>2027-02-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>13</UID>
        <Start>2027-02-22T08:00:00</Start>
        <Finish>2027-02-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>13</UID>
        <Start>2027-02-23T08:00:00</Start>
        <Finish>2027-02-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>13</UID>
        <Start>2027-02-24T08:00:00</Start>
        <Finish>2027-02-24T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>13</UID>
        <Start>2027-02-12T08:00:00</Start>
        <Finish>2027-02-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>96000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>13</UID>
        <Start>2027-02-15T08:00:00</Start>
        <Finish>2027-02-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>96000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>13</UID>
        <Start>2027-02-16T08:00:00</Start>
        <Finish>2027-02-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>96000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>13</UID>
        <Start>2027-02-17T08:00:00</Start>
        <Finish>2027-02-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>96000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>13</UID>
        <Start>2027-02-18T08:00:00</Start>
        <Finish>2027-02-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>96000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>13</UID>
        <Start>2027-02-19T08:00:00</Start>
        <Finish>2027-02-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>96000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>13</UID>
        <Start>2027-02-22T08:00:00</Start>
        <Finish>2027-02-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>144000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>13</UID>
        <Start>2027-02-23T08:00:00</Start>
        <Finish>2027-02-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>144000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>13</UID>
        <Start>2027-02-24T08:00:00</Start>
        <Finish>2027-02-24T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>144000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>14</UID>
      <ID>14</ID>
      <Name>Pile caps and ground beams</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.2.1</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-12T08:00:00</Start>
      <Finish>2027-02-19T17:00:00</Finish>
      <Duration>PT48H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT96H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>100</PercentComplete>
      <PercentWorkComplete>100</PercentWorkComplete>
      <Cost>576000</Cost>
      <ActualStart>2027-02-12T08:00:00</ActualStart>
      <ActualFinish>2027-02-19T17:00:00</ActualFinish>
      <ActualCost>576000</ActualCost>
      <ActualWork>PT96H0M0S</ActualWork>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>11</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-02-12T08:00:00</Start>
        <Finish>2027-02-19T17:00:00</Finish>
        <Duration>PT48H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT96H0M0S</Work>
        <Cost>576000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>14</UID>
        <Start>2027-02-12T08:00:00</Start>
        <Finish>2027-02-19T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT96H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>14</UID>
        <Start>2027-02-12T08:00:00</Start>
        <Finish>2027-02-19T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>576000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>15</UID>
      <ID>15</ID>
      <Name>Ground floor slab</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.2.2</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-22T08:00:00</Start>
      <Finish>2027-02-24T17:00:00</Finish>
      <Duration>PT24H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT72H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>100</PercentComplete>
      <PercentWorkComplete>100</PercentWorkComplete>
      <Cost>432000</Cost>
      <ActualStart>2027-02-22T08:00:00</ActualStart>
      <ActualFinish>2027-02-24T17:00:00</ActualFinish>
      <ActualCost>432000</ActualCost>
      <ActualWork>PT72H0M0S</ActualWork>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>14</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>12</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-02-22T08:00:00</Start>
        <Finish>2027-02-24T17:00:00</Finish>
        <Duration>PT24H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT72H0M0S</Work>
        <Cost>432000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>15</UID>
        <Start>2027-02-22T08:00:00</Start>
        <Finish>2027-02-24T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT72H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>15</UID>
        <Start>2027-02-22T08:00:00</Start>
        <Finish>2027-02-24T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>432000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>16</UID>
      <ID>16</ID>
      <Name>Substructure complete</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-24T17:00:00</Start>
      <Finish>2027-02-24T17:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>100</PercentComplete>
      <ActualStart>2027-02-24T17:00:00</ActualStart>
      <ActualFinish>2027-02-24T17:00:00</ActualFinish>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>15</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-02-24T17:00:00</Start>
        <Finish>2027-02-24T17:00:00</Finish>
        <Duration>PT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
      </Baseline>
    </Task>
    <Task>
      <UID>17</UID>
      <ID>17</ID>
      <Name>Superstructure</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-25T08:00:00</Start>
      <Finish>2027-04-05T17:00:00</Finish>
      <Duration>PT224H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>21</PercentComplete>
      <Cost>5404800</Cost>
      <ActualCost>2122567</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-02-25T08:00:00</Start>
        <Finish>2027-04-05T17:00:00</Finish>
        <Duration>PT224H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT800H0M0S</Work>
        <Cost>5404800</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>17</UID>
        <Start>2027-02-25T08:00:00</Start>
        <Finish>2027-02-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>17</UID>
        <Start>2027-02-26T08:00:00</Start>
        <Finish>2027-02-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>17</UID>
        <Start>2027-03-01T08:00:00</Start>
        <Finish>2027-03-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>17</UID>
        <Start>2027-03-02T08:00:00</Start>
        <Finish>2027-03-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>17</UID>
        <Start>2027-03-03T08:00:00</Start>
        <Finish>2027-03-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>17</UID>
        <Start>2027-03-04T08:00:00</Start>
        <Finish>2027-03-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>17</UID>
        <Start>2027-03-05T08:00:00</Start>
        <Finish>2027-03-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>17</UID>
        <Start>2027-03-08T08:00:00</Start>
        <Finish>2027-03-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>17</UID>
        <Start>2027-03-09T08:00:00</Start>
        <Finish>2027-03-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>17</UID>
        <Start>2027-03-10T08:00:00</Start>
        <Finish>2027-03-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>17</UID>
        <Start>2027-03-11T08:00:00</Start>
        <Finish>2027-03-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>17</UID>
        <Start>2027-03-12T08:00:00</Start>
        <Finish>2027-03-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>17</UID>
        <Start>2027-03-15T08:00:00</Start>
        <Finish>2027-03-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>17</UID>
        <Start>2027-03-16T08:00:00</Start>
        <Finish>2027-03-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>17</UID>
        <Start>2027-03-17T08:00:00</Start>
        <Finish>2027-03-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>17</UID>
        <Start>2027-03-18T08:00:00</Start>
        <Finish>2027-03-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>17</UID>
        <Start>2027-03-19T08:00:00</Start>
        <Finish>2027-03-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>17</UID>
        <Start>2027-03-22T08:00:00</Start>
        <Finish>2027-03-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>17</UID>
        <Start>2027-03-23T08:00:00</Start>
        <Finish>2027-03-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>17</UID>
        <Start>2027-03-24T08:00:00</Start>
        <Finish>2027-03-25T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>17</UID>
        <Start>2027-03-25T08:00:00</Start>
        <Finish>2027-03-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>17</UID>
        <Start>2027-03-26T08:00:00</Start>
        <Finish>2027-03-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>17</UID>
        <Start>2027-03-29T08:00:00</Start>
        <Finish>2027-03-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>17</UID>
        <Start>2027-03-30T08:00:00</Start>
        <Finish>2027-03-31T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>17</UID>
        <Start>2027-03-31T08:00:00</Start>
        <Finish>2027-04-01T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>17</UID>
        <Start>2027-04-01T08:00:00</Start>
        <Finish>2027-04-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>17</UID>
        <Start>2027-04-02T08:00:00</Start>
        <Finish>2027-04-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>17</UID>
        <Start>2027-04-05T08:00:00</Start>
        <Finish>2027-04-05T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>17</UID>
        <Start>2027-02-25T08:00:00</Start>
        <Finish>2027-02-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>264000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>17</UID>
        <Start>2027-02-26T08:00:00</Start>
        <Finish>2027-02-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>264000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>17</UID>
        <Start>2027-03-01T08:00:00</Start>
        <Finish>2027-03-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>264000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>17</UID>
        <Start>2027-03-02T08:00:00</Start>
        <Finish>2027-03-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>264000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>17</UID>
        <Start>2027-03-03T08:00:00</Start>
        <Finish>2027-03-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>264000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>17</UID>
        <Start>2027-03-04T08:00:00</Start>
        <Finish>2027-03-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>264000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>17</UID>
        <Start>2027-03-05T08:00:00</Start>
        <Finish>2027-03-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>264000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>17</UID>
        <Start>2027-03-08T08:00:00</Start>
        <Finish>2027-03-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>264000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>17</UID>
        <Start>2027-03-09T08:00:00</Start>
        <Finish>2027-03-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>264000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>17</UID>
        <Start>2027-03-10T08:00:00</Start>
        <Finish>2027-03-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>264000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>17</UID>
        <Start>2027-03-11T08:00:00</Start>
        <Finish>2027-03-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>264000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>17</UID>
        <Start>2027-03-12T08:00:00</Start>
        <Finish>2027-03-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>264000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>17</UID>
        <Start>2027-03-15T08:00:00</Start>
        <Finish>2027-03-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>176000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>17</UID>
        <Start>2027-03-16T08:00:00</Start>
        <Finish>2027-03-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>176000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>17</UID>
        <Start>2027-03-17T08:00:00</Start>
        <Finish>2027-03-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>176000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>17</UID>
        <Start>2027-03-18T08:00:00</Start>
        <Finish>2027-03-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>176000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>17</UID>
        <Start>2027-03-19T08:00:00</Start>
        <Finish>2027-03-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>176000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>17</UID>
        <Start>2027-03-22T08:00:00</Start>
        <Finish>2027-03-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>160000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>17</UID>
        <Start>2027-03-23T08:00:00</Start>
        <Finish>2027-03-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>160000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>17</UID>
        <Start>2027-03-24T08:00:00</Start>
        <Finish>2027-03-25T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>160000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>17</UID>
        <Start>2027-03-25T08:00:00</Start>
        <Finish>2027-03-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>160000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>17</UID>
        <Start>2027-03-26T08:00:00</Start>
        <Finish>2027-03-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>160000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>17</UID>
        <Start>2027-03-29T08:00:00</Start>
        <Finish>2027-03-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>92800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>17</UID>
        <Start>2027-03-30T08:00:00</Start>
        <Finish>2027-03-31T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>92800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>17</UID>
        <Start>2027-03-31T08:00:00</Start>
        <Finish>2027-04-01T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>92800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>17</UID>
        <Start>2027-04-01T08:00:00</Start>
        <Finish>2027-04-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>92800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>17</UID>
        <Start>2027-04-02T08:00:00</Start>
        <Finish>2027-04-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>92800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>17</UID>
        <Start>2027-04-05T08:00:00</Start>
        <Finish>2027-04-05T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>92800</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>18</UID>
      <ID>18</ID>
      <Name>Steel frame</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-25T08:00:00</Start>
      <Finish>2027-03-19T17:00:00</Finish>
      <Duration>PT136H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>47</PercentComplete>
      <Cost>3648000</Cost>
      <ActualCost>2122567</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-02-25T08:00:00</Start>
        <Finish>2027-03-19T17:00:00</Finish>
        <Duration>PT136H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT464H0M0S</Work>
        <Cost>3648000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-02-25T08:00:00</Start>
        <Finish>2027-02-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-02-26T08:00:00</Start>
        <Finish>2027-02-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-03-01T08:00:00</Start>
        <Finish>2027-03-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-03-02T08:00:00</Start>
        <Finish>2027-03-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-03-03T08:00:00</Start>
        <Finish>2027-03-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-03-04T08:00:00</Start>
        <Finish>2027-03-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-03-05T08:00:00</Start>
        <Finish>2027-03-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-03-08T08:00:00</Start>
        <Finish>2027-03-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-03-09T08:00:00</Start>
        <Finish>2027-03-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-03-10T08:00:00</Start>
        <Finish>2027-03-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-03-11T08:00:00</Start>
        <Finish>2027-03-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-03-12T08:00:00</Start>
        <Finish>2027-03-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-03-15T08:00:00</Start>
        <Finish>2027-03-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-03-16T08:00:00</Start>
        <Finish>2027-03-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-03-17T08:00:00</Start>
        <Finish>2027-03-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-03-18T08:00:00</Start>
        <Finish>2027-03-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-03-19T08:00:00</Start>
        <Finish>2027-03-19T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-02-25T08:00:00</Start>
        <Finish>2027-02-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>264000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-02-26T08:00:00</Start>
        <Finish>2027-02-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>264000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-03-01T08:00:00</Start>
