<?xml version="1.0" encoding="UTF-8" standalone="yes"?>
<Project xmlns="http://schemas.microsoft.com/project">
  <SaveVersion>14</SaveVersion>
  <Name>Head office move</Name>
  <Title>Head office move</Title>
  <ScheduleFromStart>1</ScheduleFromStart>
  <StartDate>2027-01-04T08:00:00</StartDate>
  <FinishDate>2027-04-05T17:00:00</FinishDate>
  <CalendarUID>1</CalendarUID>
  <DefaultStartTime>08:00:00</DefaultStartTime>
  <DefaultFinishTime>17:00:00</DefaultFinishTime>
  <DurationFormat>7</DurationFormat>
  <StatusDate>2027-02-08T17:00:00</StatusDate>
  <NewTasksAreManual>0</NewTasksAreManual>
  <ProjectExternallyEdited>0</ProjectExternallyEdited>
  <ExtendedAttributes>
    <ExtendedAttribute>
      <FieldID>188743783</FieldID>
      <FieldName>Duration1</FieldName>
      <Alias>Optimistic Duration</Alias>
    </ExtendedAttribute>
    <ExtendedAttribute>
      <FieldID>188743785</FieldID>
      <FieldName>Duration3</FieldName>
      <Alias>Pessimistic Duration</Alias>
    </ExtendedAttribute>
  </ExtendedAttributes>
  <Calendars>
    <Calendar>
      <UID>1</UID>
      <Name>Standard</Name>
      <IsBaseCalendar>1</IsBaseCalendar>
      <BaseCalendarUID>-1</BaseCalendarUID>
      <WeekDays>
        <WeekDay>
          <DayType>1</DayType>
          <DayWorking>0</DayWorking>
        </WeekDay>
        <WeekDay>
          <DayType>2</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>3</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>4</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>5</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>6</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>7</DayType>
          <DayWorking>0</DayWorking>
        </WeekDay>
      </WeekDays>
    </Calendar>
  </Calendars>
  <Tasks>
    <Task>
      <UID>0</UID>
      <ID>0</ID>
      <Name>Head office move</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>0</OutlineNumber>
      <OutlineLevel>0</OutlineLevel>
      <Start>2027-01-04T08:00:00</Start>
      <Finish>2027-04-05T17:00:00</Finish>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-04-05T17:00:00</Finish>
        <Work>PT1584H0M0S</Work>
        <Cost>9105000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-01-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-05T08:00:00</Start>
        <Finish>2027-01-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-06T08:00:00</Start>
        <Finish>2027-01-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-07T08:00:00</Start>
        <Finish>2027-01-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-08T08:00:00</Start>
        <Finish>2027-01-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-11T08:00:00</Start>
        <Finish>2027-01-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-12T08:00:00</Start>
        <Finish>2027-01-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-13T08:00:00</Start>
        <Finish>2027-01-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-14T08:00:00</Start>
        <Finish>2027-01-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-15T08:00:00</Start>
        <Finish>2027-01-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-18T08:00:00</Start>
        <Finish>2027-01-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-19T08:00:00</Start>
        <Finish>2027-01-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-20T08:00:00</Start>
        <Finish>2027-01-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT26H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-21T08:00:00</Start>
        <Finish>2027-01-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT20H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-22T08:00:00</Start>
        <Finish>2027-01-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-01-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-26T08:00:00</Start>
        <Finish>2027-01-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-01-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT20H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-28T08:00:00</Start>
        <Finish>2027-01-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT20H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-29T08:00:00</Start>
        <Finish>2027-01-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT20H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-01T08:00:00</Start>
        <Finish>2027-02-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT20H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-02T08:00:00</Start>
        <Finish>2027-02-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-03T08:00:00</Start>
        <Finish>2027-02-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-04T08:00:00</Start>
        <Finish>2027-02-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-05T08:00:00</Start>
        <Finish>2027-02-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-08T08:00:00</Start>
        <Finish>2027-02-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-09T08:00:00</Start>
        <Finish>2027-02-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-10T08:00:00</Start>
        <Finish>2027-02-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT18H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-12T08:00:00</Start>
        <Finish>2027-02-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT26H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-15T08:00:00</Start>
        <Finish>2027-02-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT26H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-16T08:00:00</Start>
        <Finish>2027-02-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT26H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-17T08:00:00</Start>
        <Finish>2027-02-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT26H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-18T08:00:00</Start>
        <Finish>2027-02-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT18H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-19T08:00:00</Start>
        <Finish>2027-02-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT34H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-22T08:00:00</Start>
        <Finish>2027-02-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT34H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-23T08:00:00</Start>
        <Finish>2027-02-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT34H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-24T08:00:00</Start>
        <Finish>2027-02-25T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT48H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-25T08:00:00</Start>
        <Finish>2027-02-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT48H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-26T08:00:00</Start>
        <Finish>2027-02-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT48H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-01T08:00:00</Start>
        <Finish>2027-03-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT40H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-02T08:00:00</Start>
        <Finish>2027-03-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT40H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-03T08:00:00</Start>
        <Finish>2027-03-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT40H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-04T08:00:00</Start>
        <Finish>2027-03-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT40H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-05T08:00:00</Start>
        <Finish>2027-03-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT40H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-08T08:00:00</Start>
        <Finish>2027-03-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT48H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-09T08:00:00</Start>
        <Finish>2027-03-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT40H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-10T08:00:00</Start>
        <Finish>2027-03-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-11T08:00:00</Start>
        <Finish>2027-03-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-12T08:00:00</Start>
        <Finish>2027-03-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-15T08:00:00</Start>
        <Finish>2027-03-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-16T08:00:00</Start>
        <Finish>2027-03-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-17T08:00:00</Start>
        <Finish>2027-03-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-18T08:00:00</Start>
        <Finish>2027-03-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-19T08:00:00</Start>
        <Finish>2027-03-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-22T08:00:00</Start>
        <Finish>2027-03-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT72H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-23T08:00:00</Start>
        <Finish>2027-03-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT72H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-24T08:00:00</Start>
        <Finish>2027-03-25T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT40H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-25T08:00:00</Start>
        <Finish>2027-03-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT40H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-26T08:00:00</Start>
        <Finish>2027-03-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-29T08:00:00</Start>
        <Finish>2027-03-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-30T08:00:00</Start>
        <Finish>2027-03-31T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-31T08:00:00</Start>
        <Finish>2027-04-01T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-01T08:00:00</Start>
        <Finish>2027-04-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-02T08:00:00</Start>
        <Finish>2027-04-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-05T08:00:00</Start>
        <Finish>2027-04-05T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-01-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-05T08:00:00</Start>
        <Finish>2027-01-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-06T08:00:00</Start>
        <Finish>2027-01-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-07T08:00:00</Start>
        <Finish>2027-01-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-08T08:00:00</Start>
        <Finish>2027-01-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>106000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-11T08:00:00</Start>
        <Finish>2027-01-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>106000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-12T08:00:00</Start>
        <Finish>2027-01-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>106000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-13T08:00:00</Start>
        <Finish>2027-01-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>106000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-14T08:00:00</Start>
        <Finish>2027-01-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>106000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-15T08:00:00</Start>
        <Finish>2027-01-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>104000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-18T08:00:00</Start>
        <Finish>2027-01-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>104000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-19T08:00:00</Start>
        <Finish>2027-01-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>104000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-20T08:00:00</Start>
        <Finish>2027-01-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>180000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-21T08:00:00</Start>
        <Finish>2027-01-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>133000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-22T08:00:00</Start>
        <Finish>2027-01-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>77000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-01-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>77000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-26T08:00:00</Start>
        <Finish>2027-01-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>77000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-01-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>141000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-28T08:00:00</Start>
        <Finish>2027-01-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>141000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-29T08:00:00</Start>
        <Finish>2027-01-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>141000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-01T08:00:00</Start>
        <Finish>2027-02-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>141000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-02T08:00:00</Start>
        <Finish>2027-02-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>77000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-03T08:00:00</Start>
        <Finish>2027-02-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>77000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-04T08:00:00</Start>
        <Finish>2027-02-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>77000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-05T08:00:00</Start>
        <Finish>2027-02-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>77000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-08T08:00:00</Start>
        <Finish>2027-02-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>81000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-09T08:00:00</Start>
        <Finish>2027-02-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>81000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-10T08:00:00</Start>
        <Finish>2027-02-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>81000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>116000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-12T08:00:00</Start>
        <Finish>2027-02-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>164000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-15T08:00:00</Start>
        <Finish>2027-02-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>164000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-16T08:00:00</Start>
        <Finish>2027-02-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>164000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-17T08:00:00</Start>
        <Finish>2027-02-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>164000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-18T08:00:00</Start>
        <Finish>2027-02-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>120000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-19T08:00:00</Start>
        <Finish>2027-02-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>224000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-22T08:00:00</Start>
        <Finish>2027-02-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>224000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-23T08:00:00</Start>
        <Finish>2027-02-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>224000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-24T08:00:00</Start>
        <Finish>2027-02-25T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>288000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-25T08:00:00</Start>
        <Finish>2027-02-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>288000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-26T08:00:00</Start>
        <Finish>2027-02-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>288000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-01T08:00:00</Start>
        <Finish>2027-03-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>236000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-02T08:00:00</Start>
        <Finish>2027-03-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>236000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-03T08:00:00</Start>
        <Finish>2027-03-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>236000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-04T08:00:00</Start>
        <Finish>2027-03-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>236000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-05T08:00:00</Start>
        <Finish>2027-03-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>236000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-08T08:00:00</Start>
        <Finish>2027-03-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>300000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-09T08:00:00</Start>
        <Finish>2027-03-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>236000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-10T08:00:00</Start>
        <Finish>2027-03-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>196000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-11T08:00:00</Start>
        <Finish>2027-03-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>176000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-12T08:00:00</Start>
        <Finish>2027-03-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>176000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-15T08:00:00</Start>
        <Finish>2027-03-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>72000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-16T08:00:00</Start>
        <Finish>2027-03-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>72000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-17T08:00:00</Start>
        <Finish>2027-03-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>64000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-18T08:00:00</Start>
        <Finish>2027-03-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>64000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-19T08:00:00</Start>
        <Finish>2027-03-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>64000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-22T08:00:00</Start>
        <Finish>2027-03-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>312000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-23T08:00:00</Start>
        <Finish>2027-03-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>312000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-24T08:00:00</Start>
        <Finish>2027-03-25T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>148000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-25T08:00:00</Start>
        <Finish>2027-03-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>148000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-26T08:00:00</Start>
        <Finish>2027-03-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>72000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-29T08:00:00</Start>
        <Finish>2027-03-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>72000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-30T08:00:00</Start>
        <Finish>2027-03-31T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>72000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-31T08:00:00</Start>
        <Finish>2027-04-01T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-01T08:00:00</Start>
        <Finish>2027-04-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>48000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-02T08:00:00</Start>
        <Finish>2027-04-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-05T08:00:00</Start>
        <Finish>2027-04-05T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>1</UID>
      <ID>1</ID>
      <Name>Planning</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-04T08:00:00</Start>
      <Finish>2027-02-11T17:00:00</Finish>
      <Duration>PT232H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>86</PercentComplete>
      <Cost>1738000</Cost>
      <ActualCost>1514000</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-02-11T17:00:00</Finish>
        <Duration>PT232H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT262H0M0S</Work>
        <Cost>1738000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-01-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-05T08:00:00</Start>
        <Finish>2027-01-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-06T08:00:00</Start>
        <Finish>2027-01-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-07T08:00:00</Start>
        <Finish>2027-01-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-08T08:00:00</Start>
        <Finish>2027-01-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-11T08:00:00</Start>
        <Finish>2027-01-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-12T08:00:00</Start>
        <Finish>2027-01-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-13T08:00:00</Start>
        <Finish>2027-01-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-14T08:00:00</Start>
        <Finish>2027-01-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-15T08:00:00</Start>
        <Finish>2027-01-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-18T08:00:00</Start>
        <Finish>2027-01-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-19T08:00:00</Start>
        <Finish>2027-01-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-20T08:00:00</Start>
        <Finish>2027-01-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT10H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-21T08:00:00</Start>
        <Finish>2027-01-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT10H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-22T08:00:00</Start>
        <Finish>2027-01-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT10H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-01-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT10H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-26T08:00:00</Start>
        <Finish>2027-01-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT10H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-01-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-28T08:00:00</Start>
        <Finish>2027-01-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-29T08:00:00</Start>
        <Finish>2027-01-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-02-01T08:00:00</Start>
        <Finish>2027-02-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-02-02T08:00:00</Start>
        <Finish>2027-02-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-02-03T08:00:00</Start>
        <Finish>2027-02-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-02-04T08:00:00</Start>
        <Finish>2027-02-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-02-05T08:00:00</Start>
        <Finish>2027-02-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-02-08T08:00:00</Start>
        <Finish>2027-02-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-02-09T08:00:00</Start>
        <Finish>2027-02-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-02-10T08:00:00</Start>
        <Finish>2027-02-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-11T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-01-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-05T08:00:00</Start>
        <Finish>2027-01-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-06T08:00:00</Start>
        <Finish>2027-01-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-07T08:00:00</Start>
        <Finish>2027-01-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-08T08:00:00</Start>
        <Finish>2027-01-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>78000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-11T08:00:00</Start>
        <Finish>2027-01-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>78000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-12T08:00:00</Start>
        <Finish>2027-01-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>78000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-13T08:00:00</Start>
        <Finish>2027-01-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>78000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-14T08:00:00</Start>
        <Finish>2027-01-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>78000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-15T08:00:00</Start>
        <Finish>2027-01-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>48000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-18T08:00:00</Start>
        <Finish>2027-01-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>48000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-19T08:00:00</Start>
        <Finish>2027-01-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>48000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-20T08:00:00</Start>
        <Finish>2027-01-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>68000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-21T08:00:00</Start>
        <Finish>2027-01-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>68000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-22T08:00:00</Start>
        <Finish>2027-01-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>68000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-01-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>68000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-26T08:00:00</Start>
        <Finish>2027-01-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>68000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-01-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>52000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-28T08:00:00</Start>
        <Finish>2027-01-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>52000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-29T08:00:00</Start>
        <Finish>2027-01-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>52000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-02-01T08:00:00</Start>
        <Finish>2027-02-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>52000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-02-02T08:00:00</Start>
        <Finish>2027-02-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>52000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-02-03T08:00:00</Start>
        <Finish>2027-02-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>52000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-02-04T08:00:00</Start>
        <Finish>2027-02-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>52000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-02-05T08:00:00</Start>
        <Finish>2027-02-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>52000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-02-08T08:00:00</Start>
        <Finish>2027-02-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-02-09T08:00:00</Start>
        <Finish>2027-02-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-02-10T08:00:00</Start>
        <Finish>2027-02-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-11T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>2</UID>
      <ID>2</ID>
      <Name>Move approved</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-04T08:00:00</Start>
      <Finish>2027-01-04T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>100</PercentComplete>
      <ActualStart>2027-01-04T08:00:00</ActualStart>
      <ActualFinish>2027-01-04T08:00:00</ActualFinish>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-01-04T08:00:00</Finish>
        <Duration>PT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
      </Baseline>
    </Task>
    <Task>
      <UID>3</UID>
      <ID>3</ID>
      <Name>Requirements</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-04T08:00:00</Start>
      <Finish>2027-01-19T17:00:00</Finish>
      <Duration>PT96H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>100</PercentComplete>
      <Cost>758000</Cost>
      <ActualCost>758000</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-01-19T17:00:00</Finish>
        <Duration>PT96H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT116H0M0S</Work>
        <Cost>758000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-01-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-05T08:00:00</Start>
        <Finish>2027-01-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-06T08:00:00</Start>
        <Finish>2027-01-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-07T08:00:00</Start>
        <Finish>2027-01-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-08T08:00:00</Start>
        <Finish>2027-01-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-11T08:00:00</Start>
        <Finish>2027-01-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-12T08:00:00</Start>
        <Finish>2027-01-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-13T08:00:00</Start>
        <Finish>2027-01-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-14T08:00:00</Start>
        <Finish>2027-01-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-15T08:00:00</Start>
        <Finish>2027-01-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-18T08:00:00</Start>
        <Finish>2027-01-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-19T08:00:00</Start>
        <Finish>2027-01-19T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-01-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-05T08:00:00</Start>
        <Finish>2027-01-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-06T08:00:00</Start>
        <Finish>2027-01-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-07T08:00:00</Start>
        <Finish>2027-01-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-08T08:00:00</Start>
        <Finish>2027-01-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>78000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-11T08:00:00</Start>
        <Finish>2027-01-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>78000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-12T08:00:00</Start>
        <Finish>2027-01-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>78000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-13T08:00:00</Start>
        <Finish>2027-01-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>78000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-14T08:00:00</Start>
        <Finish>2027-01-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>78000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-15T08:00:00</Start>
        <Finish>2027-01-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>48000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-18T08:00:00</Start>
        <Finish>2027-01-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>48000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-19T08:00:00</Start>
        <Finish>2027-01-19T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>48000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>4</UID>
      <ID>4</ID>
      <Name>Survey current space and headcount</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.2.1</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-04T08:00:00</Start>
      <Finish>2027-01-07T17:00:00</Finish>
      <Duration>PT32H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT32H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>100</PercentComplete>
      <PercentWorkComplete>100</PercentWorkComplete>
      <Cost>224000</Cost>
      <ActualStart>2027-01-04T08:00:00</ActualStart>
      <ActualFinish>2027-01-07T17:00:00</ActualFinish>
      <ActualCost>224000</ActualCost>
      <ActualWork>PT32H0M0S</ActualWork>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>2</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-01-07T17:00:00</Finish>
        <Duration>PT32H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT32H0M0S</Work>
        <Cost>224000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>4</UID>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-01-07T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>4</UID>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-01-07T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>224000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>5</UID>
      <ID>5</ID>
      <Name>Workplace brief and seating plan</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.2.2</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-08T08:00:00</Start>
      <Finish>2027-01-14T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT60H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>100</PercentComplete>
      <PercentWorkComplete>100</PercentWorkComplete>
      <Cost>390000</Cost>
      <ActualStart>2027-01-08T08:00:00</ActualStart>
      <ActualFinish>2027-01-14T17:00:00</ActualFinish>
      <ActualCost>390000</ActualCost>
      <ActualWork>PT60H0M0S</ActualWork>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>4</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-08T08:00:00</Start>
        <Finish>2027-01-14T17:00:00</Finish>
        <Duration>PT40H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT60H0M0S</Work>
        <Cost>390000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>5</UID>
        <Start>2027-01-08T08:00:00</Start>
        <Finish>2027-01-14T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT60H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>5</UID>
        <Start>2027-01-08T08:00:00</Start>
        <Finish>2027-01-14T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>390000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>6</UID>
      <ID>6</ID>
      <Name>Move budget approved</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.2.3</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-15T08:00:00</Start>
      <Finish>2027-01-19T17:00:00</Finish>
      <Duration>PT24H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT24H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>100</PercentComplete>
      <PercentWorkComplete>100</PercentWorkComplete>
      <Cost>144000</Cost>
      <ActualStart>2027-01-15T08:00:00</ActualStart>
      <ActualFinish>2027-01-19T17:00:00</ActualFinish>
      <ActualCost>144000</ActualCost>
      <ActualWork>PT24H0M0S</ActualWork>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>5</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-15T08:00:00</Start>
        <Finish>2027-01-19T17:00:00</Finish>
        <Duration>PT24H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT24H0M0S</Work>
        <Cost>144000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>6</UID>
        <Start>2027-01-15T08:00:00</Start>
        <Finish>2027-01-19T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>6</UID>
        <Start>2027-01-15T08:00:00</Start>
        <Finish>2027-01-19T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>144000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>7</UID>
      <ID>7</ID>
      <Name>New premises</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-20T08:00:00</Start>
      <Finish>2027-02-11T17:00:00</Finish>
      <Duration>PT136H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>76</PercentComplete>
      <Cost>980000</Cost>
      <ActualCost>756000</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-20T08:00:00</Start>
        <Finish>2027-02-11T17:00:00</Finish>
        <Duration>PT136H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT146H0M0S</Work>
        <Cost>980000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-01-20T08:00:00</Start>
        <Finish>2027-01-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT10H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-01-21T08:00:00</Start>