        <Finish>2027-03-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>264000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-03-02T08:00:00</Start>
        <Finish>2027-03-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>264000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-03-03T08:00:00</Start>
        <Finish>2027-03-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>264000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-03-04T08:00:00</Start>
        <Finish>2027-03-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>264000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-03-05T08:00:00</Start>
        <Finish>2027-03-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>264000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-03-08T08:00:00</Start>
        <Finish>2027-03-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>264000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-03-09T08:00:00</Start>
        <Finish>2027-03-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>264000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-03-10T08:00:00</Start>
        <Finish>2027-03-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>264000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-03-11T08:00:00</Start>
        <Finish>2027-03-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>264000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-03-12T08:00:00</Start>
        <Finish>2027-03-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>264000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-03-15T08:00:00</Start>
        <Finish>2027-03-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>96000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-03-16T08:00:00</Start>
        <Finish>2027-03-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>96000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-03-17T08:00:00</Start>
        <Finish>2027-03-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>96000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-03-18T08:00:00</Start>
        <Finish>2027-03-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>96000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-03-19T08:00:00</Start>
        <Finish>2027-03-19T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>96000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>19</UID>
      <ID>19</ID>
      <Name>Erect steel frame, level 1</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.1.1</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-25T08:00:00</Start>
      <Finish>2027-03-04T17:00:00</Finish>
      <Duration>PT48H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT192H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>100</PercentComplete>
      <PercentWorkComplete>100</PercentWorkComplete>
      <Cost>1584000</Cost>
      <ActualStart>2027-02-25T08:00:00</ActualStart>
      <ActualFinish>2027-03-04T17:00:00</ActualFinish>
      <ActualCost>1584000</ActualCost>
      <ActualWork>PT192H0M0S</ActualWork>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>16</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-02-25T08:00:00</Start>
        <Finish>2027-03-04T17:00:00</Finish>
        <Duration>PT48H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT192H0M0S</Work>
        <Cost>1584000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>19</UID>
        <Start>2027-02-25T08:00:00</Start>
        <Finish>2027-03-04T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT192H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>19</UID>
        <Start>2027-02-25T08:00:00</Start>
        <Finish>2027-03-04T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>1584000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>20</UID>
      <ID>20</ID>
      <Name>Erect steel frame, level 2 and roof</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.1.2</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-05T08:00:00</Start>
      <Finish>2027-03-12T17:00:00</Finish>
      <Duration>PT48H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT192H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>34</PercentComplete>
      <PercentWorkComplete>34</PercentWorkComplete>
      <Cost>1584000</Cost>
      <ActualStart>2027-03-05T08:00:00</ActualStart>
      <ActualCost>538567</ActualCost>
      <ActualWork>PT65H17M0S</ActualWork>
      <RemainingWork>PT126H43M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>19</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-03-05T08:00:00</Start>
        <Finish>2027-03-12T17:00:00</Finish>
        <Duration>PT48H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT192H0M0S</Work>
        <Cost>1584000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>20</UID>
        <Start>2027-03-05T08:00:00</Start>
        <Finish>2027-03-12T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT192H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>20</UID>
        <Start>2027-03-05T08:00:00</Start>
        <Finish>2027-03-12T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>1584000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>21</UID>
      <ID>21</ID>
      <Name>Metal decking and floor topping</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.1.3</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-15T08:00:00</Start>
      <Finish>2027-03-19T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT80H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>28800</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>480000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT80H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>20</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-03-15T08:00:00</Start>
        <Finish>2027-03-19T17:00:00</Finish>
        <Duration>PT40H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT80H0M0S</Work>
        <Cost>480000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>21</UID>
        <Start>2027-03-15T08:00:00</Start>
        <Finish>2027-03-19T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT80H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>21</UID>
        <Start>2027-03-15T08:00:00</Start>
        <Finish>2027-03-19T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>480000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>22</UID>
      <ID>22</ID>
      <Name>Envelope</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-15T08:00:00</Start>
      <Finish>2027-04-05T17:00:00</Finish>
      <Duration>PT128H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <Cost>1756800</Cost>
      <ActualCost>0</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-03-15T08:00:00</Start>
        <Finish>2027-04-05T17:00:00</Finish>
        <Duration>PT128H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT336H0M0S</Work>
        <Cost>1756800</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>22</UID>
        <Start>2027-03-15T08:00:00</Start>
        <Finish>2027-03-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>22</UID>
        <Start>2027-03-16T08:00:00</Start>
        <Finish>2027-03-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>22</UID>
        <Start>2027-03-17T08:00:00</Start>
        <Finish>2027-03-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>22</UID>
        <Start>2027-03-18T08:00:00</Start>
        <Finish>2027-03-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>22</UID>
        <Start>2027-03-19T08:00:00</Start>
        <Finish>2027-03-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>22</UID>
        <Start>2027-03-22T08:00:00</Start>
        <Finish>2027-03-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>22</UID>
        <Start>2027-03-23T08:00:00</Start>
        <Finish>2027-03-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>22</UID>
        <Start>2027-03-24T08:00:00</Start>
        <Finish>2027-03-25T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>22</UID>
        <Start>2027-03-25T08:00:00</Start>
        <Finish>2027-03-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>22</UID>
        <Start>2027-03-26T08:00:00</Start>
        <Finish>2027-03-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>22</UID>
        <Start>2027-03-29T08:00:00</Start>
        <Finish>2027-03-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>22</UID>
        <Start>2027-03-30T08:00:00</Start>
        <Finish>2027-03-31T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>22</UID>
        <Start>2027-03-31T08:00:00</Start>
        <Finish>2027-04-01T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>22</UID>
        <Start>2027-04-01T08:00:00</Start>
        <Finish>2027-04-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>22</UID>
        <Start>2027-04-02T08:00:00</Start>
        <Finish>2027-04-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>22</UID>
        <Start>2027-04-05T08:00:00</Start>
        <Finish>2027-04-05T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>22</UID>
        <Start>2027-03-15T08:00:00</Start>
        <Finish>2027-03-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>80000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>22</UID>
        <Start>2027-03-16T08:00:00</Start>
        <Finish>2027-03-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>80000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>22</UID>
        <Start>2027-03-17T08:00:00</Start>
        <Finish>2027-03-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>80000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>22</UID>
        <Start>2027-03-18T08:00:00</Start>
        <Finish>2027-03-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>80000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>22</UID>
        <Start>2027-03-19T08:00:00</Start>
        <Finish>2027-03-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>80000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>22</UID>
        <Start>2027-03-22T08:00:00</Start>
        <Finish>2027-03-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>160000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>22</UID>
        <Start>2027-03-23T08:00:00</Start>
        <Finish>2027-03-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>160000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>22</UID>
        <Start>2027-03-24T08:00:00</Start>
        <Finish>2027-03-25T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>160000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>22</UID>
        <Start>2027-03-25T08:00:00</Start>
        <Finish>2027-03-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>160000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>22</UID>
        <Start>2027-03-26T08:00:00</Start>
        <Finish>2027-03-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>160000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>22</UID>
        <Start>2027-03-29T08:00:00</Start>
        <Finish>2027-03-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>92800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>22</UID>
        <Start>2027-03-30T08:00:00</Start>
        <Finish>2027-03-31T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>92800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>22</UID>
        <Start>2027-03-31T08:00:00</Start>
        <Finish>2027-04-01T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>92800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>22</UID>
        <Start>2027-04-01T08:00:00</Start>
        <Finish>2027-04-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>92800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>22</UID>
        <Start>2027-04-02T08:00:00</Start>
        <Finish>2027-04-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>92800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>22</UID>
        <Start>2027-04-05T08:00:00</Start>
        <Finish>2027-04-05T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>92800</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>23</UID>
      <ID>23</ID>
      <Name>Roof deck and membrane</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.2.1</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-22T08:00:00</Start>
      <Finish>2027-03-26T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT80H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>28800</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>400000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT80H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>21</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-03-22T08:00:00</Start>
        <Finish>2027-03-26T17:00:00</Finish>
        <Duration>PT40H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT80H0M0S</Work>
        <Cost>400000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>23</UID>
        <Start>2027-03-22T08:00:00</Start>
        <Finish>2027-03-26T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT80H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>23</UID>
        <Start>2027-03-22T08:00:00</Start>
        <Finish>2027-03-26T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>400000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>24</UID>
      <ID>24</ID>
      <Name>External cladding</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.2.2</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-15T08:00:00</Start>
      <Finish>2027-03-26T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT160H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>800000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT160H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>20</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <ExtendedAttribute>
        <FieldID>188743783</FieldID>
        <Value>PT68H0M0S</Value>
      </ExtendedAttribute>
      <ExtendedAttribute>
        <FieldID>188743785</FieldID>
        <Value>PT112H0M0S</Value>
      </ExtendedAttribute>
      <Baseline>
        <Number>0</Number>
        <Start>2027-03-15T08:00:00</Start>
        <Finish>2027-03-26T17:00:00</Finish>
        <Duration>PT80H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT160H0M0S</Work>
        <Cost>800000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>24</UID>
        <Start>2027-03-15T08:00:00</Start>
        <Finish>2027-03-26T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT160H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>24</UID>
        <Start>2027-03-15T08:00:00</Start>
        <Finish>2027-03-26T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>800000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>25</UID>
      <ID>25</ID>
      <Name>Windows and curtain walling</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.2.3</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-29T08:00:00</Start>
      <Finish>2027-04-05T17:00:00</Finish>
      <Duration>PT48H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT96H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>556800</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT96H0M0S</RemainingWork>
      <ConstraintType>2</ConstraintType>
      <ConstraintDate>2027-03-29T08:00:00</ConstraintDate>
      <PredecessorLink>
        <PredecessorUID>24</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <ExtendedAttribute>
        <FieldID>188743783</FieldID>
        <Value>PT40H0M0S</Value>
      </ExtendedAttribute>
      <ExtendedAttribute>
        <FieldID>188743785</FieldID>
        <Value>PT68H0M0S</Value>
      </ExtendedAttribute>
      <Baseline>
        <Number>0</Number>
        <Start>2027-03-29T08:00:00</Start>
        <Finish>2027-04-05T17:00:00</Finish>
        <Duration>PT48H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT96H0M0S</Work>
        <Cost>556800</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>25</UID>
        <Start>2027-03-29T08:00:00</Start>
        <Finish>2027-04-05T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT96H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>25</UID>
        <Start>2027-03-29T08:00:00</Start>
        <Finish>2027-04-05T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>556800</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>26</UID>
      <ID>26</ID>
      <Name>Building watertight</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-05T17:00:00</Start>
      <Finish>2027-04-05T17:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>23</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>25</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-04-05T17:00:00</Start>
        <Finish>2027-04-05T17:00:00</Finish>
        <Duration>PT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
      </Baseline>
    </Task>
    <Task>
      <UID>27</UID>
      <ID>27</ID>
      <Name>Services and fit-out</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-18T08:00:00</Start>
      <Finish>2027-05-20T17:00:00</Finish>
      <Duration>PT712H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>43</PercentComplete>
      <Cost>6860400</Cost>
      <ActualCost>885650</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-18T08:00:00</Start>
        <Finish>2027-05-20T17:00:00</Finish>
        <Duration>PT712H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT1088H0M0S</Work>
        <Cost>6240000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-01-18T08:00:00</Start>
        <Finish>2027-01-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-01-19T08:00:00</Start>
        <Finish>2027-01-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-01-20T08:00:00</Start>
        <Finish>2027-01-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-01-21T08:00:00</Start>
        <Finish>2027-01-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-01-22T08:00:00</Start>
        <Finish>2027-01-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-01-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-01-26T08:00:00</Start>