        <Finish>2027-01-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT10H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-01-22T08:00:00</Start>
        <Finish>2027-01-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT10H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-01-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT10H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-01-26T08:00:00</Start>
        <Finish>2027-01-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT10H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-01-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-01-28T08:00:00</Start>
        <Finish>2027-01-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-01-29T08:00:00</Start>
        <Finish>2027-01-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-02-01T08:00:00</Start>
        <Finish>2027-02-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-02-02T08:00:00</Start>
        <Finish>2027-02-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-02-03T08:00:00</Start>
        <Finish>2027-02-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-02-04T08:00:00</Start>
        <Finish>2027-02-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-02-05T08:00:00</Start>
        <Finish>2027-02-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-02-08T08:00:00</Start>
        <Finish>2027-02-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-02-09T08:00:00</Start>
        <Finish>2027-02-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-02-10T08:00:00</Start>
        <Finish>2027-02-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-11T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-01-20T08:00:00</Start>
        <Finish>2027-01-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>68000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-01-21T08:00:00</Start>
        <Finish>2027-01-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>68000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-01-22T08:00:00</Start>
        <Finish>2027-01-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>68000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-01-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>68000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-01-26T08:00:00</Start>
        <Finish>2027-01-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>68000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-01-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>52000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-01-28T08:00:00</Start>
        <Finish>2027-01-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>52000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-01-29T08:00:00</Start>
        <Finish>2027-01-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>52000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-02-01T08:00:00</Start>
        <Finish>2027-02-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>52000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-02-02T08:00:00</Start>
        <Finish>2027-02-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>52000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-02-03T08:00:00</Start>
        <Finish>2027-02-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>52000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-02-04T08:00:00</Start>
        <Finish>2027-02-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>52000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-02-05T08:00:00</Start>
        <Finish>2027-02-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>52000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-02-08T08:00:00</Start>
        <Finish>2027-02-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-02-09T08:00:00</Start>
        <Finish>2027-02-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-02-10T08:00:00</Start>
        <Finish>2027-02-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-11T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>8</UID>
      <ID>8</ID>
      <Name>Sign the lease for the new office</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.3.1</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-20T08:00:00</Start>
      <Finish>2027-01-26T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT50H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>100</PercentComplete>
      <PercentWorkComplete>100</PercentWorkComplete>
      <Cost>340000</Cost>
      <ActualStart>2027-01-20T08:00:00</ActualStart>
      <ActualFinish>2027-01-26T17:00:00</ActualFinish>
      <ActualCost>340000</ActualCost>
      <ActualWork>PT50H0M0S</ActualWork>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>6</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-20T08:00:00</Start>
        <Finish>2027-01-26T17:00:00</Finish>
        <Duration>PT40H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT50H0M0S</Work>
        <Cost>340000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>8</UID>
        <Start>2027-01-20T08:00:00</Start>
        <Finish>2027-01-26T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT50H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>8</UID>
        <Start>2027-01-20T08:00:00</Start>
        <Finish>2027-01-26T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>340000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>9</UID>
      <ID>9</ID>
      <Name>Fit-out design</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.3.2</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-27T08:00:00</Start>
      <Finish>2027-02-05T17:00:00</Finish>
      <Duration>PT64H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT64H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>100</PercentComplete>
      <PercentWorkComplete>100</PercentWorkComplete>
      <Cost>416000</Cost>
      <ActualStart>2027-01-27T08:00:00</ActualStart>
      <ActualFinish>2027-02-05T17:00:00</ActualFinish>
      <ActualCost>416000</ActualCost>
      <ActualWork>PT64H0M0S</ActualWork>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>8</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-02-05T17:00:00</Finish>
        <Duration>PT64H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT64H0M0S</Work>
        <Cost>416000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>9</UID>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-02-05T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT64H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>9</UID>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-02-05T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>416000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>10</UID>
      <ID>10</ID>
      <Name>Landlord approval of the fit-out</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.3.3</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-08T08:00:00</Start>
      <Finish>2027-02-11T17:00:00</Finish>
      <Duration>PT32H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT32H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>224000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT32H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>9</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <ExtendedAttribute>
        <FieldID>188743783</FieldID>
        <Value>PT24H0M0S</Value>
      </ExtendedAttribute>
      <ExtendedAttribute>
        <FieldID>188743785</FieldID>
        <Value>PT48H0M0S</Value>
      </ExtendedAttribute>
      <Baseline>
        <Number>0</Number>
        <Start>2027-02-08T08:00:00</Start>
        <Finish>2027-02-11T17:00:00</Finish>
        <Duration>PT32H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT32H0M0S</Work>
        <Cost>224000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>10</UID>
        <Start>2027-02-08T08:00:00</Start>
        <Finish>2027-02-11T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>10</UID>
        <Start>2027-02-08T08:00:00</Start>
        <Finish>2027-02-11T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>224000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>11</UID>
      <ID>11</ID>
      <Name>Fit-out</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-15T08:00:00</Start>
      <Finish>2027-03-16T17:00:00</Finish>
      <Duration>PT344H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>28</PercentComplete>
      <Cost>4099000</Cost>
      <ActualCost>333425</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-15T08:00:00</Start>
        <Finish>2027-03-16T17:00:00</Finish>
        <Duration>PT344H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT670H0M0S</Work>
        <Cost>4063000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-01-15T08:00:00</Start>
        <Finish>2027-01-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-01-18T08:00:00</Start>
        <Finish>2027-01-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-01-19T08:00:00</Start>
        <Finish>2027-01-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-01-20T08:00:00</Start>
        <Finish>2027-01-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-01-21T08:00:00</Start>
        <Finish>2027-01-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-01-22T08:00:00</Start>
        <Finish>2027-01-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-01-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-01-26T08:00:00</Start>
        <Finish>2027-01-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-01-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-01-28T08:00:00</Start>
        <Finish>2027-01-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-01-29T08:00:00</Start>
        <Finish>2027-01-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-02-01T08:00:00</Start>
        <Finish>2027-02-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-02-02T08:00:00</Start>
        <Finish>2027-02-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-02-03T08:00:00</Start>
        <Finish>2027-02-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-02-04T08:00:00</Start>
        <Finish>2027-02-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-02-05T08:00:00</Start>
        <Finish>2027-02-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-02-08T08:00:00</Start>
        <Finish>2027-02-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-02-09T08:00:00</Start>
        <Finish>2027-02-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-02-10T08:00:00</Start>
        <Finish>2027-02-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-02-12T08:00:00</Start>
        <Finish>2027-02-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-02-15T08:00:00</Start>
        <Finish>2027-02-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-02-16T08:00:00</Start>
        <Finish>2027-02-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-02-17T08:00:00</Start>
        <Finish>2027-02-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-02-18T08:00:00</Start>
        <Finish>2027-02-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-02-19T08:00:00</Start>
        <Finish>2027-02-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-02-22T08:00:00</Start>
        <Finish>2027-02-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-02-23T08:00:00</Start>
        <Finish>2027-02-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-02-24T08:00:00</Start>
        <Finish>2027-02-25T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT48H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-02-25T08:00:00</Start>
        <Finish>2027-02-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT48H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-02-26T08:00:00</Start>
        <Finish>2027-02-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT48H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-03-01T08:00:00</Start>
        <Finish>2027-03-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT40H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-03-02T08:00:00</Start>
        <Finish>2027-03-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT40H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-03-03T08:00:00</Start>
        <Finish>2027-03-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-03-04T08:00:00</Start>
        <Finish>2027-03-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-03-05T08:00:00</Start>
        <Finish>2027-03-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-03-08T08:00:00</Start>
        <Finish>2027-03-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-03-09T08:00:00</Start>
        <Finish>2027-03-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-03-10T08:00:00</Start>
        <Finish>2027-03-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-03-11T08:00:00</Start>
        <Finish>2027-03-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-03-12T08:00:00</Start>
        <Finish>2027-03-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-03-15T08:00:00</Start>
        <Finish>2027-03-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-03-16T08:00:00</Start>
        <Finish>2027-03-16T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-01-15T08:00:00</Start>
        <Finish>2027-01-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-01-18T08:00:00</Start>
        <Finish>2027-01-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-01-19T08:00:00</Start>
        <Finish>2027-01-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-01-20T08:00:00</Start>
        <Finish>2027-01-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-01-21T08:00:00</Start>
        <Finish>2027-01-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-01-22T08:00:00</Start>
        <Finish>2027-01-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-01-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-01-26T08:00:00</Start>
        <Finish>2027-01-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-01-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-01-28T08:00:00</Start>
        <Finish>2027-01-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-01-29T08:00:00</Start>
        <Finish>2027-01-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-02-01T08:00:00</Start>
        <Finish>2027-02-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-02-02T08:00:00</Start>
        <Finish>2027-02-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-02-03T08:00:00</Start>
        <Finish>2027-02-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-02-04T08:00:00</Start>
        <Finish>2027-02-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-02-05T08:00:00</Start>
        <Finish>2027-02-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-02-08T08:00:00</Start>
        <Finish>2027-02-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-02-09T08:00:00</Start>
        <Finish>2027-02-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-02-10T08:00:00</Start>
        <Finish>2027-02-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-02-12T08:00:00</Start>
        <Finish>2027-02-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>104000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-02-15T08:00:00</Start>
        <Finish>2027-02-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>104000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-02-16T08:00:00</Start>
        <Finish>2027-02-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>104000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-02-17T08:00:00</Start>
        <Finish>2027-02-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>104000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-02-18T08:00:00</Start>
        <Finish>2027-02-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>104000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-02-19T08:00:00</Start>
        <Finish>2027-02-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>208000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-02-22T08:00:00</Start>
        <Finish>2027-02-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>208000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-02-23T08:00:00</Start>
        <Finish>2027-02-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>208000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-02-24T08:00:00</Start>
        <Finish>2027-02-25T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>288000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-02-25T08:00:00</Start>
        <Finish>2027-02-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>288000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-02-26T08:00:00</Start>
        <Finish>2027-02-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>288000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-03-01T08:00:00</Start>
        <Finish>2027-03-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>236000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-03-02T08:00:00</Start>
        <Finish>2027-03-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>236000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-03-03T08:00:00</Start>
        <Finish>2027-03-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>156000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-03-04T08:00:00</Start>
        <Finish>2027-03-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>156000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-03-05T08:00:00</Start>
        <Finish>2027-03-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>156000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-03-08T08:00:00</Start>
        <Finish>2027-03-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>156000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-03-09T08:00:00</Start>
        <Finish>2027-03-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>156000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-03-10T08:00:00</Start>
        <Finish>2027-03-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>156000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-03-11T08:00:00</Start>
        <Finish>2027-03-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>72000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-03-12T08:00:00</Start>
        <Finish>2027-03-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>72000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-03-15T08:00:00</Start>
        <Finish>2027-03-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>72000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-03-16T08:00:00</Start>
        <Finish>2027-03-16T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>72000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>12</UID>
      <ID>12</ID>
      <Name>Works</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-12T08:00:00</Start>
      <Finish>2027-03-10T17:00:00</Finish>
      <Duration>PT152H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <Cost>3416000</Cost>
      <ActualCost>0</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-02-12T08:00:00</Start>
        <Finish>2027-03-10T17:00:00</Finish>
        <Duration>PT152H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT544H0M0S</Work>
        <Cost>3416000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>12</UID>
        <Start>2027-02-12T08:00:00</Start>
        <Finish>2027-02-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>12</UID>
        <Start>2027-02-15T08:00:00</Start>
        <Finish>2027-02-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>12</UID>
        <Start>2027-02-16T08:00:00</Start>
        <Finish>2027-02-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>12</UID>
        <Start>2027-02-17T08:00:00</Start>
        <Finish>2027-02-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>12</UID>
        <Start>2027-02-18T08:00:00</Start>
        <Finish>2027-02-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>12</UID>
        <Start>2027-02-19T08:00:00</Start>
        <Finish>2027-02-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>12</UID>
        <Start>2027-02-22T08:00:00</Start>
        <Finish>2027-02-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>12</UID>
        <Start>2027-02-23T08:00:00</Start>
        <Finish>2027-02-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>12</UID>
        <Start>2027-02-24T08:00:00</Start>
        <Finish>2027-02-25T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT48H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>12</UID>
        <Start>2027-02-25T08:00:00</Start>
        <Finish>2027-02-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT48H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>12</UID>
        <Start>2027-02-26T08:00:00</Start>
        <Finish>2027-02-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT48H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>12</UID>
        <Start>2027-03-01T08:00:00</Start>
        <Finish>2027-03-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT40H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>12</UID>
        <Start>2027-03-02T08:00:00</Start>
        <Finish>2027-03-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT40H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>12</UID>
        <Start>2027-03-03T08:00:00</Start>
        <Finish>2027-03-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>12</UID>
        <Start>2027-03-04T08:00:00</Start>
        <Finish>2027-03-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>12</UID>
        <Start>2027-03-05T08:00:00</Start>
        <Finish>2027-03-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>12</UID>
        <Start>2027-03-08T08:00:00</Start>
        <Finish>2027-03-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>12</UID>
        <Start>2027-03-09T08:00:00</Start>
        <Finish>2027-03-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>12</UID>
        <Start>2027-03-10T08:00:00</Start>
        <Finish>2027-03-10T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>12</UID>
        <Start>2027-02-12T08:00:00</Start>
        <Finish>2027-02-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>104000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>12</UID>
        <Start>2027-02-15T08:00:00</Start>
        <Finish>2027-02-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>104000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>12</UID>
        <Start>2027-02-16T08:00:00</Start>
        <Finish>2027-02-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>104000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>12</UID>
        <Start>2027-02-17T08:00:00</Start>
        <Finish>2027-02-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>104000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>12</UID>
        <Start>2027-02-18T08:00:00</Start>
        <Finish>2027-02-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>104000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>12</UID>
        <Start>2027-02-19T08:00:00</Start>
        <Finish>2027-02-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>208000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>12</UID>
        <Start>2027-02-22T08:00:00</Start>
        <Finish>2027-02-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>208000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>12</UID>
        <Start>2027-02-23T08:00:00</Start>
        <Finish>2027-02-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>208000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>12</UID>
        <Start>2027-02-24T08:00:00</Start>
        <Finish>2027-02-25T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>288000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>12</UID>
        <Start>2027-02-25T08:00:00</Start>
        <Finish>2027-02-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>288000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>12</UID>
        <Start>2027-02-26T08:00:00</Start>
        <Finish>2027-02-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>288000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>12</UID>
        <Start>2027-03-01T08:00:00</Start>
        <Finish>2027-03-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>236000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>12</UID>
        <Start>2027-03-02T08:00:00</Start>
        <Finish>2027-03-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>236000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>12</UID>
        <Start>2027-03-03T08:00:00</Start>
        <Finish>2027-03-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>156000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>12</UID>
        <Start>2027-03-04T08:00:00</Start>
        <Finish>2027-03-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>156000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>12</UID>
        <Start>2027-03-05T08:00:00</Start>
        <Finish>2027-03-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>156000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>12</UID>
        <Start>2027-03-08T08:00:00</Start>
        <Finish>2027-03-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>156000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>12</UID>
        <Start>2027-03-09T08:00:00</Start>
        <Finish>2027-03-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>156000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>12</UID>
        <Start>2027-03-10T08:00:00</Start>
        <Finish>2027-03-10T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>156000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>13</UID>
      <ID>13</ID>
      <Name>Strip-out and making good</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.1.1</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-12T08:00:00</Start>
      <Finish>2027-02-18T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT80H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>520000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT80H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>10</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <ExtendedAttribute>
        <FieldID>188743783</FieldID>
        <Value>PT32H0M0S</Value>
      </ExtendedAttribute>
      <ExtendedAttribute>
        <FieldID>188743785</FieldID>
        <Value>PT60H0M0S</Value>
      </ExtendedAttribute>
      <Baseline>
        <Number>0</Number>
        <Start>2027-02-12T08:00:00</Start>
        <Finish>2027-02-18T17:00:00</Finish>
        <Duration>PT40H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT80H0M0S</Work>
        <Cost>520000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>13</UID>
        <Start>2027-02-12T08:00:00</Start>
        <Finish>2027-02-18T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT80H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>13</UID>
        <Start>2027-02-12T08:00:00</Start>
        <Finish>2027-02-18T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>520000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>14</UID>
      <ID>14</ID>
      <Name>Partitions and meeting rooms</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.1.2</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-19T08:00:00</Start>
      <Finish>2027-03-02T17:00:00</Finish>
      <Duration>PT64H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT192H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>1248000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT192H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>13</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <ExtendedAttribute>
        <FieldID>188743783</FieldID>
        <Value>PT52H0M0S</Value>
      </ExtendedAttribute>
      <ExtendedAttribute>
        <FieldID>188743785</FieldID>
        <Value>PT96H0M0S</Value>
      </ExtendedAttribute>
      <Baseline>
        <Number>0</Number>
        <Start>2027-02-19T08:00:00</Start>
        <Finish>2027-03-02T17:00:00</Finish>
        <Duration>PT64H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT192H0M0S</Work>
        <Cost>1248000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>14</UID>
        <Start>2027-02-19T08:00:00</Start>
        <Finish>2027-03-02T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT192H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>14</UID>
        <Start>2027-02-19T08:00:00</Start>
        <Finish>2027-03-02T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>1248000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>15</UID>
      <ID>15</ID>
      <Name>Small power and lighting</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.1.3</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-19T08:00:00</Start>
      <Finish>2027-02-26T17:00:00</Finish>
      <Duration>PT48H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT48H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>9600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>312000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT48H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>13</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-02-19T08:00:00</Start>
        <Finish>2027-02-26T17:00:00</Finish>
        <Duration>PT48H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT48H0M0S</Work>
        <Cost>312000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>15</UID>
        <Start>2027-02-19T08:00:00</Start>
        <Finish>2027-02-26T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT48H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>15</UID>
        <Start>2027-02-19T08:00:00</Start>
        <Finish>2027-02-26T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>312000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>16</UID>
      <ID>16</ID>
      <Name>Structured cabling</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.1.4</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-24T08:00:00</Start>
      <Finish>2027-03-02T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT80H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>14400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>400000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT80H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>14</PredecessorUID>
        <Type>3</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>14400</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-02-24T08:00:00</Start>
        <Finish>2027-03-02T17:00:00</Finish>
        <Duration>PT40H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT80H0M0S</Work>
        <Cost>400000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>16</UID>
        <Start>2027-02-24T08:00:00</Start>
        <Finish>2027-03-02T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT80H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>16</UID>
        <Start>2027-02-24T08:00:00</Start>
        <Finish>2027-03-02T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>400000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>17</UID>
      <ID>17</ID>
      <Name>Decoration and flooring</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.1.5</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-03T08:00:00</Start>
      <Finish>2027-03-10T17:00:00</Finish>
      <Duration>PT48H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT144H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>936000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT144H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>14</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>15</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <ExtendedAttribute>
        <FieldID>188743783</FieldID>
        <Value>PT40H0M0S</Value>
      </ExtendedAttribute>
      <ExtendedAttribute>
        <FieldID>188743785</FieldID>
        <Value>PT72H0M0S</Value>
      </ExtendedAttribute>
      <Baseline>
        <Number>0</Number>
        <Start>2027-03-03T08:00:00</Start>
        <Finish>2027-03-10T17:00:00</Finish>
        <Duration>PT48H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT144H0M0S</Work>
        <Cost>936000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>17</UID>
        <Start>2027-03-03T08:00:00</Start>
        <Finish>2027-03-10T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT144H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>17</UID>
        <Start>2027-03-03T08:00:00</Start>
        <Finish>2027-03-10T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>936000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>18</UID>
      <ID>18</ID>
      <Name>Furniture</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-15T08:00:00</Start>
      <Finish>2027-03-16T17:00:00</Finish>
      <Duration>PT344H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>60</PercentComplete>
      <Cost>683000</Cost>
      <ActualCost>333425</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-15T08:00:00</Start>
        <Finish>2027-03-16T17:00:00</Finish>
        <Duration>PT344H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT126H0M0S</Work>
        <Cost>647000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-01-15T08:00:00</Start>
        <Finish>2027-01-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-01-18T08:00:00</Start>
        <Finish>2027-01-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-01-19T08:00:00</Start>
        <Finish>2027-01-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-01-20T08:00:00</Start>
        <Finish>2027-01-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-01-21T08:00:00</Start>
        <Finish>2027-01-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-01-22T08:00:00</Start>
        <Finish>2027-01-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-01-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-01-26T08:00:00</Start>
        <Finish>2027-01-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-01-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-01-28T08:00:00</Start>
        <Finish>2027-01-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-01-29T08:00:00</Start>
        <Finish>2027-01-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-02-01T08:00:00</Start>
        <Finish>2027-02-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-02-02T08:00:00</Start>
        <Finish>2027-02-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-02-03T08:00:00</Start>
        <Finish>2027-02-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-02-04T08:00:00</Start>
        <Finish>2027-02-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-02-05T08:00:00</Start>
        <Finish>2027-02-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-02-08T08:00:00</Start>
        <Finish>2027-02-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-02-09T08:00:00</Start>
        <Finish>2027-02-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-02-10T08:00:00</Start>
        <Finish>2027-02-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-03-11T08:00:00</Start>
        <Finish>2027-03-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-03-12T08:00:00</Start>
        <Finish>2027-03-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-03-15T08:00:00</Start>
        <Finish>2027-03-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-03-16T08:00:00</Start>
        <Finish>2027-03-16T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-01-15T08:00:00</Start>
        <Finish>2027-01-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-01-18T08:00:00</Start>
        <Finish>2027-01-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-01-19T08:00:00</Start>
        <Finish>2027-01-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-01-20T08:00:00</Start>
        <Finish>2027-01-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-01-21T08:00:00</Start>
        <Finish>2027-01-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-01-22T08:00:00</Start>