        <Finish>2027-01-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-01-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-01-28T08:00:00</Start>
        <Finish>2027-01-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-01-29T08:00:00</Start>
        <Finish>2027-01-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-02-01T08:00:00</Start>
        <Finish>2027-02-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-02-02T08:00:00</Start>
        <Finish>2027-02-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-02-03T08:00:00</Start>
        <Finish>2027-02-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-02-04T08:00:00</Start>
        <Finish>2027-02-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-02-05T08:00:00</Start>
        <Finish>2027-02-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-02-08T08:00:00</Start>
        <Finish>2027-02-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-02-09T08:00:00</Start>
        <Finish>2027-02-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-02-10T08:00:00</Start>
        <Finish>2027-02-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-02-12T08:00:00</Start>
        <Finish>2027-02-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-02-15T08:00:00</Start>
        <Finish>2027-02-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT0H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-02-16T08:00:00</Start>
        <Finish>2027-02-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT0H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-02-17T08:00:00</Start>
        <Finish>2027-02-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT0H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-02-18T08:00:00</Start>
        <Finish>2027-02-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT0H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-02-19T08:00:00</Start>
        <Finish>2027-02-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT0H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-02-22T08:00:00</Start>
        <Finish>2027-02-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT0H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-02-23T08:00:00</Start>
        <Finish>2027-02-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT0H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-02-24T08:00:00</Start>
        <Finish>2027-02-25T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT0H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-02-25T08:00:00</Start>
        <Finish>2027-02-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT0H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-02-26T08:00:00</Start>
        <Finish>2027-02-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT0H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-03-01T08:00:00</Start>
        <Finish>2027-03-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT0H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-03-02T08:00:00</Start>
        <Finish>2027-03-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT0H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-03-03T08:00:00</Start>
        <Finish>2027-03-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT0H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-03-04T08:00:00</Start>
        <Finish>2027-03-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT0H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-03-05T08:00:00</Start>
        <Finish>2027-03-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT0H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-03-08T08:00:00</Start>
        <Finish>2027-03-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT0H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-03-09T08:00:00</Start>
        <Finish>2027-03-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT0H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-03-10T08:00:00</Start>
        <Finish>2027-03-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT0H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-03-11T08:00:00</Start>
        <Finish>2027-03-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT0H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-03-12T08:00:00</Start>
        <Finish>2027-03-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT0H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-04-06T08:00:00</Start>
        <Finish>2027-04-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT52H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-04-07T08:00:00</Start>
        <Finish>2027-04-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT52H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-04-08T08:00:00</Start>
        <Finish>2027-04-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT52H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-04-09T08:00:00</Start>
        <Finish>2027-04-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT52H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-04-12T08:00:00</Start>
        <Finish>2027-04-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT52H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-04-13T08:00:00</Start>
        <Finish>2027-04-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT52H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-04-14T08:00:00</Start>
        <Finish>2027-04-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT52H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-04-15T08:00:00</Start>
        <Finish>2027-04-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT60H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-04-16T08:00:00</Start>
        <Finish>2027-04-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT40H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-04-19T08:00:00</Start>
        <Finish>2027-04-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT40H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-04-20T08:00:00</Start>
        <Finish>2027-04-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-04-21T08:00:00</Start>
        <Finish>2027-04-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-04-22T08:00:00</Start>
        <Finish>2027-04-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-04-23T08:00:00</Start>
        <Finish>2027-04-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-04-26T08:00:00</Start>
        <Finish>2027-04-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-04-27T08:00:00</Start>
        <Finish>2027-04-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-04-28T08:00:00</Start>
        <Finish>2027-04-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-04-29T08:00:00</Start>
        <Finish>2027-04-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-04-30T08:00:00</Start>
        <Finish>2027-05-01T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-05-03T08:00:00</Start>
        <Finish>2027-05-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-05-04T08:00:00</Start>
        <Finish>2027-05-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-05-05T08:00:00</Start>
        <Finish>2027-05-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-05-06T08:00:00</Start>
        <Finish>2027-05-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-05-07T08:00:00</Start>
        <Finish>2027-05-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-05-10T08:00:00</Start>
        <Finish>2027-05-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-05-11T08:00:00</Start>
        <Finish>2027-05-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-05-12T08:00:00</Start>
        <Finish>2027-05-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-05-13T08:00:00</Start>
        <Finish>2027-05-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-05-14T08:00:00</Start>
        <Finish>2027-05-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-05-17T08:00:00</Start>
        <Finish>2027-05-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-05-18T08:00:00</Start>
        <Finish>2027-05-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-05-19T08:00:00</Start>
        <Finish>2027-05-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-05-20T08:00:00</Start>
        <Finish>2027-05-20T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-01-18T08:00:00</Start>
        <Finish>2027-01-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>13600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-01-19T08:00:00</Start>
        <Finish>2027-01-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>13600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-01-20T08:00:00</Start>
        <Finish>2027-01-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>13600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-01-21T08:00:00</Start>
        <Finish>2027-01-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>13600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-01-22T08:00:00</Start>
        <Finish>2027-01-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>13600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-01-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>13600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-01-26T08:00:00</Start>
        <Finish>2027-01-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>13600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-01-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>13600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-01-28T08:00:00</Start>
        <Finish>2027-01-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>13600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-01-29T08:00:00</Start>
        <Finish>2027-01-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>13600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-02-01T08:00:00</Start>
        <Finish>2027-02-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>13600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-02-02T08:00:00</Start>
        <Finish>2027-02-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>13600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-02-03T08:00:00</Start>
        <Finish>2027-02-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>13600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-02-04T08:00:00</Start>
        <Finish>2027-02-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>13600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-02-05T08:00:00</Start>
        <Finish>2027-02-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>13600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-02-08T08:00:00</Start>
        <Finish>2027-02-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>13600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-02-09T08:00:00</Start>
        <Finish>2027-02-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>13600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-02-10T08:00:00</Start>
        <Finish>2027-02-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>13600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>13600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-02-12T08:00:00</Start>
        <Finish>2027-02-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>13600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-02-15T08:00:00</Start>
        <Finish>2027-02-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>6800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-02-16T08:00:00</Start>
        <Finish>2027-02-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>6800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-02-17T08:00:00</Start>
        <Finish>2027-02-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>6800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-02-18T08:00:00</Start>
        <Finish>2027-02-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>6800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-02-19T08:00:00</Start>
        <Finish>2027-02-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>6800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-02-22T08:00:00</Start>
        <Finish>2027-02-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>6800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-02-23T08:00:00</Start>
        <Finish>2027-02-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>6800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-02-24T08:00:00</Start>
        <Finish>2027-02-25T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>6800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-02-25T08:00:00</Start>
        <Finish>2027-02-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>6800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-02-26T08:00:00</Start>
        <Finish>2027-02-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>6800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-03-01T08:00:00</Start>
        <Finish>2027-03-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>6800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-03-02T08:00:00</Start>
        <Finish>2027-03-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>6800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-03-03T08:00:00</Start>
        <Finish>2027-03-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>6800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-03-04T08:00:00</Start>
        <Finish>2027-03-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>6800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-03-05T08:00:00</Start>
        <Finish>2027-03-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>6800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-03-08T08:00:00</Start>
        <Finish>2027-03-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>6800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-03-09T08:00:00</Start>
        <Finish>2027-03-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>6800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-03-10T08:00:00</Start>
        <Finish>2027-03-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>6800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-03-11T08:00:00</Start>
        <Finish>2027-03-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>6800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-03-12T08:00:00</Start>
        <Finish>2027-03-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>6800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-04-06T08:00:00</Start>
        <Finish>2027-04-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>328800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-04-07T08:00:00</Start>
        <Finish>2027-04-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>328800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-04-08T08:00:00</Start>
        <Finish>2027-04-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>328800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-04-09T08:00:00</Start>
        <Finish>2027-04-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>328800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-04-12T08:00:00</Start>
        <Finish>2027-04-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>328800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-04-13T08:00:00</Start>
        <Finish>2027-04-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>328800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-04-14T08:00:00</Start>
        <Finish>2027-04-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>328800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-04-15T08:00:00</Start>
        <Finish>2027-04-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>352800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-04-16T08:00:00</Start>
        <Finish>2027-04-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>228800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-04-19T08:00:00</Start>
        <Finish>2027-04-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>228800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-04-20T08:00:00</Start>
        <Finish>2027-04-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>120000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-04-21T08:00:00</Start>
        <Finish>2027-04-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>120000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-04-22T08:00:00</Start>
        <Finish>2027-04-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>120000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-04-23T08:00:00</Start>
        <Finish>2027-04-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>120000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-04-26T08:00:00</Start>
        <Finish>2027-04-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>120000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-04-27T08:00:00</Start>
        <Finish>2027-04-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>120000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-04-28T08:00:00</Start>
        <Finish>2027-04-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>120000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-04-29T08:00:00</Start>
        <Finish>2027-04-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>80000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-04-30T08:00:00</Start>
        <Finish>2027-05-01T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>80000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-05-03T08:00:00</Start>
        <Finish>2027-05-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>80000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-05-04T08:00:00</Start>
        <Finish>2027-05-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>80000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-05-05T08:00:00</Start>
        <Finish>2027-05-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>80000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-05-06T08:00:00</Start>