        <Finish>2027-01-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-01-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-01-26T08:00:00</Start>
        <Finish>2027-01-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-01-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-01-28T08:00:00</Start>
        <Finish>2027-01-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-01-29T08:00:00</Start>
        <Finish>2027-01-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-02-01T08:00:00</Start>
        <Finish>2027-02-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-02-02T08:00:00</Start>
        <Finish>2027-02-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-02-03T08:00:00</Start>
        <Finish>2027-02-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-02-04T08:00:00</Start>
        <Finish>2027-02-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-02-05T08:00:00</Start>
        <Finish>2027-02-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-02-08T08:00:00</Start>
        <Finish>2027-02-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-02-09T08:00:00</Start>
        <Finish>2027-02-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-02-10T08:00:00</Start>
        <Finish>2027-02-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-03-11T08:00:00</Start>
        <Finish>2027-03-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>72000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-03-12T08:00:00</Start>
        <Finish>2027-03-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>72000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-03-15T08:00:00</Start>
        <Finish>2027-03-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>72000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-03-16T08:00:00</Start>
        <Finish>2027-03-16T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>72000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>19</UID>
      <ID>19</ID>
      <Name>Select furniture</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.2.1</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-15T08:00:00</Start>
      <Finish>2027-01-20T17:00:00</Finish>
      <Duration>PT32H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT32H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>76800</TotalSlack>
      <PercentComplete>100</PercentComplete>
      <PercentWorkComplete>100</PercentWorkComplete>
      <Cost>224000</Cost>
      <ActualStart>2027-01-15T08:00:00</ActualStart>
      <ActualFinish>2027-01-20T17:00:00</ActualFinish>
      <ActualCost>224000</ActualCost>
      <ActualWork>PT32H0M0S</ActualWork>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>5</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-15T08:00:00</Start>
        <Finish>2027-01-20T17:00:00</Finish>
        <Duration>PT32H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT32H0M0S</Work>
        <Cost>224000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>19</UID>
        <Start>2027-01-15T08:00:00</Start>
        <Finish>2027-01-20T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>19</UID>
        <Start>2027-01-15T08:00:00</Start>
        <Finish>2027-01-20T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>224000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>20</UID>
      <ID>20</ID>
      <Name>Furniture made and delivered</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.2.2</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-21T08:00:00</Start>
      <Finish>2027-02-16T17:00:00</Finish>
      <Duration>PT152H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT38H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>76800</TotalSlack>
      <PercentComplete>64</PercentComplete>
      <PercentWorkComplete>64</PercentWorkComplete>
      <Cost>171000</Cost>
      <ActualStart>2027-01-21T08:00:00</ActualStart>
      <ActualCost>109425</ActualCost>
      <ActualWork>PT24H19M0S</ActualWork>
      <RemainingWork>PT13H41M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>19</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>6</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-21T08:00:00</Start>
        <Finish>2027-02-10T17:00:00</Finish>
        <Duration>PT120H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT30H0M0S</Work>
        <Cost>135000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>20</UID>
        <Start>2027-01-21T08:00:00</Start>
        <Finish>2027-02-10T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT30H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>20</UID>
        <Start>2027-01-21T08:00:00</Start>
        <Finish>2027-02-10T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>135000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>21</UID>
      <ID>21</ID>
      <Name>Install furniture</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.2.3</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-11T08:00:00</Start>
      <Finish>2027-03-16T17:00:00</Finish>
      <Duration>PT32H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT64H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>288000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT64H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>17</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>20</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <ExtendedAttribute>
        <FieldID>188743783</FieldID>
        <Value>PT24H0M0S</Value>
      </ExtendedAttribute>
      <ExtendedAttribute>
        <FieldID>188743785</FieldID>
        <Value>PT48H0M0S</Value>
      </ExtendedAttribute>
      <Baseline>
        <Number>0</Number>
        <Start>2027-03-11T08:00:00</Start>
        <Finish>2027-03-16T17:00:00</Finish>
        <Duration>PT32H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT64H0M0S</Work>
        <Cost>288000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>21</UID>
        <Start>2027-03-11T08:00:00</Start>
        <Finish>2027-03-16T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT64H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>21</UID>
        <Start>2027-03-11T08:00:00</Start>
        <Finish>2027-03-16T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>288000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>22</UID>
      <ID>22</ID>
      <Name>Fit-out complete</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-16T17:00:00</Start>
      <Finish>2027-03-16T17:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>21</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>16</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-03-16T17:00:00</Start>
        <Finish>2027-03-16T17:00:00</Finish>
        <Duration>PT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
      </Baseline>
    </Task>
    <Task>
      <UID>23</UID>
      <ID>23</ID>
      <Name>Technology</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-27T08:00:00</Start>
      <Finish>2027-03-12T17:00:00</Finish>
      <Duration>PT264H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>14400</TotalSlack>
      <PercentComplete>34</PercentComplete>
      <Cost>1288000</Cost>
      <ActualCost>384000</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-03-12T17:00:00</Finish>
        <Duration>PT264H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT200H0M0S</Work>
        <Cost>1288000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>23</UID>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-01-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT10H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>23</UID>
        <Start>2027-01-28T08:00:00</Start>
        <Finish>2027-01-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT10H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>23</UID>
        <Start>2027-01-29T08:00:00</Start>
        <Finish>2027-01-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT10H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>23</UID>
        <Start>2027-02-01T08:00:00</Start>
        <Finish>2027-02-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT10H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>23</UID>
        <Start>2027-02-02T08:00:00</Start>
        <Finish>2027-02-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>23</UID>
        <Start>2027-02-03T08:00:00</Start>
        <Finish>2027-02-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>23</UID>
        <Start>2027-02-04T08:00:00</Start>
        <Finish>2027-02-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>23</UID>
        <Start>2027-02-05T08:00:00</Start>
        <Finish>2027-02-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>23</UID>
        <Start>2027-02-08T08:00:00</Start>
        <Finish>2027-02-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>23</UID>
        <Start>2027-02-09T08:00:00</Start>
        <Finish>2027-02-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>23</UID>
        <Start>2027-02-10T08:00:00</Start>
        <Finish>2027-02-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>23</UID>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>23</UID>
        <Start>2027-02-12T08:00:00</Start>
        <Finish>2027-02-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>23</UID>
        <Start>2027-02-15T08:00:00</Start>
        <Finish>2027-02-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>23</UID>
        <Start>2027-02-16T08:00:00</Start>
        <Finish>2027-02-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>23</UID>
        <Start>2027-02-17T08:00:00</Start>
        <Finish>2027-02-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>23</UID>
        <Start>2027-02-18T08:00:00</Start>
        <Finish>2027-02-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>23</UID>
        <Start>2027-02-19T08:00:00</Start>
        <Finish>2027-02-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>23</UID>
        <Start>2027-02-22T08:00:00</Start>
        <Finish>2027-02-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>23</UID>
        <Start>2027-02-23T08:00:00</Start>
        <Finish>2027-02-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>23</UID>
        <Start>2027-03-03T08:00:00</Start>
        <Finish>2027-03-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>23</UID>
        <Start>2027-03-04T08:00:00</Start>
        <Finish>2027-03-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>23</UID>
        <Start>2027-03-05T08:00:00</Start>
        <Finish>2027-03-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>23</UID>
        <Start>2027-03-08T08:00:00</Start>
        <Finish>2027-03-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>23</UID>
        <Start>2027-03-09T08:00:00</Start>
        <Finish>2027-03-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>23</UID>
        <Start>2027-03-10T08:00:00</Start>
        <Finish>2027-03-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>23</UID>
        <Start>2027-03-11T08:00:00</Start>
        <Finish>2027-03-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>23</UID>
        <Start>2027-03-12T08:00:00</Start>
        <Finish>2027-03-12T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>23</UID>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-01-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>80000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>23</UID>
        <Start>2027-01-28T08:00:00</Start>
        <Finish>2027-01-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>80000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>23</UID>
        <Start>2027-01-29T08:00:00</Start>
        <Finish>2027-01-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>80000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>23</UID>
        <Start>2027-02-01T08:00:00</Start>
        <Finish>2027-02-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>80000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>23</UID>
        <Start>2027-02-02T08:00:00</Start>
        <Finish>2027-02-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>16000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>23</UID>
        <Start>2027-02-03T08:00:00</Start>
        <Finish>2027-02-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>16000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>23</UID>
        <Start>2027-02-04T08:00:00</Start>
        <Finish>2027-02-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>16000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>23</UID>
        <Start>2027-02-05T08:00:00</Start>
        <Finish>2027-02-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>16000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>23</UID>
        <Start>2027-02-08T08:00:00</Start>
        <Finish>2027-02-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>16000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>23</UID>
        <Start>2027-02-09T08:00:00</Start>
        <Finish>2027-02-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>16000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>23</UID>
        <Start>2027-02-10T08:00:00</Start>
        <Finish>2027-02-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>16000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>23</UID>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>16000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>23</UID>
        <Start>2027-02-12T08:00:00</Start>
        <Finish>2027-02-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>16000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>23</UID>
        <Start>2027-02-15T08:00:00</Start>
        <Finish>2027-02-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>16000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>23</UID>
        <Start>2027-02-16T08:00:00</Start>
        <Finish>2027-02-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>16000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>23</UID>
        <Start>2027-02-17T08:00:00</Start>
        <Finish>2027-02-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>16000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>23</UID>
        <Start>2027-02-18T08:00:00</Start>
        <Finish>2027-02-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>16000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>23</UID>
        <Start>2027-02-19T08:00:00</Start>
        <Finish>2027-02-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>16000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>23</UID>
        <Start>2027-02-22T08:00:00</Start>
        <Finish>2027-02-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>16000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>23</UID>
        <Start>2027-02-23T08:00:00</Start>
        <Finish>2027-02-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>16000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>23</UID>
        <Start>2027-03-03T08:00:00</Start>
        <Finish>2027-03-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>80000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>23</UID>
        <Start>2027-03-04T08:00:00</Start>
        <Finish>2027-03-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>80000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>23</UID>
        <Start>2027-03-05T08:00:00</Start>
        <Finish>2027-03-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>80000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>23</UID>
        <Start>2027-03-08T08:00:00</Start>
        <Finish>2027-03-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>144000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>23</UID>
        <Start>2027-03-09T08:00:00</Start>
        <Finish>2027-03-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>80000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>23</UID>
        <Start>2027-03-10T08:00:00</Start>
        <Finish>2027-03-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>40000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>23</UID>
        <Start>2027-03-11T08:00:00</Start>
        <Finish>2027-03-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>104000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>23</UID>
        <Start>2027-03-12T08:00:00</Start>
        <Finish>2027-03-12T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>104000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>24</UID>
      <ID>24</ID>
      <Name>Network</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-27T08:00:00</Start>
      <Finish>2027-03-08T17:00:00</Finish>
      <Duration>PT232H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>14400</TotalSlack>
      <PercentComplete>43</PercentComplete>
      <Cost>880000</Cost>
      <ActualCost>384000</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-03-08T17:00:00</Finish>
        <Duration>PT232H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT128H0M0S</Work>
        <Cost>880000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>24</UID>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-01-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT10H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>24</UID>
        <Start>2027-01-28T08:00:00</Start>
        <Finish>2027-01-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT10H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>24</UID>
        <Start>2027-01-29T08:00:00</Start>
        <Finish>2027-01-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT10H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>24</UID>
        <Start>2027-02-01T08:00:00</Start>
        <Finish>2027-02-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT10H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>24</UID>
        <Start>2027-02-02T08:00:00</Start>
        <Finish>2027-02-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>24</UID>
        <Start>2027-02-03T08:00:00</Start>
        <Finish>2027-02-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>24</UID>
        <Start>2027-02-04T08:00:00</Start>
        <Finish>2027-02-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>24</UID>
        <Start>2027-02-05T08:00:00</Start>
        <Finish>2027-02-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>24</UID>
        <Start>2027-02-08T08:00:00</Start>
        <Finish>2027-02-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>24</UID>
        <Start>2027-02-09T08:00:00</Start>
        <Finish>2027-02-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>24</UID>
        <Start>2027-02-10T08:00:00</Start>
        <Finish>2027-02-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>24</UID>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>24</UID>
        <Start>2027-02-12T08:00:00</Start>
        <Finish>2027-02-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>24</UID>
        <Start>2027-02-15T08:00:00</Start>
        <Finish>2027-02-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>24</UID>
        <Start>2027-02-16T08:00:00</Start>
        <Finish>2027-02-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>24</UID>
        <Start>2027-02-17T08:00:00</Start>
        <Finish>2027-02-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>24</UID>
        <Start>2027-02-18T08:00:00</Start>
        <Finish>2027-02-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>24</UID>
        <Start>2027-02-19T08:00:00</Start>
        <Finish>2027-02-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>24</UID>
        <Start>2027-02-22T08:00:00</Start>
        <Finish>2027-02-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>24</UID>
        <Start>2027-02-23T08:00:00</Start>
        <Finish>2027-02-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT2H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>24</UID>
        <Start>2027-03-03T08:00:00</Start>
        <Finish>2027-03-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>24</UID>
        <Start>2027-03-04T08:00:00</Start>
        <Finish>2027-03-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>24</UID>
        <Start>2027-03-05T08:00:00</Start>
        <Finish>2027-03-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>24</UID>
        <Start>2027-03-08T08:00:00</Start>
        <Finish>2027-03-08T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>24</UID>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-01-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>80000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>24</UID>
        <Start>2027-01-28T08:00:00</Start>
        <Finish>2027-01-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>80000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>24</UID>
        <Start>2027-01-29T08:00:00</Start>
        <Finish>2027-01-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>80000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>24</UID>
        <Start>2027-02-01T08:00:00</Start>
        <Finish>2027-02-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>80000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>24</UID>
        <Start>2027-02-02T08:00:00</Start>
        <Finish>2027-02-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>16000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>24</UID>
        <Start>2027-02-03T08:00:00</Start>
        <Finish>2027-02-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>16000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>24</UID>
        <Start>2027-02-04T08:00:00</Start>
        <Finish>2027-02-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>16000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>24</UID>
        <Start>2027-02-05T08:00:00</Start>
        <Finish>2027-02-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>16000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>24</UID>
        <Start>2027-02-08T08:00:00</Start>
        <Finish>2027-02-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>16000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>24</UID>
        <Start>2027-02-09T08:00:00</Start>
        <Finish>2027-02-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>16000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>24</UID>
        <Start>2027-02-10T08:00:00</Start>
        <Finish>2027-02-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>16000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>24</UID>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>16000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>24</UID>
        <Start>2027-02-12T08:00:00</Start>
        <Finish>2027-02-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>16000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>24</UID>
        <Start>2027-02-15T08:00:00</Start>
        <Finish>2027-02-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>16000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>24</UID>
        <Start>2027-02-16T08:00:00</Start>
        <Finish>2027-02-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>16000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>24</UID>
        <Start>2027-02-17T08:00:00</Start>
        <Finish>2027-02-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>16000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>24</UID>
        <Start>2027-02-18T08:00:00</Start>
        <Finish>2027-02-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>16000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>24</UID>
        <Start>2027-02-19T08:00:00</Start>
        <Finish>2027-02-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>16000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>24</UID>
        <Start>2027-02-22T08:00:00</Start>
        <Finish>2027-02-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>16000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>24</UID>
        <Start>2027-02-23T08:00:00</Start>
        <Finish>2027-02-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>16000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>24</UID>
        <Start>2027-03-03T08:00:00</Start>
        <Finish>2027-03-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>80000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>24</UID>
        <Start>2027-03-04T08:00:00</Start>
        <Finish>2027-03-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>80000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>24</UID>
        <Start>2027-03-05T08:00:00</Start>
        <Finish>2027-03-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>80000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>24</UID>
        <Start>2027-03-08T08:00:00</Start>
        <Finish>2027-03-08T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>64000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>25</UID>
      <ID>25</ID>
      <Name>Order internet lines</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.1.1</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-27T08:00:00</Start>
      <Finish>2027-02-23T17:00:00</Finish>
      <Duration>PT160H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT40H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>52800</TotalSlack>
      <PercentComplete>40</PercentComplete>
      <PercentWorkComplete>40</PercentWorkComplete>
      <Cost>320000</Cost>
      <ActualStart>2027-01-27T08:00:00</ActualStart>
      <ActualCost>128000</ActualCost>
      <ActualWork>PT16H0M0S</ActualWork>
      <RemainingWork>PT24H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>8</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-02-23T17:00:00</Finish>
        <Duration>PT160H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT40H0M0S</Work>
        <Cost>320000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>25</UID>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-02-23T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT40H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>25</UID>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-02-23T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>320000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>26</UID>
      <ID>26</ID>
      <Name>Network and Wi-Fi design</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.1.2</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-27T08:00:00</Start>
      <Finish>2027-02-01T17:00:00</Finish>
      <Duration>PT32H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT32H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>115200</TotalSlack>
      <PercentComplete>100</PercentComplete>
      <PercentWorkComplete>100</PercentWorkComplete>
      <Cost>256000</Cost>
      <ActualStart>2027-01-27T08:00:00</ActualStart>
      <ActualFinish>2027-02-01T17:00:00</ActualFinish>
      <ActualCost>256000</ActualCost>
      <ActualWork>PT32H0M0S</ActualWork>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>8</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-02-01T17:00:00</Finish>
        <Duration>PT32H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT32H0M0S</Work>
        <Cost>256000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>26</UID>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-02-01T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>26</UID>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-02-01T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>256000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>27</UID>
      <ID>27</ID>
      <Name>Install switches and Wi-Fi</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.1.3</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-03T08:00:00</Start>
      <Finish>2027-03-05T17:00:00</Finish>
      <Duration>PT24H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT48H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>14400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>240000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT48H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>16</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>26</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-03-03T08:00:00</Start>
        <Finish>2027-03-05T17:00:00</Finish>
        <Duration>PT24H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT48H0M0S</Work>
        <Cost>240000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-03-03T08:00:00</Start>
        <Finish>2027-03-05T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT48H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-03-03T08:00:00</Start>
        <Finish>2027-03-05T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>240000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>28</UID>
      <ID>28</ID>
      <Name>Internet lines live</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.1.4</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-08T08:00:00</Start>
      <Finish>2027-03-08T17:00:00</Finish>
      <Duration>PT8H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT8H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>14400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>64000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT8H0M0S</RemainingWork>
      <ConstraintType>7</ConstraintType>
      <ConstraintDate>2027-03-11T17:00:00</ConstraintDate>
      <PredecessorLink>
        <PredecessorUID>25</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>27</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-03-08T08:00:00</Start>
        <Finish>2027-03-08T17:00:00</Finish>
        <Duration>PT8H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT8H0M0S</Work>
        <Cost>64000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>28</UID>
        <Start>2027-03-08T08:00:00</Start>
        <Finish>2027-03-08T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>28</UID>
        <Start>2027-03-08T08:00:00</Start>
        <Finish>2027-03-08T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>64000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>29</UID>
      <ID>29</ID>
      <Name>Devices</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-08T08:00:00</Start>
      <Finish>2027-03-12T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>24000</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <Cost>408000</Cost>
      <ActualCost>0</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-03-08T08:00:00</Start>
        <Finish>2027-03-12T17:00:00</Finish>
        <Duration>PT40H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT72H0M0S</Work>
        <Cost>408000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>29</UID>
        <Start>2027-03-08T08:00:00</Start>
        <Finish>2027-03-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>29</UID>
        <Start>2027-03-09T08:00:00</Start>
        <Finish>2027-03-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>29</UID>
        <Start>2027-03-10T08:00:00</Start>
        <Finish>2027-03-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>29</UID>
        <Start>2027-03-11T08:00:00</Start>
        <Finish>2027-03-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>29</UID>
        <Start>2027-03-12T08:00:00</Start>
        <Finish>2027-03-12T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>29</UID>
        <Start>2027-03-08T08:00:00</Start>
        <Finish>2027-03-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>80000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>29</UID>
        <Start>2027-03-09T08:00:00</Start>
        <Finish>2027-03-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>80000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>29</UID>
        <Start>2027-03-10T08:00:00</Start>
        <Finish>2027-03-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>40000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>29</UID>
        <Start>2027-03-11T08:00:00</Start>
        <Finish>2027-03-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>104000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>29</UID>
        <Start>2027-03-12T08:00:00</Start>
        <Finish>2027-03-12T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>104000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>30</UID>
      <ID>30</ID>
      <Name>Meeting room audio-visual</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.2.1</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-08T08:00:00</Start>
      <Finish>2027-03-10T17:00:00</Finish>
      <Duration>PT24H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT24H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>24000</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>120000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT24H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>27</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-03-08T08:00:00</Start>
        <Finish>2027-03-10T17:00:00</Finish>
        <Duration>PT24H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT24H0M0S</Work>
        <Cost>120000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>30</UID>
        <Start>2027-03-08T08:00:00</Start>
        <Finish>2027-03-10T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>30</UID>
        <Start>2027-03-08T08:00:00</Start>
        <Finish>2027-03-10T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>120000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>31</UID>
      <ID>31</ID>
      <Name>Printers and badge access</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.2.2</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-08T08:00:00</Start>
      <Finish>2027-03-09T17:00:00</Finish>
      <Duration>PT16H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT16H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>28800</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>80000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT16H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>27</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-03-08T08:00:00</Start>
        <Finish>2027-03-09T17:00:00</Finish>
        <Duration>PT16H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT16H0M0S</Work>
        <Cost>80000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>31</UID>
        <Start>2027-03-08T08:00:00</Start>
        <Finish>2027-03-09T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>31</UID>
        <Start>2027-03-08T08:00:00</Start>
        <Finish>2027-03-09T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>80000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>32</UID>
      <ID>32</ID>
      <Name>End-to-end IT testing</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.2.3</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-11T08:00:00</Start>
      <Finish>2027-03-12T17:00:00</Finish>
      <Duration>PT16H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT32H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>24000</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>208000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT32H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>28</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>30</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>31</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-03-11T08:00:00</Start>
        <Finish>2027-03-12T17:00:00</Finish>
        <Duration>PT16H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT32H0M0S</Work>
        <Cost>208000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>32</UID>
        <Start>2027-03-11T08:00:00</Start>
        <Finish>2027-03-12T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>32</UID>
        <Start>2027-03-11T08:00:00</Start>
        <Finish>2027-03-12T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>208000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>33</UID>
      <ID>33</ID>
      <Name>Move</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-08T08:00:00</Start>
      <Finish>2027-03-25T17:00:00</Finish>
      <Duration>PT440H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>38</PercentComplete>