        <Finish>2027-05-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>72000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-05-07T08:00:00</Start>
        <Finish>2027-05-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>144000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-05-10T08:00:00</Start>
        <Finish>2027-05-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>144000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-05-11T08:00:00</Start>
        <Finish>2027-05-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>144000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-05-12T08:00:00</Start>
        <Finish>2027-05-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>144000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-05-13T08:00:00</Start>
        <Finish>2027-05-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>144000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-05-14T08:00:00</Start>
        <Finish>2027-05-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>147200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-05-17T08:00:00</Start>
        <Finish>2027-05-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>147200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-05-18T08:00:00</Start>
        <Finish>2027-05-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>147200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-05-19T08:00:00</Start>
        <Finish>2027-05-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>147200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-05-20T08:00:00</Start>
        <Finish>2027-05-20T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>99200</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>28</UID>
      <ID>28</ID>
      <Name>Mechanical and electrical</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-06T08:00:00</Start>
      <Finish>2027-05-20T17:00:00</Finish>
      <Duration>PT264H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <Cost>3440000</Cost>
      <ActualCost>0</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-04-06T08:00:00</Start>
        <Finish>2027-05-20T17:00:00</Finish>
        <Duration>PT264H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT544H0M0S</Work>
        <Cost>3440000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>28</UID>
        <Start>2027-04-06T08:00:00</Start>
        <Finish>2027-04-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT52H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>28</UID>
        <Start>2027-04-07T08:00:00</Start>
        <Finish>2027-04-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT52H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>28</UID>
        <Start>2027-04-08T08:00:00</Start>
        <Finish>2027-04-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT52H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>28</UID>
        <Start>2027-04-09T08:00:00</Start>
        <Finish>2027-04-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT52H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>28</UID>
        <Start>2027-04-12T08:00:00</Start>
        <Finish>2027-04-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT52H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>28</UID>
        <Start>2027-04-13T08:00:00</Start>
        <Finish>2027-04-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT52H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>28</UID>
        <Start>2027-04-14T08:00:00</Start>
        <Finish>2027-04-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT52H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>28</UID>
        <Start>2027-04-15T08:00:00</Start>
        <Finish>2027-04-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT36H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>28</UID>
        <Start>2027-04-16T08:00:00</Start>
        <Finish>2027-04-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>28</UID>
        <Start>2027-04-19T08:00:00</Start>
        <Finish>2027-04-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>28</UID>
        <Start>2027-05-14T08:00:00</Start>
        <Finish>2027-05-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>28</UID>
        <Start>2027-05-17T08:00:00</Start>
        <Finish>2027-05-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>28</UID>
        <Start>2027-05-18T08:00:00</Start>
        <Finish>2027-05-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>28</UID>
        <Start>2027-05-19T08:00:00</Start>
        <Finish>2027-05-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>28</UID>
        <Start>2027-05-20T08:00:00</Start>
        <Finish>2027-05-20T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>28</UID>
        <Start>2027-04-06T08:00:00</Start>
        <Finish>2027-04-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>328800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>28</UID>
        <Start>2027-04-07T08:00:00</Start>
        <Finish>2027-04-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>328800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>28</UID>
        <Start>2027-04-08T08:00:00</Start>
        <Finish>2027-04-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>328800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>28</UID>
        <Start>2027-04-09T08:00:00</Start>
        <Finish>2027-04-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>328800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>28</UID>
        <Start>2027-04-12T08:00:00</Start>
        <Finish>2027-04-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>328800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>28</UID>
        <Start>2027-04-13T08:00:00</Start>
        <Finish>2027-04-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>328800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>28</UID>
        <Start>2027-04-14T08:00:00</Start>
        <Finish>2027-04-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>328800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>28</UID>
        <Start>2027-04-15T08:00:00</Start>
        <Finish>2027-04-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>232800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>28</UID>
        <Start>2027-04-16T08:00:00</Start>
        <Finish>2027-04-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>108800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>28</UID>
        <Start>2027-04-19T08:00:00</Start>
        <Finish>2027-04-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>108800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>28</UID>
        <Start>2027-05-14T08:00:00</Start>
        <Finish>2027-05-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>147200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>28</UID>
        <Start>2027-05-17T08:00:00</Start>
        <Finish>2027-05-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>147200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>28</UID>
        <Start>2027-05-18T08:00:00</Start>
        <Finish>2027-05-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>147200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>28</UID>
        <Start>2027-05-19T08:00:00</Start>
        <Finish>2027-05-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>147200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>28</UID>
        <Start>2027-05-20T08:00:00</Start>
        <Finish>2027-05-20T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>99200</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>29</UID>
      <ID>29</ID>
      <Name>Electrical</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.1.1</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-06T08:00:00</Start>
      <Finish>2027-05-20T17:00:00</Finish>
      <Duration>PT264H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <Cost>1289600</Cost>
      <ActualCost>0</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-04-06T08:00:00</Start>
        <Finish>2027-05-20T17:00:00</Finish>
        <Duration>PT264H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT208H0M0S</Work>
        <Cost>1289600</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>29</UID>
        <Start>2027-04-06T08:00:00</Start>
        <Finish>2027-04-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>29</UID>
        <Start>2027-04-07T08:00:00</Start>
        <Finish>2027-04-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>29</UID>
        <Start>2027-04-08T08:00:00</Start>
        <Finish>2027-04-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>29</UID>
        <Start>2027-04-09T08:00:00</Start>
        <Finish>2027-04-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>29</UID>
        <Start>2027-04-12T08:00:00</Start>
        <Finish>2027-04-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>29</UID>
        <Start>2027-04-13T08:00:00</Start>
        <Finish>2027-04-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>29</UID>
        <Start>2027-04-14T08:00:00</Start>
        <Finish>2027-04-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>29</UID>
        <Start>2027-04-15T08:00:00</Start>
        <Finish>2027-04-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>29</UID>
        <Start>2027-05-14T08:00:00</Start>
        <Finish>2027-05-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>29</UID>
        <Start>2027-05-17T08:00:00</Start>
        <Finish>2027-05-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>29</UID>
        <Start>2027-05-18T08:00:00</Start>
        <Finish>2027-05-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>29</UID>
        <Start>2027-05-19T08:00:00</Start>
        <Finish>2027-05-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>29</UID>
        <Start>2027-05-20T08:00:00</Start>
        <Finish>2027-05-20T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>29</UID>
        <Start>2027-04-06T08:00:00</Start>
        <Finish>2027-04-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>99200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>29</UID>
        <Start>2027-04-07T08:00:00</Start>
        <Finish>2027-04-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>99200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>29</UID>
        <Start>2027-04-08T08:00:00</Start>
        <Finish>2027-04-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>99200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>29</UID>
        <Start>2027-04-09T08:00:00</Start>
        <Finish>2027-04-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>99200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>29</UID>
        <Start>2027-04-12T08:00:00</Start>
        <Finish>2027-04-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>99200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>29</UID>
        <Start>2027-04-13T08:00:00</Start>
        <Finish>2027-04-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>99200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>29</UID>
        <Start>2027-04-14T08:00:00</Start>
        <Finish>2027-04-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>99200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>29</UID>
        <Start>2027-04-15T08:00:00</Start>
        <Finish>2027-04-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>99200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>29</UID>
        <Start>2027-05-14T08:00:00</Start>
        <Finish>2027-05-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>99200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>29</UID>
        <Start>2027-05-17T08:00:00</Start>
        <Finish>2027-05-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>99200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>29</UID>
        <Start>2027-05-18T08:00:00</Start>
        <Finish>2027-05-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>99200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>29</UID>
        <Start>2027-05-19T08:00:00</Start>
        <Finish>2027-05-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>99200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>29</UID>
        <Start>2027-05-20T08:00:00</Start>
        <Finish>2027-05-20T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>99200</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>30</UID>
      <ID>30</ID>
      <Name>Electrical first fix</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.1.1.1</OutlineNumber>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-06T08:00:00</Start>
      <Finish>2027-04-15T17:00:00</Finish>
      <Duration>PT64H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT128H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>9600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>793600</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT128H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>26</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-04-06T08:00:00</Start>
        <Finish>2027-04-15T17:00:00</Finish>
        <Duration>PT64H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT128H0M0S</Work>
        <Cost>793600</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>30</UID>
        <Start>2027-04-06T08:00:00</Start>
        <Finish>2027-04-15T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT128H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>30</UID>
        <Start>2027-04-06T08:00:00</Start>
        <Finish>2027-04-15T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>793600</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>31</UID>
      <ID>31</ID>
      <Name>Electrical second fix</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.1.1.2</OutlineNumber>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-05-14T08:00:00</Start>
      <Finish>2027-05-20T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT80H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>496000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT80H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>40</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <ExtendedAttribute>
        <FieldID>188743783</FieldID>
        <Value>PT36H0M0S</Value>
      </ExtendedAttribute>
      <ExtendedAttribute>
        <FieldID>188743785</FieldID>
        <Value>PT56H0M0S</Value>
      </ExtendedAttribute>
      <Baseline>
        <Number>0</Number>
        <Start>2027-05-14T08:00:00</Start>
        <Finish>2027-05-20T17:00:00</Finish>
        <Duration>PT40H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT80H0M0S</Work>
        <Cost>496000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>31</UID>
        <Start>2027-05-14T08:00:00</Start>
        <Finish>2027-05-20T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT80H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>31</UID>
        <Start>2027-05-14T08:00:00</Start>
        <Finish>2027-05-20T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>496000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>32</UID>
      <ID>32</ID>
      <Name>Plumbing and heating</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.1.2</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-06T08:00:00</Start>
      <Finish>2027-05-19T17:00:00</Finish>
      <Duration>PT256H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <Cost>864000</Cost>
      <ActualCost>0</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-04-06T08:00:00</Start>
        <Finish>2027-05-19T17:00:00</Finish>
        <Duration>PT256H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT144H0M0S</Work>
        <Cost>864000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>32</UID>
        <Start>2027-04-06T08:00:00</Start>
        <Finish>2027-04-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>32</UID>
        <Start>2027-04-07T08:00:00</Start>
        <Finish>2027-04-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>32</UID>
        <Start>2027-04-08T08:00:00</Start>
        <Finish>2027-04-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>32</UID>
        <Start>2027-04-09T08:00:00</Start>
        <Finish>2027-04-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>32</UID>
        <Start>2027-04-12T08:00:00</Start>
        <Finish>2027-04-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>32</UID>
        <Start>2027-04-13T08:00:00</Start>
        <Finish>2027-04-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>32</UID>
        <Start>2027-04-14T08:00:00</Start>
        <Finish>2027-04-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>32</UID>
        <Start>2027-05-14T08:00:00</Start>
        <Finish>2027-05-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>32</UID>
        <Start>2027-05-17T08:00:00</Start>
        <Finish>2027-05-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>32</UID>
        <Start>2027-05-18T08:00:00</Start>
        <Finish>2027-05-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>32</UID>
        <Start>2027-05-19T08:00:00</Start>
        <Finish>2027-05-19T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>32</UID>
        <Start>2027-04-06T08:00:00</Start>
        <Finish>2027-04-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>96000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>32</UID>
        <Start>2027-04-07T08:00:00</Start>
        <Finish>2027-04-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>96000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>32</UID>
        <Start>2027-04-08T08:00:00</Start>
        <Finish>2027-04-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>96000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>32</UID>
        <Start>2027-04-09T08:00:00</Start>
        <Finish>2027-04-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>96000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>32</UID>
        <Start>2027-04-12T08:00:00</Start>
        <Finish>2027-04-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>96000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>32</UID>
        <Start>2027-04-13T08:00:00</Start>
        <Finish>2027-04-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>96000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>32</UID>
        <Start>2027-04-14T08:00:00</Start>
        <Finish>2027-04-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>96000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>32</UID>
        <Start>2027-05-14T08:00:00</Start>
        <Finish>2027-05-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>48000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>32</UID>
        <Start>2027-05-17T08:00:00</Start>
        <Finish>2027-05-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>48000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>32</UID>
        <Start>2027-05-18T08:00:00</Start>
        <Finish>2027-05-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>48000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>32</UID>
        <Start>2027-05-19T08:00:00</Start>
        <Finish>2027-05-19T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>48000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>33</UID>
      <ID>33</ID>
      <Name>Plumbing first fix</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.1.2.1</OutlineNumber>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-06T08:00:00</Start>
      <Finish>2027-04-14T17:00:00</Finish>
      <Duration>PT56H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT112H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>672000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT112H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>26</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <ExtendedAttribute>
        <FieldID>188743783</FieldID>
        <Value>PT48H0M0S</Value>
      </ExtendedAttribute>
      <ExtendedAttribute>
        <FieldID>188743785</FieldID>
        <Value>PT80H0M0S</Value>
      </ExtendedAttribute>
      <Baseline>
        <Number>0</Number>
        <Start>2027-04-06T08:00:00</Start>
        <Finish>2027-04-14T17:00:00</Finish>
        <Duration>PT56H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT112H0M0S</Work>
        <Cost>672000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>33</UID>
        <Start>2027-04-06T08:00:00</Start>
        <Finish>2027-04-14T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT112H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>33</UID>
        <Start>2027-04-06T08:00:00</Start>
        <Finish>2027-04-14T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>672000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>34</UID>
      <ID>34</ID>
      <Name>Sanitaryware and second fix</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.1.2.2</OutlineNumber>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-05-14T08:00:00</Start>
      <Finish>2027-05-19T17:00:00</Finish>
      <Duration>PT32H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT32H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>4800</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>192000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT32H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>40</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-05-14T08:00:00</Start>
        <Finish>2027-05-19T17:00:00</Finish>
        <Duration>PT32H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT32H0M0S</Work>
        <Cost>192000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>34</UID>
        <Start>2027-05-14T08:00:00</Start>
        <Finish>2027-05-19T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>34</UID>
        <Start>2027-05-14T08:00:00</Start>
        <Finish>2027-05-19T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>192000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>35</UID>
      <ID>35</ID>
      <Name>Ductwork and air handling units</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.1.3</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-06T08:00:00</Start>
      <Finish>2027-04-19T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT160H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>33600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>1088000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT160H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>26</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>44</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-04-06T08:00:00</Start>
        <Finish>2027-04-19T17:00:00</Finish>
        <Duration>PT80H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT160H0M0S</Work>
        <Cost>1088000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>35</UID>
        <Start>2027-04-06T08:00:00</Start>
        <Finish>2027-04-19T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT160H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>35</UID>
        <Start>2027-04-06T08:00:00</Start>
        <Finish>2027-04-19T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>1088000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>36</UID>
      <ID>36</ID>
      <Name>Lift installation</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.1.4</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-06T08:00:00</Start>
      <Finish>2027-04-15T17:00:00</Finish>
      <Duration>PT64H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT32H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>120000</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>198400</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT32H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>26</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>43</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-04-06T08:00:00</Start>
        <Finish>2027-04-15T17:00:00</Finish>
        <Duration>PT64H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT32H0M0S</Work>
        <Cost>198400</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>36</UID>
        <Start>2027-04-06T08:00:00</Start>
        <Finish>2027-04-15T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>36</UID>
        <Start>2027-04-06T08:00:00</Start>
        <Finish>2027-04-15T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>198400</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>37</UID>
      <ID>37</ID>
      <Name>Interiors</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-15T08:00:00</Start>
      <Finish>2027-05-13T17:00:00</Finish>
      <Duration>PT168H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <Cost>2392000</Cost>
      <ActualCost>0</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-04-15T08:00:00</Start>
        <Finish>2027-05-13T17:00:00</Finish>
        <Duration>PT168H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT496H0M0S</Work>
        <Cost>2392000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>37</UID>
        <Start>2027-04-15T08:00:00</Start>
        <Finish>2027-04-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>37</UID>
        <Start>2027-04-16T08:00:00</Start>
        <Finish>2027-04-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>37</UID>
        <Start>2027-04-19T08:00:00</Start>
        <Finish>2027-04-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>37</UID>
        <Start>2027-04-20T08:00:00</Start>
        <Finish>2027-04-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>37</UID>
        <Start>2027-04-21T08:00:00</Start>
        <Finish>2027-04-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>37</UID>
        <Start>2027-04-22T08:00:00</Start>
        <Finish>2027-04-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>37</UID>
        <Start>2027-04-23T08:00:00</Start>
        <Finish>2027-04-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>37</UID>
        <Start>2027-04-26T08:00:00</Start>
        <Finish>2027-04-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>37</UID>
        <Start>2027-04-27T08:00:00</Start>
        <Finish>2027-04-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>37</UID>
        <Start>2027-04-28T08:00:00</Start>
        <Finish>2027-04-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>37</UID>
        <Start>2027-04-29T08:00:00</Start>
        <Finish>2027-04-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>37</UID>
        <Start>2027-04-30T08:00:00</Start>
        <Finish>2027-05-01T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>37</UID>
        <Start>2027-05-03T08:00:00</Start>
        <Finish>2027-05-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>37</UID>
        <Start>2027-05-04T08:00:00</Start>
        <Finish>2027-05-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>37</UID>
        <Start>2027-05-05T08:00:00</Start>
        <Finish>2027-05-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>37</UID>
        <Start>2027-05-06T08:00:00</Start>
        <Finish>2027-05-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>37</UID>
        <Start>2027-05-07T08:00:00</Start>
        <Finish>2027-05-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>37</UID>
        <Start>2027-05-10T08:00:00</Start>
        <Finish>2027-05-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>37</UID>
        <Start>2027-05-11T08:00:00</Start>
        <Finish>2027-05-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>37</UID>
        <Start>2027-05-12T08:00:00</Start>
        <Finish>2027-05-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>37</UID>
        <Start>2027-05-13T08:00:00</Start>
        <Finish>2027-05-13T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>37</UID>
        <Start>2027-04-15T08:00:00</Start>
        <Finish>2027-04-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>120000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>37</UID>
        <Start>2027-04-16T08:00:00</Start>
        <Finish>2027-04-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>120000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>37</UID>
        <Start>2027-04-19T08:00:00</Start>
        <Finish>2027-04-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>120000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>37</UID>
        <Start>2027-04-20T08:00:00</Start>
        <Finish>2027-04-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>120000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>37</UID>
        <Start>2027-04-21T08:00:00</Start>
        <Finish>2027-04-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>120000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>37</UID>
        <Start>2027-04-22T08:00:00</Start>
        <Finish>2027-04-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>120000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>37</UID>
        <Start>2027-04-23T08:00:00</Start>
        <Finish>2027-04-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>120000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>37</UID>
        <Start>2027-04-26T08:00:00</Start>
        <Finish>2027-04-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>120000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>37</UID>
        <Start>2027-04-27T08:00:00</Start>
        <Finish>2027-04-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>120000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>37</UID>
        <Start>2027-04-28T08:00:00</Start>
        <Finish>2027-04-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>120000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>37</UID>
        <Start>2027-04-29T08:00:00</Start>
        <Finish>2027-04-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>80000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>37</UID>
        <Start>2027-04-30T08:00:00</Start>
        <Finish>2027-05-01T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>80000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>37</UID>
        <Start>2027-05-03T08:00:00</Start>
        <Finish>2027-05-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>80000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>37</UID>
        <Start>2027-05-04T08:00:00</Start>
        <Finish>2027-05-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>80000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>37</UID>
        <Start>2027-05-05T08:00:00</Start>
        <Finish>2027-05-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>80000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>37</UID>
        <Start>2027-05-06T08:00:00</Start>
        <Finish>2027-05-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>72000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>37</UID>
        <Start>2027-05-07T08:00:00</Start>
        <Finish>2027-05-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>144000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>37</UID>
        <Start>2027-05-10T08:00:00</Start>
        <Finish>2027-05-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>144000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>37</UID>
        <Start>2027-05-11T08:00:00</Start>
        <Finish>2027-05-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>144000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>37</UID>
        <Start>2027-05-12T08:00:00</Start>
        <Finish>2027-05-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>144000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>37</UID>
        <Start>2027-05-13T08:00:00</Start>
        <Finish>2027-05-13T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>144000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>38</UID>
      <ID>38</ID>
      <Name>Partitions and drylining</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.2.1</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-15T08:00:00</Start>
      <Finish>2027-04-28T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT240H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>1200000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT240H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>30</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>-14400</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>33</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <ExtendedAttribute>
        <FieldID>188743783</FieldID>
        <Value>PT68H0M0S</Value>
      </ExtendedAttribute>
      <ExtendedAttribute>
        <FieldID>188743785</FieldID>
        <Value>PT112H0M0S</Value>
      </ExtendedAttribute>
      <Baseline>
        <Number>0</Number>
        <Start>2027-04-15T08:00:00</Start>
        <Finish>2027-04-28T17:00:00</Finish>
        <Duration>PT80H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT240H0M0S</Work>
        <Cost>1200000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>38</UID>
        <Start>2027-04-15T08:00:00</Start>
        <Finish>2027-04-28T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT240H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>38</UID>
        <Start>2027-04-15T08:00:00</Start>
        <Finish>2027-04-28T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>1200000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>39</UID>
      <ID>39</ID>
      <Name>Suspended ceilings</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.2.2</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-29T08:00:00</Start>
      <Finish>2027-05-05T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT80H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>400000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT80H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>38</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>35</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <ExtendedAttribute>
        <FieldID>188743783</FieldID>
        <Value>PT36H0M0S</Value>
      </ExtendedAttribute>
      <ExtendedAttribute>
        <FieldID>188743785</FieldID>
        <Value>PT56H0M0S</Value>
      </ExtendedAttribute>
      <Baseline>
        <Number>0</Number>
        <Start>2027-04-29T08:00:00</Start>
        <Finish>2027-05-05T17:00:00</Finish>
        <Duration>PT40H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT80H0M0S</Work>
        <Cost>400000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>39</UID>
        <Start>2027-04-29T08:00:00</Start>
        <Finish>2027-05-05T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT80H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>39</UID>
        <Start>2027-04-29T08:00:00</Start>
        <Finish>2027-05-05T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>400000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>40</UID>
      <ID>40</ID>
      <Name>Decoration</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.2.3</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-05-06T08:00:00</Start>
      <Finish>2027-05-13T17:00:00</Finish>
      <Duration>PT48H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT96H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>432000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT96H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>39</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <ExtendedAttribute>
        <FieldID>188743783</FieldID>
        <Value>PT40H0M0S</Value>
      </ExtendedAttribute>
      <ExtendedAttribute>
        <FieldID>188743785</FieldID>
        <Value>PT68H0M0S</Value>
      </ExtendedAttribute>
      <Baseline>
        <Number>0</Number>
        <Start>2027-05-06T08:00:00</Start>
        <Finish>2027-05-13T17:00:00</Finish>
        <Duration>PT48H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT96H0M0S</Work>
        <Cost>432000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>40</UID>
        <Start>2027-05-06T08:00:00</Start>