      <Cost>1440000</Cost>
      <ActualCost>296000</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-08T08:00:00</Start>
        <Finish>2027-03-25T17:00:00</Finish>
        <Duration>PT440H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT300H0M0S</Work>
        <Cost>1440000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>33</UID>
        <Start>2027-01-08T08:00:00</Start>
        <Finish>2027-01-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>33</UID>
        <Start>2027-01-11T08:00:00</Start>
        <Finish>2027-01-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>33</UID>
        <Start>2027-01-12T08:00:00</Start>
        <Finish>2027-01-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>33</UID>
        <Start>2027-01-13T08:00:00</Start>
        <Finish>2027-01-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>33</UID>
        <Start>2027-01-14T08:00:00</Start>
        <Finish>2027-01-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>33</UID>
        <Start>2027-01-20T08:00:00</Start>
        <Finish>2027-01-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>33</UID>
        <Start>2027-01-21T08:00:00</Start>
        <Finish>2027-01-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>33</UID>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>33</UID>
        <Start>2027-02-12T08:00:00</Start>
        <Finish>2027-02-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>33</UID>
        <Start>2027-02-15T08:00:00</Start>
        <Finish>2027-02-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>33</UID>
        <Start>2027-02-16T08:00:00</Start>
        <Finish>2027-02-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>33</UID>
        <Start>2027-02-17T08:00:00</Start>
        <Finish>2027-02-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>33</UID>
        <Start>2027-03-17T08:00:00</Start>
        <Finish>2027-03-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>33</UID>
        <Start>2027-03-18T08:00:00</Start>
        <Finish>2027-03-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>33</UID>
        <Start>2027-03-19T08:00:00</Start>
        <Finish>2027-03-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>33</UID>
        <Start>2027-03-22T08:00:00</Start>
        <Finish>2027-03-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT72H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>33</UID>
        <Start>2027-03-23T08:00:00</Start>
        <Finish>2027-03-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT72H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>33</UID>
        <Start>2027-03-24T08:00:00</Start>
        <Finish>2027-03-25T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>33</UID>
        <Start>2027-03-25T08:00:00</Start>
        <Finish>2027-03-25T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>33</UID>
        <Start>2027-01-08T08:00:00</Start>
        <Finish>2027-01-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>33</UID>
        <Start>2027-01-11T08:00:00</Start>
        <Finish>2027-01-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>33</UID>
        <Start>2027-01-12T08:00:00</Start>
        <Finish>2027-01-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>33</UID>
        <Start>2027-01-13T08:00:00</Start>
        <Finish>2027-01-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>33</UID>
        <Start>2027-01-14T08:00:00</Start>
        <Finish>2027-01-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>33</UID>
        <Start>2027-01-20T08:00:00</Start>
        <Finish>2027-01-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>33</UID>
        <Start>2027-01-21T08:00:00</Start>
        <Finish>2027-01-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>33</UID>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>44000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>33</UID>
        <Start>2027-02-12T08:00:00</Start>
        <Finish>2027-02-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>44000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>33</UID>
        <Start>2027-02-15T08:00:00</Start>
        <Finish>2027-02-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>44000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>33</UID>
        <Start>2027-02-16T08:00:00</Start>
        <Finish>2027-02-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>44000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>33</UID>
        <Start>2027-02-17T08:00:00</Start>
        <Finish>2027-02-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>44000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>33</UID>
        <Start>2027-03-17T08:00:00</Start>
        <Finish>2027-03-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>64000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>33</UID>
        <Start>2027-03-18T08:00:00</Start>
        <Finish>2027-03-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>64000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>33</UID>
        <Start>2027-03-19T08:00:00</Start>
        <Finish>2027-03-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>64000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>33</UID>
        <Start>2027-03-22T08:00:00</Start>
        <Finish>2027-03-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>312000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>33</UID>
        <Start>2027-03-23T08:00:00</Start>
        <Finish>2027-03-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>312000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>33</UID>
        <Start>2027-03-24T08:00:00</Start>
        <Finish>2027-03-25T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>76000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>33</UID>
        <Start>2027-03-25T08:00:00</Start>
        <Finish>2027-03-25T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>76000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>34</UID>
      <ID>34</ID>
      <Name>Preparation</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-08T08:00:00</Start>
      <Finish>2027-03-19T17:00:00</Finish>
      <Duration>PT408H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>53</PercentComplete>
      <Cost>664000</Cost>
      <ActualCost>296000</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-08T08:00:00</Start>
        <Finish>2027-03-19T17:00:00</Finish>
        <Duration>PT408H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT124H0M0S</Work>
        <Cost>664000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>34</UID>
        <Start>2027-01-08T08:00:00</Start>
        <Finish>2027-01-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>34</UID>
        <Start>2027-01-11T08:00:00</Start>
        <Finish>2027-01-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>34</UID>
        <Start>2027-01-12T08:00:00</Start>
        <Finish>2027-01-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>34</UID>
        <Start>2027-01-13T08:00:00</Start>
        <Finish>2027-01-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>34</UID>
        <Start>2027-01-14T08:00:00</Start>
        <Finish>2027-01-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>34</UID>
        <Start>2027-01-20T08:00:00</Start>
        <Finish>2027-01-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>34</UID>
        <Start>2027-01-21T08:00:00</Start>
        <Finish>2027-01-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>34</UID>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>34</UID>
        <Start>2027-02-12T08:00:00</Start>
        <Finish>2027-02-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>34</UID>
        <Start>2027-02-15T08:00:00</Start>
        <Finish>2027-02-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>34</UID>
        <Start>2027-02-16T08:00:00</Start>
        <Finish>2027-02-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>34</UID>
        <Start>2027-02-17T08:00:00</Start>
        <Finish>2027-02-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>34</UID>
        <Start>2027-03-17T08:00:00</Start>
        <Finish>2027-03-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>34</UID>
        <Start>2027-03-18T08:00:00</Start>
        <Finish>2027-03-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>34</UID>
        <Start>2027-03-19T08:00:00</Start>
        <Finish>2027-03-19T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>34</UID>
        <Start>2027-01-08T08:00:00</Start>
        <Finish>2027-01-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>34</UID>
        <Start>2027-01-11T08:00:00</Start>
        <Finish>2027-01-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>34</UID>
        <Start>2027-01-12T08:00:00</Start>
        <Finish>2027-01-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>34</UID>
        <Start>2027-01-13T08:00:00</Start>
        <Finish>2027-01-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>34</UID>
        <Start>2027-01-14T08:00:00</Start>
        <Finish>2027-01-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>34</UID>
        <Start>2027-01-20T08:00:00</Start>
        <Finish>2027-01-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>34</UID>
        <Start>2027-01-21T08:00:00</Start>
        <Finish>2027-01-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>34</UID>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>44000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>34</UID>
        <Start>2027-02-12T08:00:00</Start>
        <Finish>2027-02-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>44000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>34</UID>
        <Start>2027-02-15T08:00:00</Start>
        <Finish>2027-02-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>44000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>34</UID>
        <Start>2027-02-16T08:00:00</Start>
        <Finish>2027-02-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>44000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>34</UID>
        <Start>2027-02-17T08:00:00</Start>
        <Finish>2027-02-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>44000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>34</UID>
        <Start>2027-03-17T08:00:00</Start>
        <Finish>2027-03-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>64000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>34</UID>
        <Start>2027-03-18T08:00:00</Start>
        <Finish>2027-03-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>64000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>34</UID>
        <Start>2027-03-19T08:00:00</Start>
        <Finish>2027-03-19T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>64000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>35</UID>
      <ID>35</ID>
      <Name>Book the removal company</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.1.1</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-20T08:00:00</Start>
      <Finish>2027-01-21T17:00:00</Finish>
      <Duration>PT16H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT16H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>182400</TotalSlack>
      <PercentComplete>100</PercentComplete>
      <PercentWorkComplete>100</PercentWorkComplete>
      <Cost>112000</Cost>
      <ActualStart>2027-01-20T08:00:00</ActualStart>
      <ActualFinish>2027-01-21T17:00:00</ActualFinish>
      <ActualCost>112000</ActualCost>
      <ActualWork>PT16H0M0S</ActualWork>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>6</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-20T08:00:00</Start>
        <Finish>2027-01-21T17:00:00</Finish>
        <Duration>PT16H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT16H0M0S</Work>
        <Cost>112000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>35</UID>
        <Start>2027-01-20T08:00:00</Start>
        <Finish>2027-01-21T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>35</UID>
        <Start>2027-01-20T08:00:00</Start>
        <Finish>2027-01-21T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>112000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>36</UID>
      <ID>36</ID>
      <Name>Archive and dispose of old records</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.1.2</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-08T08:00:00</Start>
      <Finish>2027-01-14T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT20H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>206400</TotalSlack>
      <PercentComplete>100</PercentComplete>
      <PercentWorkComplete>100</PercentWorkComplete>
      <Cost>140000</Cost>
      <ActualStart>2027-01-08T08:00:00</ActualStart>
      <ActualFinish>2027-01-14T17:00:00</ActualFinish>
      <ActualCost>140000</ActualCost>
      <ActualWork>PT20H0M0S</ActualWork>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>4</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-08T08:00:00</Start>
        <Finish>2027-01-14T17:00:00</Finish>
        <Duration>PT40H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT20H0M0S</Work>
        <Cost>140000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>36</UID>
        <Start>2027-01-08T08:00:00</Start>
        <Finish>2027-01-14T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT20H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>36</UID>
        <Start>2027-01-08T08:00:00</Start>
        <Finish>2027-01-14T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>140000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>37</UID>
      <ID>37</ID>
      <Name>Staff communications and move packs</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.1.3</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-11T08:00:00</Start>
      <Finish>2027-02-17T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT40H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>91200</TotalSlack>
      <PercentComplete>20</PercentComplete>
      <PercentWorkComplete>20</PercentWorkComplete>
      <Cost>220000</Cost>
      <ActualStart>2027-02-11T08:00:00</ActualStart>
      <ActualCost>44000</ActualCost>
      <ActualWork>PT8H0M0S</ActualWork>
      <RemainingWork>PT32H0M0S</RemainingWork>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-02-11T08:00:00</ConstraintDate>
      <PredecessorLink>
        <PredecessorUID>5</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-17T17:00:00</Finish>
        <Duration>PT40H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT40H0M0S</Work>
        <Cost>220000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>37</UID>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-17T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT40H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>37</UID>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-17T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>220000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>38</UID>
      <ID>38</ID>
      <Name>Packing and labelling</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.1.4</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-17T08:00:00</Start>
      <Finish>2027-03-19T17:00:00</Finish>
      <Duration>PT24H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT48H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>192000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT48H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>37</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>36</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>35</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>22</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <ExtendedAttribute>
        <FieldID>188743783</FieldID>
        <Value>PT20H0M0S</Value>
      </ExtendedAttribute>
      <ExtendedAttribute>
        <FieldID>188743785</FieldID>
        <Value>PT36H0M0S</Value>
      </ExtendedAttribute>
      <Baseline>
        <Number>0</Number>
        <Start>2027-03-17T08:00:00</Start>
        <Finish>2027-03-19T17:00:00</Finish>
        <Duration>PT24H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT48H0M0S</Work>
        <Cost>192000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>38</UID>
        <Start>2027-03-17T08:00:00</Start>
        <Finish>2027-03-19T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT48H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>38</UID>
        <Start>2027-03-17T08:00:00</Start>
        <Finish>2027-03-19T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>192000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>39</UID>
      <ID>39</ID>
      <Name>Move weekend</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-22T08:00:00</Start>
      <Finish>2027-03-25T17:00:00</Finish>
      <Duration>PT32H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <Cost>776000</Cost>
      <ActualCost>0</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-03-22T08:00:00</Start>
        <Finish>2027-03-25T17:00:00</Finish>
        <Duration>PT32H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT176H0M0S</Work>
        <Cost>776000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>39</UID>
        <Start>2027-03-22T08:00:00</Start>
        <Finish>2027-03-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT72H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>39</UID>
        <Start>2027-03-23T08:00:00</Start>
        <Finish>2027-03-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT72H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>39</UID>
        <Start>2027-03-24T08:00:00</Start>
        <Finish>2027-03-25T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>39</UID>
        <Start>2027-03-25T08:00:00</Start>
        <Finish>2027-03-25T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>39</UID>
        <Start>2027-03-22T08:00:00</Start>