        <Finish>2027-05-13T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT96H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>40</UID>
        <Start>2027-05-06T08:00:00</Start>
        <Finish>2027-05-13T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>432000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>41</UID>
      <ID>41</ID>
      <Name>Floor finishes</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.2.4</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-05-07T08:00:00</Start>
      <Finish>2027-05-13T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT80H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>52800</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>360000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT80H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>40</PredecessorUID>
        <Type>0</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-05-07T08:00:00</Start>
        <Finish>2027-05-13T17:00:00</Finish>
        <Duration>PT40H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT80H0M0S</Work>
        <Cost>360000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>41</UID>
        <Start>2027-05-07T08:00:00</Start>
        <Finish>2027-05-13T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT80H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>41</UID>
        <Start>2027-05-07T08:00:00</Start>
        <Finish>2027-05-13T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>360000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>42</UID>
      <ID>42</ID>
      <Name>Procurement</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-18T08:00:00</Start>
      <Finish>2027-03-17T17:00:00</Finish>
      <Duration>PT344H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>182400</TotalSlack>
      <PercentComplete>89</PercentComplete>
      <Cost>1028400</Cost>
      <ActualCost>885650</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-18T08:00:00</Start>
        <Finish>2027-03-12T17:00:00</Finish>
        <Duration>PT320H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT48H0M0S</Work>
        <Cost>408000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-01-18T08:00:00</Start>
        <Finish>2027-01-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-01-19T08:00:00</Start>
        <Finish>2027-01-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-01-20T08:00:00</Start>
        <Finish>2027-01-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-01-21T08:00:00</Start>
        <Finish>2027-01-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-01-22T08:00:00</Start>
        <Finish>2027-01-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-01-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-01-26T08:00:00</Start>
        <Finish>2027-01-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-01-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-01-28T08:00:00</Start>
        <Finish>2027-01-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-01-29T08:00:00</Start>
        <Finish>2027-01-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-02-01T08:00:00</Start>
        <Finish>2027-02-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-02-02T08:00:00</Start>
        <Finish>2027-02-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-02-03T08:00:00</Start>
        <Finish>2027-02-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-02-04T08:00:00</Start>
        <Finish>2027-02-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-02-05T08:00:00</Start>
        <Finish>2027-02-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-02-08T08:00:00</Start>
        <Finish>2027-02-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-02-09T08:00:00</Start>
        <Finish>2027-02-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-02-10T08:00:00</Start>
        <Finish>2027-02-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-02-12T08:00:00</Start>
        <Finish>2027-02-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-02-15T08:00:00</Start>
        <Finish>2027-02-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT0H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-02-16T08:00:00</Start>
        <Finish>2027-02-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT0H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-02-17T08:00:00</Start>
        <Finish>2027-02-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT0H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-02-18T08:00:00</Start>
        <Finish>2027-02-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT0H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-02-19T08:00:00</Start>
        <Finish>2027-02-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT0H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-02-22T08:00:00</Start>
        <Finish>2027-02-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT0H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-02-23T08:00:00</Start>
        <Finish>2027-02-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT0H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-02-24T08:00:00</Start>
        <Finish>2027-02-25T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT0H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-02-25T08:00:00</Start>
        <Finish>2027-02-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT0H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-02-26T08:00:00</Start>
        <Finish>2027-02-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT0H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-03-01T08:00:00</Start>
        <Finish>2027-03-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT0H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-03-02T08:00:00</Start>
        <Finish>2027-03-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT0H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-03-03T08:00:00</Start>
        <Finish>2027-03-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT0H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-03-04T08:00:00</Start>
        <Finish>2027-03-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT0H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-03-05T08:00:00</Start>
        <Finish>2027-03-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT0H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-03-08T08:00:00</Start>
        <Finish>2027-03-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT0H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-03-09T08:00:00</Start>
        <Finish>2027-03-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT0H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-03-10T08:00:00</Start>
        <Finish>2027-03-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT0H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-03-11T08:00:00</Start>
        <Finish>2027-03-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT0H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-03-12T08:00:00</Start>
        <Finish>2027-03-12T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT0H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-01-18T08:00:00</Start>
        <Finish>2027-01-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>13600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-01-19T08:00:00</Start>
        <Finish>2027-01-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>13600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-01-20T08:00:00</Start>
        <Finish>2027-01-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>13600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-01-21T08:00:00</Start>
        <Finish>2027-01-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>13600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-01-22T08:00:00</Start>
        <Finish>2027-01-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>13600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-01-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>13600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-01-26T08:00:00</Start>
        <Finish>2027-01-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>13600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-01-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>13600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-01-28T08:00:00</Start>
        <Finish>2027-01-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>13600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-01-29T08:00:00</Start>
        <Finish>2027-01-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>13600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-02-01T08:00:00</Start>
        <Finish>2027-02-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>13600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-02-02T08:00:00</Start>
        <Finish>2027-02-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>13600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-02-03T08:00:00</Start>
        <Finish>2027-02-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>13600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-02-04T08:00:00</Start>
        <Finish>2027-02-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>13600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-02-05T08:00:00</Start>
        <Finish>2027-02-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>13600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-02-08T08:00:00</Start>
        <Finish>2027-02-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>13600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-02-09T08:00:00</Start>
        <Finish>2027-02-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>13600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-02-10T08:00:00</Start>
        <Finish>2027-02-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>13600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>13600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-02-12T08:00:00</Start>
        <Finish>2027-02-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>13600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-02-15T08:00:00</Start>
        <Finish>2027-02-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>6800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-02-16T08:00:00</Start>
        <Finish>2027-02-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>6800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-02-17T08:00:00</Start>
        <Finish>2027-02-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>6800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-02-18T08:00:00</Start>
        <Finish>2027-02-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>6800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-02-19T08:00:00</Start>
        <Finish>2027-02-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>6800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-02-22T08:00:00</Start>
        <Finish>2027-02-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>6800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-02-23T08:00:00</Start>
        <Finish>2027-02-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>6800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-02-24T08:00:00</Start>
        <Finish>2027-02-25T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>6800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-02-25T08:00:00</Start>
        <Finish>2027-02-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>6800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-02-26T08:00:00</Start>
        <Finish>2027-02-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>6800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-03-01T08:00:00</Start>
        <Finish>2027-03-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>6800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-03-02T08:00:00</Start>
        <Finish>2027-03-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>6800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-03-03T08:00:00</Start>
        <Finish>2027-03-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>6800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-03-04T08:00:00</Start>
        <Finish>2027-03-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>6800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-03-05T08:00:00</Start>
        <Finish>2027-03-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>6800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-03-08T08:00:00</Start>
        <Finish>2027-03-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>6800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-03-09T08:00:00</Start>
        <Finish>2027-03-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>6800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-03-10T08:00:00</Start>
        <Finish>2027-03-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>6800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-03-11T08:00:00</Start>
        <Finish>2027-03-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>6800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-03-12T08:00:00</Start>
        <Finish>2027-03-12T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>6800</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>43</UID>
      <ID>43</ID>
      <Name>Lift manufacture and delivery</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.3.1</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-18T08:00:00</Start>
      <Finish>2027-03-17T17:00:00</Finish>
      <Duration>PT344H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT34H24M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>182400</TotalSlack>
      <FixedCost>600000</FixedCost>
      <PercentComplete>84</PercentComplete>
      <PercentWorkComplete>84</PercentWorkComplete>
      <Cost>892400</Cost>
      <ActualStart>2027-01-18T08:00:00</ActualStart>
      <ActualCost>749650</ActualCost>
      <ActualWork>PT28H54M0S</ActualWork>
      <RemainingWork>PT5H30M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>4</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-18T08:00:00</Start>
        <Finish>2027-03-12T17:00:00</Finish>
        <Duration>PT320H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT32H0M0S</Work>
        <Cost>272000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>43</UID>
        <Start>2027-01-18T08:00:00</Start>
        <Finish>2027-03-12T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>43</UID>
        <Start>2027-01-18T08:00:00</Start>
        <Finish>2027-03-12T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>272000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>44</UID>
      <ID>44</ID>
      <Name>Air handling units delivery</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.3.2</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-18T08:00:00</Start>
      <Finish>2027-02-12T17:00:00</Finish>
      <Duration>PT160H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT16H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>206400</TotalSlack>
      <PercentComplete>100</PercentComplete>
      <PercentWorkComplete>100</PercentWorkComplete>
      <Cost>136000</Cost>
      <ActualStart>2027-01-18T08:00:00</ActualStart>
      <ActualFinish>2027-02-12T17:00:00</ActualFinish>
      <ActualCost>136000</ActualCost>
      <ActualWork>PT16H0M0S</ActualWork>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>4</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-18T08:00:00</Start>
        <Finish>2027-02-12T17:00:00</Finish>
        <Duration>PT160H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT16H0M0S</Work>
        <Cost>136000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>44</UID>
        <Start>2027-01-18T08:00:00</Start>
        <Finish>2027-02-12T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>44</UID>
        <Start>2027-01-18T08:00:00</Start>
        <Finish>2027-02-12T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>136000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>45</UID>
      <ID>45</ID>
      <Name>Handover</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-05-12T08:00:00</Start>
      <Finish>2027-06-03T17:00:00</Finish>
      <Duration>PT136H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <Cost>1852000</Cost>
      <ActualCost>0</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-05-12T08:00:00</Start>
        <Finish>2027-06-03T17:00:00</Finish>
        <Duration>PT136H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT312H0M0S</Work>
        <Cost>1852000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>45</UID>
        <Start>2027-05-12T08:00:00</Start>
        <Finish>2027-05-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>45</UID>
        <Start>2027-05-13T08:00:00</Start>
        <Finish>2027-05-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>45</UID>
        <Start>2027-05-14T08:00:00</Start>
        <Finish>2027-05-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>45</UID>
        <Start>2027-05-17T08:00:00</Start>
        <Finish>2027-05-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>45</UID>
        <Start>2027-05-18T08:00:00</Start>
        <Finish>2027-05-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>45</UID>
        <Start>2027-05-19T08:00:00</Start>
        <Finish>2027-05-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>45</UID>
        <Start>2027-05-20T08:00:00</Start>
        <Finish>2027-05-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>45</UID>
        <Start>2027-05-21T08:00:00</Start>
        <Finish>2027-05-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>45</UID>
        <Start>2027-05-24T08:00:00</Start>
        <Finish>2027-05-25T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>45</UID>
        <Start>2027-05-25T08:00:00</Start>
        <Finish>2027-05-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>45</UID>
        <Start>2027-05-26T08:00:00</Start>
        <Finish>2027-05-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>45</UID>
        <Start>2027-05-27T08:00:00</Start>
        <Finish>2027-05-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>45</UID>
        <Start>2027-05-28T08:00:00</Start>
        <Finish>2027-05-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>45</UID>
        <Start>2027-05-31T08:00:00</Start>
        <Finish>2027-06-01T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>45</UID>
        <Start>2027-06-01T08:00:00</Start>
        <Finish>2027-06-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>45</UID>
        <Start>2027-06-02T08:00:00</Start>
        <Finish>2027-06-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>45</UID>
        <Start>2027-06-03T08:00:00</Start>
        <Finish>2027-06-03T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>45</UID>
        <Start>2027-05-12T08:00:00</Start>
        <Finish>2027-05-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>45</UID>
        <Start>2027-05-13T08:00:00</Start>
        <Finish>2027-05-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>45</UID>
        <Start>2027-05-14T08:00:00</Start>
        <Finish>2027-05-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>45</UID>
        <Start>2027-05-17T08:00:00</Start>
        <Finish>2027-05-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>45</UID>
        <Start>2027-05-18T08:00:00</Start>
        <Finish>2027-05-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>45</UID>
        <Start>2027-05-19T08:00:00</Start>
        <Finish>2027-05-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>45</UID>
        <Start>2027-05-20T08:00:00</Start>
        <Finish>2027-05-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>45</UID>
        <Start>2027-05-21T08:00:00</Start>
        <Finish>2027-05-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>192000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>45</UID>
        <Start>2027-05-24T08:00:00</Start>
        <Finish>2027-05-25T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>104000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>45</UID>
        <Start>2027-05-25T08:00:00</Start>
        <Finish>2027-05-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>104000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>45</UID>
        <Start>2027-05-26T08:00:00</Start>
        <Finish>2027-05-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>104000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>45</UID>
        <Start>2027-05-27T08:00:00</Start>
        <Finish>2027-05-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>104000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>45</UID>
        <Start>2027-05-28T08:00:00</Start>
        <Finish>2027-05-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>140000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>45</UID>
        <Start>2027-05-31T08:00:00</Start>
        <Finish>2027-06-01T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>140000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>45</UID>
        <Start>2027-06-01T08:00:00</Start>
        <Finish>2027-06-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>140000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>45</UID>
        <Start>2027-06-02T08:00:00</Start>
        <Finish>2027-06-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>140000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>45</UID>
        <Start>2027-06-03T08:00:00</Start>
        <Finish>2027-06-03T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>68000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>46</UID>
      <ID>46</ID>
      <Name>Testing</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-05-21T08:00:00</Start>
      <Finish>2027-05-31T17:00:00</Finish>
      <Duration>PT56H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <Cost>656000</Cost>
      <ActualCost>0</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-05-21T08:00:00</Start>
        <Finish>2027-05-31T17:00:00</Finish>
        <Duration>PT56H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT96H0M0S</Work>
        <Cost>656000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>46</UID>
        <Start>2027-05-21T08:00:00</Start>
        <Finish>2027-05-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>46</UID>
        <Start>2027-05-24T08:00:00</Start>
        <Finish>2027-05-25T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>46</UID>
        <Start>2027-05-25T08:00:00</Start>
        <Finish>2027-05-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>46</UID>
        <Start>2027-05-26T08:00:00</Start>
        <Finish>2027-05-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>46</UID>
        <Start>2027-05-27T08:00:00</Start>
        <Finish>2027-05-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>46</UID>
        <Start>2027-05-28T08:00:00</Start>
        <Finish>2027-05-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>46</UID>
        <Start>2027-05-31T08:00:00</Start>
        <Finish>2027-05-31T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>46</UID>
        <Start>2027-05-21T08:00:00</Start>
        <Finish>2027-05-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>104000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>46</UID>
        <Start>2027-05-24T08:00:00</Start>
        <Finish>2027-05-25T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>104000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>46</UID>
        <Start>2027-05-25T08:00:00</Start>
        <Finish>2027-05-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>104000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>46</UID>
        <Start>2027-05-26T08:00:00</Start>
        <Finish>2027-05-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>104000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>46</UID>
        <Start>2027-05-27T08:00:00</Start>
        <Finish>2027-05-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>104000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>46</UID>
        <Start>2027-05-28T08:00:00</Start>
        <Finish>2027-05-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>68000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>46</UID>
        <Start>2027-05-31T08:00:00</Start>
        <Finish>2027-05-31T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>68000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>47</UID>
      <ID>47</ID>
      <Name>Testing and commissioning</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5.1.1</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-05-21T08:00:00</Start>
      <Finish>2027-05-27T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT80H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>520000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT80H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>31</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>34</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>35</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>36</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <ExtendedAttribute>
        <FieldID>188743783</FieldID>
        <Value>PT36H0M0S</Value>
      </ExtendedAttribute>
      <ExtendedAttribute>
        <FieldID>188743785</FieldID>
        <Value>PT56H0M0S</Value>
      </ExtendedAttribute>
      <Baseline>
        <Number>0</Number>
        <Start>2027-05-21T08:00:00</Start>
        <Finish>2027-05-27T17:00:00</Finish>
        <Duration>PT40H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT80H0M0S</Work>
        <Cost>520000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>47</UID>
        <Start>2027-05-21T08:00:00</Start>
        <Finish>2027-05-27T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT80H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>47</UID>
        <Start>2027-05-21T08:00:00</Start>
        <Finish>2027-05-27T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>520000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>48</UID>
      <ID>48</ID>
      <Name>Fire alarm and life safety certification</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5.1.2</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-05-28T08:00:00</Start>
      <Finish>2027-05-31T17:00:00</Finish>
      <Duration>PT16H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT16H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>136000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT16H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>47</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <ExtendedAttribute>
        <FieldID>188743783</FieldID>
        <Value>PT12H0M0S</Value>
      </ExtendedAttribute>
      <ExtendedAttribute>
        <FieldID>188743785</FieldID>
        <Value>PT24H0M0S</Value>
      </ExtendedAttribute>
      <Baseline>
        <Number>0</Number>
        <Start>2027-05-28T08:00:00</Start>
        <Finish>2027-05-31T17:00:00</Finish>
        <Duration>PT16H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT16H0M0S</Work>
        <Cost>136000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>48</UID>
        <Start>2027-05-28T08:00:00</Start>
        <Finish>2027-05-31T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>48</UID>
        <Start>2027-05-28T08:00:00</Start>
        <Finish>2027-05-31T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>136000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>49</UID>
      <ID>49</ID>
      <Name>Close-out</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-05-12T08:00:00</Start>
      <Finish>2027-06-03T17:00:00</Finish>
      <Duration>PT136H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <Cost>1196000</Cost>
      <ActualCost>0</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-05-12T08:00:00</Start>
        <Finish>2027-06-03T17:00:00</Finish>
        <Duration>PT136H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT216H0M0S</Work>
        <Cost>1196000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>49</UID>
        <Start>2027-05-12T08:00:00</Start>
        <Finish>2027-05-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>49</UID>
        <Start>2027-05-13T08:00:00</Start>
        <Finish>2027-05-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>49</UID>
        <Start>2027-05-14T08:00:00</Start>
        <Finish>2027-05-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>49</UID>
        <Start>2027-05-17T08:00:00</Start>
        <Finish>2027-05-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>49</UID>
        <Start>2027-05-18T08:00:00</Start>
        <Finish>2027-05-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>49</UID>
        <Start>2027-05-19T08:00:00</Start>
        <Finish>2027-05-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>49</UID>
        <Start>2027-05-20T08:00:00</Start>
        <Finish>2027-05-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>49</UID>
        <Start>2027-05-21T08:00:00</Start>
        <Finish>2027-05-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>49</UID>
        <Start>2027-05-28T08:00:00</Start>
        <Finish>2027-05-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>49</UID>
        <Start>2027-05-31T08:00:00</Start>
        <Finish>2027-06-01T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>49</UID>
        <Start>2027-06-01T08:00:00</Start>
        <Finish>2027-06-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>49</UID>
        <Start>2027-06-02T08:00:00</Start>
        <Finish>2027-06-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>49</UID>
        <Start>2027-06-03T08:00:00</Start>
        <Finish>2027-06-03T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>49</UID>
        <Start>2027-05-12T08:00:00</Start>
        <Finish>2027-05-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>49</UID>
        <Start>2027-05-13T08:00:00</Start>
        <Finish>2027-05-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>49</UID>
        <Start>2027-05-14T08:00:00</Start>
        <Finish>2027-05-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>49</UID>
        <Start>2027-05-17T08:00:00</Start>
        <Finish>2027-05-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>49</UID>
        <Start>2027-05-18T08:00:00</Start>
        <Finish>2027-05-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>49</UID>
        <Start>2027-05-19T08:00:00</Start>
        <Finish>2027-05-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>49</UID>
        <Start>2027-05-20T08:00:00</Start>
        <Finish>2027-05-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>49</UID>
        <Start>2027-05-21T08:00:00</Start>
        <Finish>2027-05-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>49</UID>
        <Start>2027-05-28T08:00:00</Start>
        <Finish>2027-05-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>72000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>49</UID>
        <Start>2027-05-31T08:00:00</Start>
        <Finish>2027-06-01T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>72000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>49</UID>
        <Start>2027-06-01T08:00:00</Start>
        <Finish>2027-06-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>140000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>49</UID>
        <Start>2027-06-02T08:00:00</Start>
        <Finish>2027-06-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>140000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>49</UID>
        <Start>2027-06-03T08:00:00</Start>
        <Finish>2027-06-03T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>68000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>50</UID>
      <ID>50</ID>
      <Name>Snagging and defects</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5.2.1</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-05-28T08:00:00</Start>
      <Finish>2027-06-02T17:00:00</Finish>
      <Duration>PT32H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT64H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>4800</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>288000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT64H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>47</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>41</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-05-28T08:00:00</Start>
        <Finish>2027-06-02T17:00:00</Finish>
        <Duration>PT32H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT64H0M0S</Work>
        <Cost>288000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>50</UID>
        <Start>2027-05-28T08:00:00</Start>
        <Finish>2027-06-02T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT64H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>50</UID>
        <Start>2027-05-28T08:00:00</Start>
        <Finish>2027-06-02T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>288000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>51</UID>
      <ID>51</ID>
      <Name>External works and landscaping</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5.2.2</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-05-12T08:00:00</Start>
      <Finish>2027-05-21T17:00:00</Finish>
      <Duration>PT64H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT128H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>43200</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>704000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT128H0M0S</RemainingWork>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-05-12T08:00:00</ConstraintDate>
      <PredecessorLink>
        <PredecessorUID>26</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-05-12T08:00:00</Start>
        <Finish>2027-05-21T17:00:00</Finish>
        <Duration>PT64H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT128H0M0S</Work>
        <Cost>704000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>51</UID>
        <Start>2027-05-12T08:00:00</Start>
        <Finish>2027-05-21T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT128H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>51</UID>
        <Start>2027-05-12T08:00:00</Start>
        <Finish>2027-05-21T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>704000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>52</UID>
      <ID>52</ID>
      <Name>Operation and maintenance manuals</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5.2.3</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-06-01T08:00:00</Start>
      <Finish>2027-06-03T17:00:00</Finish>
      <Duration>PT24H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT24H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>204000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT24H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>47</PredecessorUID>
        <Type>3</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>48</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <ExtendedAttribute>
        <FieldID>188743783</FieldID>
        <Value>PT20H0M0S</Value>
      </ExtendedAttribute>
      <ExtendedAttribute>
        <FieldID>188743785</FieldID>
        <Value>PT32H0M0S</Value>
      </ExtendedAttribute>
      <Baseline>
        <Number>0</Number>
        <Start>2027-06-01T08:00:00</Start>
        <Finish>2027-06-03T17:00:00</Finish>
        <Duration>PT24H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT24H0M0S</Work>
        <Cost>204000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>52</UID>
        <Start>2027-06-01T08:00:00</Start>
        <Finish>2027-06-03T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>52</UID>
        <Start>2027-06-01T08:00:00</Start>
        <Finish>2027-06-03T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>204000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>53</UID>
      <ID>53</ID>
      <Name>Practical completion</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-06-03T17:00:00</Start>
      <Finish>2027-06-03T17:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
      <Deadline>2027-06-09T17:00:00</Deadline>
      <PredecessorLink>
        <PredecessorUID>50</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>52</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>51</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-06-03T17:00:00</Start>
        <Finish>2027-06-03T17:00:00</Finish>
        <Duration>PT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
      </Baseline>
    </Task>
  </Tasks>
  <Resources>
    <Resource>
      <UID>1</UID>
      <ID>1</ID>
      <Name>Site manager</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <Initials>SM</Initials>
      <Group>Management</Group>
      <MaxUnits>1</MaxUnits>
      <StandardRate>85</StandardRate>
    </Resource>
    <Resource>
      <UID>2</UID>
      <ID>2</ID>
      <Name>Groundworks crew</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <Initials>GW</Initials>
      <Group>Civils</Group>
      <MaxUnits>3</MaxUnits>
      <StandardRate>55</StandardRate>
    </Resource>
    <Resource>
      <UID>3</UID>
      <ID>3</ID>
      <Name>Concrete crew</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <Initials>CC</Initials>
      <Group>Civils</Group>
      <MaxUnits>3</MaxUnits>
      <StandardRate>60</StandardRate>
    </Resource>
    <Resource>
      <UID>4</UID>
      <ID>4</ID>
      <Name>Steel erectors</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <Initials>SE</Initials>
      <Group>Structure</Group>
      <MaxUnits>4</MaxUnits>
      <StandardRate>70</StandardRate>
    </Resource>
    <Resource>
      <UID>5</UID>
      <ID>5</ID>
      <Name>Tower crane</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <Initials>TC</Initials>
      <Group>Plant</Group>
      <MaxUnits>1</MaxUnits>
      <StandardRate>120</StandardRate>
    </Resource>
    <Resource>
      <UID>6</UID>
      <ID>6</ID>
      <Name>Carpenters</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <Initials>CA</Initials>
      <Group>Trades</Group>
      <MaxUnits>4</MaxUnits>
      <StandardRate>50</StandardRate>
    </Resource>
    <Resource>
      <UID>7</UID>
      <ID>7</ID>
      <Name>Glaziers</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <Initials>GL</Initials>
      <Group>Trades</Group>
      <MaxUnits>2</MaxUnits>
      <StandardRate>58</StandardRate>
    </Resource>
    <Resource>
      <UID>8</UID>
      <ID>8</ID>
      <Name>Electricians</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <Initials>EL</Initials>
      <Group>Services</Group>
      <MaxUnits>3</MaxUnits>
      <StandardRate>62</StandardRate>
    </Resource>
    <Resource>
      <UID>9</UID>
      <ID>9</ID>
      <Name>Plumbers</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <Initials>PL</Initials>
      <Group>Services</Group>
      <MaxUnits>2</MaxUnits>
      <StandardRate>60</StandardRate>
    </Resource>
    <Resource>
      <UID>10</UID>
      <ID>10</ID>
      <Name>HVAC engineers</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <Initials>HV</Initials>
      <Group>Services</Group>
      <MaxUnits>2</MaxUnits>
      <StandardRate>68</StandardRate>
    </Resource>
    <Resource>
      <UID>11</UID>
      <ID>11</ID>
      <Name>Finishing crew</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <Initials>FC</Initials>
      <Group>Trades</Group>
      <MaxUnits>4</MaxUnits>
      <StandardRate>45</StandardRate>
    </Resource>
  </Resources>
  <Assignments>
    <Assignment>
      <UID>1</UID>
      <TaskUID>4</TaskUID>
      <ResourceUID>1</ResourceUID>
      <PercentWorkComplete>100</PercentWorkComplete>
      <ActualFinish>2027-01-15T17:00:00</ActualFinish>
      <ActualStart>2027-01-04T08:00:00</ActualStart>
      <ActualWork>PT80H0M0S</ActualWork>
      <Finish>2027-01-15T17:00:00</Finish>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <Start>2027-01-04T08:00:00</Start>
      <Units>1</Units>
      <Work>PT80H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>2</UID>
      <TaskUID>5</TaskUID>
      <ResourceUID>2</ResourceUID>
      <PercentWorkComplete>100</PercentWorkComplete>
      <ActualFinish>2027-01-07T17:00:00</ActualFinish>
      <ActualStart>2027-01-04T08:00:00</ActualStart>
      <ActualWork>PT16H0M0S</ActualWork>
      <Finish>2027-01-07T17:00:00</Finish>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <Start>2027-01-04T08:00:00</Start>
      <Units>0.5</Units>
      <Work>PT16H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>3</UID>
      <TaskUID>6</TaskUID>
      <ResourceUID>2</ResourceUID>
      <PercentWorkComplete>100</PercentWorkComplete>
      <ActualFinish>2027-01-12T17:00:00</ActualFinish>
      <ActualStart>2027-01-08T08:00:00</ActualStart>
      <ActualWork>PT24H0M0S</ActualWork>
      <Finish>2027-01-12T17:00:00</Finish>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <Start>2027-01-08T08:00:00</Start>
      <Units>1</Units>
      <Work>PT24H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>4</UID>
      <TaskUID>7</TaskUID>
      <ResourceUID>1</ResourceUID>
      <PercentWorkComplete>100</PercentWorkComplete>
      <ActualFinish>2027-01-22T17:00:00</ActualFinish>
      <ActualStart>2027-01-18T08:00:00</ActualStart>
      <ActualWork>PT20H0M0S</ActualWork>
      <Finish>2027-01-22T17:00:00</Finish>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <Start>2027-01-18T08:00:00</Start>
      <Units>0.5</Units>
      <Work>PT20H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>5</UID>
      <TaskUID>7</TaskUID>
      <ResourceUID>2</ResourceUID>
      <PercentWorkComplete>100</PercentWorkComplete>
      <ActualFinish>2027-01-22T17:00:00</ActualFinish>
      <ActualStart>2027-01-18T08:00:00</ActualStart>
      <ActualWork>PT40H0M0S</ActualWork>
      <Finish>2027-01-22T17:00:00</Finish>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <Start>2027-01-18T08:00:00</Start>
      <Units>1</Units>
      <Work>PT40H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>6</UID>
      <TaskUID>10</TaskUID>
      <ResourceUID>2</ResourceUID>
      <PercentWorkComplete>100</PercentWorkComplete>
      <ActualFinish>2027-02-01T17:00:00</ActualFinish>
      <ActualStart>2027-01-25T08:00:00</ActualStart>
      <ActualWork>PT96H0M0S</ActualWork>
      <Finish>2027-02-01T17:00:00</Finish>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <Start>2027-01-25T08:00:00</Start>
      <Units>2</Units>
      <Work>PT96H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>7</UID>
      <TaskUID>11</TaskUID>
      <ResourceUID>3</ResourceUID>
      <PercentWorkComplete>100</PercentWorkComplete>
      <ActualFinish>2027-02-11T17:00:00</ActualFinish>
      <ActualStart>2027-02-02T08:00:00</ActualStart>
      <ActualWork>PT64H0M0S</ActualWork>
      <Finish>2027-02-11T17:00:00</Finish>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <Start>2027-02-02T08:00:00</Start>
      <Units>1</Units>
      <Work>PT64H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>8</UID>
      <TaskUID>12</TaskUID>
      <ResourceUID>2</ResourceUID>
      <PercentWorkComplete>100</PercentWorkComplete>
      <ActualFinish>2027-02-05T17:00:00</ActualFinish>
      <ActualStart>2027-02-02T08:00:00</ActualStart>
      <ActualWork>PT32H0M0S</ActualWork>
      <Finish>2027-02-05T17:00:00</Finish>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <Start>2027-02-02T08:00:00</Start>
      <Units>1</Units>
      <Work>PT32H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>9</UID>
      <TaskUID>14</TaskUID>
      <ResourceUID>3</ResourceUID>
      <PercentWorkComplete>100</PercentWorkComplete>
      <ActualFinish>2027-02-19T17:00:00</ActualFinish>
      <ActualStart>2027-02-12T08:00:00</ActualStart>
      <ActualWork>PT96H0M0S</ActualWork>
      <Finish>2027-02-19T17:00:00</Finish>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <Start>2027-02-12T08:00:00</Start>
      <Units>2</Units>
      <Work>PT96H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>10</UID>
      <TaskUID>15</TaskUID>
      <ResourceUID>3</ResourceUID>
      <PercentWorkComplete>100</PercentWorkComplete>
      <ActualFinish>2027-02-24T17:00:00</ActualFinish>
      <ActualStart>2027-02-22T08:00:00</ActualStart>
      <ActualWork>PT72H0M0S</ActualWork>
      <Finish>2027-02-24T17:00:00</Finish>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <Start>2027-02-22T08:00:00</Start>
      <Units>3</Units>
      <Work>PT72H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>11</UID>
      <TaskUID>19</TaskUID>
      <ResourceUID>4</ResourceUID>
      <PercentWorkComplete>100</PercentWorkComplete>
      <ActualFinish>2027-03-04T17:00:00</ActualFinish>
      <ActualStart>2027-02-25T08:00:00</ActualStart>
      <ActualWork>PT144H0M0S</ActualWork>
      <Finish>2027-03-04T17:00:00</Finish>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <Start>2027-02-25T08:00:00</Start>
      <Units>3</Units>
      <Work>PT144H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>12</UID>
      <TaskUID>19</TaskUID>
      <ResourceUID>5</ResourceUID>
      <PercentWorkComplete>100</PercentWorkComplete>
      <ActualFinish>2027-03-04T17:00:00</ActualFinish>
      <ActualStart>2027-02-25T08:00:00</ActualStart>
      <ActualWork>PT48H0M0S</ActualWork>
      <Finish>2027-03-04T17:00:00</Finish>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <Start>2027-02-25T08:00:00</Start>
      <Units>1</Units>
      <Work>PT48H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>13</UID>
      <TaskUID>20</TaskUID>
      <ResourceUID>4</ResourceUID>
      <PercentWorkComplete>34</PercentWorkComplete>
      <ActualStart>2027-03-05T08:00:00</ActualStart>
      <ActualWork>PT48H58M0S</ActualWork>
      <Finish>2027-03-12T17:00:00</Finish>
      <RemainingWork>PT95H2M0S</RemainingWork>
      <Start>2027-03-05T08:00:00</Start>
      <Units>3</Units>
      <Work>PT144H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>14</UID>
      <TaskUID>20</TaskUID>
      <ResourceUID>5</ResourceUID>
      <PercentWorkComplete>34</PercentWorkComplete>
      <ActualStart>2027-03-05T08:00:00</ActualStart>
      <ActualWork>PT16H19M0S</ActualWork>
      <Finish>2027-03-12T17:00:00</Finish>
      <RemainingWork>PT31H41M0S</RemainingWork>
      <Start>2027-03-05T08:00:00</Start>
      <Units>1</Units>
      <Work>PT48H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>15</UID>
      <TaskUID>21</TaskUID>
      <ResourceUID>3</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-03-19T17:00:00</Finish>
      <RemainingWork>PT80H0M0S</RemainingWork>
      <Start>2027-03-15T08:00:00</Start>
      <Units>2</Units>
      <Work>PT80H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>16</UID>
      <TaskUID>23</TaskUID>
      <ResourceUID>6</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-03-26T17:00:00</Finish>
      <RemainingWork>PT80H0M0S</RemainingWork>
      <Start>2027-03-22T08:00:00</Start>
      <Units>2</Units>
      <Work>PT80H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>17</UID>
      <TaskUID>24</TaskUID>
      <ResourceUID>6</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-03-26T17:00:00</Finish>
      <RemainingWork>PT160H0M0S</RemainingWork>
      <Start>2027-03-15T08:00:00</Start>
      <Units>2</Units>
      <Work>PT160H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>18</UID>
      <TaskUID>25</TaskUID>
      <ResourceUID>7</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-04-05T17:00:00</Finish>
      <RemainingWork>PT96H0M0S</RemainingWork>
      <Start>2027-03-29T08:00:00</Start>
      <Units>2</Units>
      <Work>PT96H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>19</UID>
      <TaskUID>30</TaskUID>
      <ResourceUID>8</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-04-15T17:00:00</Finish>
      <RemainingWork>PT128H0M0S</RemainingWork>
      <Start>2027-04-06T08:00:00</Start>
      <Units>2</Units>
      <Work>PT128H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>20</UID>
      <TaskUID>31</TaskUID>
      <ResourceUID>8</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-05-20T17:00:00</Finish>
      <RemainingWork>PT80H0M0S</RemainingWork>
      <Start>2027-05-14T08:00:00</Start>
      <Units>2</Units>
      <Work>PT80H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>21</UID>
      <TaskUID>33</TaskUID>
      <ResourceUID>9</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-04-14T17:00:00</Finish>
      <RemainingWork>PT112H0M0S</RemainingWork>
      <Start>2027-04-06T08:00:00</Start>
      <Units>2</Units>
      <Work>PT112H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>22</UID>
      <TaskUID>34</TaskUID>
      <ResourceUID>9</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-05-19T17:00:00</Finish>
      <RemainingWork>PT32H0M0S</RemainingWork>
      <Start>2027-05-14T08:00:00</Start>
      <Units>1</Units>
      <Work>PT32H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>23</UID>
      <TaskUID>35</TaskUID>
      <ResourceUID>10</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-04-19T17:00:00</Finish>
      <RemainingWork>PT160H0M0S</RemainingWork>
      <Start>2027-04-06T08:00:00</Start>
      <Units>2</Units>
      <Work>PT160H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>24</UID>
      <TaskUID>36</TaskUID>
      <ResourceUID>8</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-04-15T17:00:00</Finish>
      <RemainingWork>PT32H0M0S</RemainingWork>
      <Start>2027-04-06T08:00:00</Start>
      <Units>0.5</Units>
      <Work>PT32H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>25</UID>
      <TaskUID>38</TaskUID>
      <ResourceUID>6</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-04-28T17:00:00</Finish>
      <RemainingWork>PT240H0M0S</RemainingWork>
      <Start>2027-04-15T08:00:00</Start>
      <Units>3</Units>
      <Work>PT240H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>26</UID>
      <TaskUID>39</TaskUID>
      <ResourceUID>6</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-05-05T17:00:00</Finish>
      <RemainingWork>PT80H0M0S</RemainingWork>
      <Start>2027-04-29T08:00:00</Start>
      <Units>2</Units>
      <Work>PT80H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>27</UID>
      <TaskUID>40</TaskUID>
      <ResourceUID>11</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-05-13T17:00:00</Finish>
      <RemainingWork>PT96H0M0S</RemainingWork>
      <Start>2027-05-06T08:00:00</Start>
      <Units>2</Units>
      <Work>PT96H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>28</UID>
      <TaskUID>41</TaskUID>
      <ResourceUID>11</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-05-13T17:00:00</Finish>
      <RemainingWork>PT80H0M0S</RemainingWork>
      <Start>2027-05-07T08:00:00</Start>
      <Units>2</Units>
      <Work>PT80H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>29</UID>
      <TaskUID>43</TaskUID>
      <ResourceUID>1</ResourceUID>
      <PercentWorkComplete>84</PercentWorkComplete>
      <ActualStart>2027-01-18T08:00:00</ActualStart>
      <ActualWork>PT28H54M0S</ActualWork>
      <Finish>2027-03-17T17:00:00</Finish>
      <RemainingWork>PT5H30M0S</RemainingWork>
      <Start>2027-01-18T08:00:00</Start>
      <Units>0.1</Units>
      <Work>PT34H24M0S</Work>
    </Assignment>
    <Assignment>
      <UID>30</UID>
      <TaskUID>44</TaskUID>
      <ResourceUID>1</ResourceUID>
      <PercentWorkComplete>100</PercentWorkComplete>
      <ActualFinish>2027-02-12T17:00:00</ActualFinish>
      <ActualStart>2027-01-18T08:00:00</ActualStart>
      <ActualWork>PT16H0M0S</ActualWork>
      <Finish>2027-02-12T17:00:00</Finish>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <Start>2027-01-18T08:00:00</Start>
      <Units>0.1</Units>
      <Work>PT16H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>31</UID>
      <TaskUID>47</TaskUID>
      <ResourceUID>8</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-05-27T17:00:00</Finish>
      <RemainingWork>PT40H0M0S</RemainingWork>
      <Start>2027-05-21T08:00:00</Start>
      <Units>1</Units>
      <Work>PT40H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>32</UID>
      <TaskUID>47</TaskUID>
      <ResourceUID>10</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-05-27T17:00:00</Finish>
      <RemainingWork>PT40H0M0S</RemainingWork>
      <Start>2027-05-21T08:00:00</Start>
      <Units>1</Units>
      <Work>PT40H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>33</UID>
      <TaskUID>48</TaskUID>
      <ResourceUID>1</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-05-31T17:00:00</Finish>
      <RemainingWork>PT16H0M0S</RemainingWork>
      <Start>2027-05-28T08:00:00</Start>
      <Units>1</Units>
      <Work>PT16H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>34</UID>
      <TaskUID>50</TaskUID>
      <ResourceUID>11</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-06-02T17:00:00</Finish>
      <RemainingWork>PT64H0M0S</RemainingWork>
      <Start>2027-05-28T08:00:00</Start>
      <Units>2</Units>
      <Work>PT64H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>35</UID>
      <TaskUID>51</TaskUID>
      <ResourceUID>2</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-05-21T17:00:00</Finish>
      <RemainingWork>PT128H0M0S</RemainingWork>
      <Start>2027-05-12T08:00:00</Start>
      <Units>2</Units>
      <Work>PT128H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>36</UID>
      <TaskUID>52</TaskUID>
      <ResourceUID>1</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-06-03T17:00:00</Finish>
      <RemainingWork>PT24H0M0S</RemainingWork>
      <Start>2027-06-01T08:00:00</Start>
      <Units>1</Units>
      <Work>PT24H0M0S</Work>
    </Assignment>
  </Assignments>
</Project>