        <Finish>2027-03-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>312000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>39</UID>
        <Start>2027-03-23T08:00:00</Start>
        <Finish>2027-03-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>312000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>39</UID>
        <Start>2027-03-24T08:00:00</Start>
        <Finish>2027-03-25T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>76000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>39</UID>
        <Start>2027-03-25T08:00:00</Start>
        <Finish>2027-03-25T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>76000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>40</UID>
      <ID>40</ID>
      <Name>Move furniture and crates</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.2.1</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-22T08:00:00</Start>
      <Finish>2027-03-23T17:00:00</Finish>
      <Duration>PT16H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT96H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>384000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT96H0M0S</RemainingWork>
      <ConstraintType>5</ConstraintType>
      <ConstraintDate>2027-03-24T08:00:00</ConstraintDate>
      <PredecessorLink>
        <PredecessorUID>38</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>32</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <ExtendedAttribute>
        <FieldID>188743783</FieldID>
        <Value>PT12H0M0S</Value>
      </ExtendedAttribute>
      <ExtendedAttribute>
        <FieldID>188743785</FieldID>
        <Value>PT24H0M0S</Value>
      </ExtendedAttribute>
      <Baseline>
        <Number>0</Number>
        <Start>2027-03-22T08:00:00</Start>
        <Finish>2027-03-23T17:00:00</Finish>
        <Duration>PT16H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT96H0M0S</Work>
        <Cost>384000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>40</UID>
        <Start>2027-03-22T08:00:00</Start>
        <Finish>2027-03-23T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT96H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>40</UID>
        <Start>2027-03-22T08:00:00</Start>
        <Finish>2027-03-23T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>384000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>41</UID>
      <ID>41</ID>
      <Name>Move and reconnect desktops</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.2.2</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-22T08:00:00</Start>
      <Finish>2027-03-23T17:00:00</Finish>
      <Duration>PT16H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT48H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>14400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>240000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT48H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>40</PredecessorUID>
        <Type>3</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-03-22T08:00:00</Start>
        <Finish>2027-03-23T17:00:00</Finish>
        <Duration>PT16H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT48H0M0S</Work>
        <Cost>240000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>41</UID>
        <Start>2027-03-22T08:00:00</Start>
        <Finish>2027-03-23T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT48H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>41</UID>
        <Start>2027-03-22T08:00:00</Start>
        <Finish>2027-03-23T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>240000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>42</UID>
      <ID>42</ID>
      <Name>Unpack and settle in</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.2.3</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-24T08:00:00</Start>
      <Finish>2027-03-25T17:00:00</Finish>
      <Duration>PT16H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT32H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>14400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>152000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT32H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>41</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-03-24T08:00:00</Start>
        <Finish>2027-03-25T17:00:00</Finish>
        <Duration>PT16H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT32H0M0S</Work>
        <Cost>152000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-03-24T08:00:00</Start>
        <Finish>2027-03-25T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-03-24T08:00:00</Start>
        <Finish>2027-03-25T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>152000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>43</UID>
      <ID>43</ID>
      <Name>Staff working in the new office</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-25T17:00:00</Start>
      <Finish>2027-03-25T17:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>14400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
      <Deadline>2027-03-30T17:00:00</Deadline>
      <PredecessorLink>
        <PredecessorUID>42</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-03-25T17:00:00</Start>
        <Finish>2027-03-25T17:00:00</Finish>
        <Duration>PT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
      </Baseline>
    </Task>
    <Task>
      <UID>44</UID>
      <ID>44</ID>
      <Name>Exit the old office</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-24T08:00:00</Start>
      <Finish>2027-04-05T17:00:00</Finish>
      <Duration>PT72H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <Cost>576000</Cost>
      <ActualCost>0</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-03-24T08:00:00</Start>
        <Finish>2027-04-05T17:00:00</Finish>
        <Duration>PT72H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT152H0M0S</Work>
        <Cost>576000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>44</UID>
        <Start>2027-03-24T08:00:00</Start>
        <Finish>2027-03-25T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>44</UID>
        <Start>2027-03-25T08:00:00</Start>
        <Finish>2027-03-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>44</UID>
        <Start>2027-03-26T08:00:00</Start>
        <Finish>2027-03-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>44</UID>
        <Start>2027-03-29T08:00:00</Start>
        <Finish>2027-03-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>44</UID>
        <Start>2027-03-30T08:00:00</Start>
        <Finish>2027-03-31T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>44</UID>
        <Start>2027-03-31T08:00:00</Start>
        <Finish>2027-04-01T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>44</UID>
        <Start>2027-04-01T08:00:00</Start>
        <Finish>2027-04-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>44</UID>
        <Start>2027-04-02T08:00:00</Start>
        <Finish>2027-04-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>44</UID>
        <Start>2027-04-05T08:00:00</Start>
        <Finish>2027-04-05T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>44</UID>
        <Start>2027-03-24T08:00:00</Start>
        <Finish>2027-03-25T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>72000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>44</UID>
        <Start>2027-03-25T08:00:00</Start>
        <Finish>2027-03-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>72000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>44</UID>
        <Start>2027-03-26T08:00:00</Start>
        <Finish>2027-03-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>72000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>44</UID>
        <Start>2027-03-29T08:00:00</Start>
        <Finish>2027-03-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>72000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>44</UID>
        <Start>2027-03-30T08:00:00</Start>
        <Finish>2027-03-31T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>72000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>44</UID>
        <Start>2027-03-31T08:00:00</Start>
        <Finish>2027-04-01T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>44</UID>
        <Start>2027-04-01T08:00:00</Start>
        <Finish>2027-04-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>48000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>44</UID>
        <Start>2027-04-02T08:00:00</Start>
        <Finish>2027-04-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>44</UID>
        <Start>2027-04-05T08:00:00</Start>
        <Finish>2027-04-05T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>45</UID>
      <ID>45</ID>
      <Name>Clean and reinstate the old office</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-24T08:00:00</Start>
      <Finish>2027-03-30T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT120H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>360000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT120H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>40</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <ExtendedAttribute>
        <FieldID>188743783</FieldID>
        <Value>PT32H0M0S</Value>
      </ExtendedAttribute>
      <ExtendedAttribute>
        <FieldID>188743785</FieldID>
        <Value>PT60H0M0S</Value>
      </ExtendedAttribute>
      <Baseline>
        <Number>0</Number>
        <Start>2027-03-24T08:00:00</Start>
        <Finish>2027-03-30T17:00:00</Finish>
        <Duration>PT40H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT120H0M0S</Work>
        <Cost>360000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>45</UID>
        <Start>2027-03-24T08:00:00</Start>
        <Finish>2027-03-30T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT120H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>45</UID>
        <Start>2027-03-24T08:00:00</Start>
        <Finish>2027-03-30T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>360000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>46</UID>
      <ID>46</ID>
      <Name>Hand back the old office keys</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-31T08:00:00</Start>
      <Finish>2027-03-31T17:00:00</Finish>
      <Duration>PT8H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT8H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>56000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT8H0M0S</RemainingWork>
      <ConstraintType>7</ConstraintType>
      <ConstraintDate>2027-04-06T17:00:00</ConstraintDate>
      <PredecessorLink>
        <PredecessorUID>45</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <ExtendedAttribute>
        <FieldID>188743783</FieldID>
        <Value>PT8H0M0S</Value>
      </ExtendedAttribute>
      <ExtendedAttribute>
        <FieldID>188743785</FieldID>
        <Value>PT12H0M0S</Value>
      </ExtendedAttribute>
      <Baseline>
        <Number>0</Number>
        <Start>2027-03-31T08:00:00</Start>
        <Finish>2027-03-31T17:00:00</Finish>
        <Duration>PT8H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT8H0M0S</Work>
        <Cost>56000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>46</UID>
        <Start>2027-03-31T08:00:00</Start>
        <Finish>2027-03-31T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>46</UID>
        <Start>2027-03-31T08:00:00</Start>
        <Finish>2027-03-31T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>47</UID>
      <ID>47</ID>
      <Name>Final meter readings and utilities closed</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-01T08:00:00</Start>
      <Finish>2027-04-01T17:00:00</Finish>
      <Duration>PT8H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT8H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>48000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT8H0M0S</RemainingWork>
      <ConstraintType>7</ConstraintType>
      <ConstraintDate>2027-04-07T17:00:00</ConstraintDate>
      <PredecessorLink>
        <PredecessorUID>46</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <ExtendedAttribute>
        <FieldID>188743783</FieldID>
        <Value>PT8H0M0S</Value>
      </ExtendedAttribute>
      <ExtendedAttribute>
        <FieldID>188743785</FieldID>
        <Value>PT12H0M0S</Value>
      </ExtendedAttribute>
      <Baseline>
        <Number>0</Number>
        <Start>2027-04-01T08:00:00</Start>
        <Finish>2027-04-01T17:00:00</Finish>
        <Duration>PT8H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT8H0M0S</Work>
        <Cost>48000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>47</UID>
        <Start>2027-04-01T08:00:00</Start>
        <Finish>2027-04-01T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>47</UID>
        <Start>2027-04-01T08:00:00</Start>
        <Finish>2027-04-01T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>48000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>48</UID>
      <ID>48</ID>
      <Name>Close the project and lessons learned</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5.4</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-02T08:00:00</Start>
      <Finish>2027-04-05T17:00:00</Finish>
      <Duration>PT16H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT16H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>112000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT16H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>47</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>43</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <ExtendedAttribute>
        <FieldID>188743783</FieldID>
        <Value>PT12H0M0S</Value>
      </ExtendedAttribute>
      <ExtendedAttribute>
        <FieldID>188743785</FieldID>
        <Value>PT24H0M0S</Value>
      </ExtendedAttribute>
      <Baseline>
        <Number>0</Number>
        <Start>2027-04-02T08:00:00</Start>
        <Finish>2027-04-05T17:00:00</Finish>
        <Duration>PT16H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT16H0M0S</Work>
        <Cost>112000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>48</UID>
        <Start>2027-04-02T08:00:00</Start>
        <Finish>2027-04-05T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>48</UID>
        <Start>2027-04-02T08:00:00</Start>
        <Finish>2027-04-05T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>112000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>49</UID>
      <ID>49</ID>
      <Name>Move complete</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5.5</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-05T17:00:00</Start>
      <Finish>2027-04-05T17:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>48</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-04-05T17:00:00</Start>
        <Finish>2027-04-05T17:00:00</Finish>
        <Duration>PT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
      </Baseline>
    </Task>
  </Tasks>
  <Resources>
    <Resource>
      <UID>1</UID>
      <ID>1</ID>
      <Name>Facilities manager</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <Initials>FM</Initials>
      <Group>Facilities</Group>
      <MaxUnits>1</MaxUnits>
      <StandardRate>70</StandardRate>
    </Resource>
    <Resource>
      <UID>2</UID>
      <ID>2</ID>
      <Name>Finance officer</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <Initials>FO</Initials>
      <Group>Finance</Group>
      <MaxUnits>1</MaxUnits>
      <StandardRate>60</StandardRate>
    </Resource>
    <Resource>
      <UID>3</UID>
      <ID>3</ID>
      <Name>HR and communications</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <Initials>HR</Initials>
      <Group>People</Group>
      <MaxUnits>1</MaxUnits>
      <StandardRate>55</StandardRate>
    </Resource>
    <Resource>
      <UID>4</UID>
      <ID>4</ID>
      <Name>IT manager</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <Initials>IT</Initials>
      <Group>IT</Group>
      <MaxUnits>1</MaxUnits>
      <StandardRate>80</StandardRate>
    </Resource>
    <Resource>
      <UID>5</UID>
      <ID>5</ID>
      <Name>IT technicians</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <Initials>TE</Initials>
      <Group>IT</Group>
      <MaxUnits>3</MaxUnits>
      <StandardRate>50</StandardRate>
    </Resource>
    <Resource>
      <UID>6</UID>
      <ID>6</ID>
      <Name>Fit-out contractor</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <Initials>FT</Initials>
      <Group>Contractors</Group>
      <MaxUnits>4</MaxUnits>
      <StandardRate>65</StandardRate>
    </Resource>
    <Resource>
      <UID>7</UID>
      <ID>7</ID>
      <Name>Furniture supplier</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <Initials>FS</Initials>
      <Group>Contractors</Group>
      <MaxUnits>2</MaxUnits>
      <StandardRate>45</StandardRate>
    </Resource>
    <Resource>
      <UID>8</UID>
      <ID>8</ID>
      <Name>Removal company</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <Initials>RC</Initials>
      <Group>Contractors</Group>
      <MaxUnits>6</MaxUnits>
      <StandardRate>40</StandardRate>
    </Resource>
    <Resource>
      <UID>9</UID>
      <ID>9</ID>
      <Name>Cleaning contractor</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <Initials>CL</Initials>
      <Group>Contractors</Group>
      <MaxUnits>3</MaxUnits>
      <StandardRate>30</StandardRate>
    </Resource>
  </Resources>
  <Assignments>
    <Assignment>
      <UID>1</UID>
      <TaskUID>4</TaskUID>
      <ResourceUID>1</ResourceUID>
      <PercentWorkComplete>100</PercentWorkComplete>
      <ActualFinish>2027-01-07T17:00:00</ActualFinish>
      <ActualStart>2027-01-04T08:00:00</ActualStart>
      <ActualWork>PT32H0M0S</ActualWork>
      <Finish>2027-01-07T17:00:00</Finish>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <Start>2027-01-04T08:00:00</Start>
      <Units>1</Units>
      <Work>PT32H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>2</UID>
      <TaskUID>5</TaskUID>
      <ResourceUID>1</ResourceUID>
      <PercentWorkComplete>100</PercentWorkComplete>
      <ActualFinish>2027-01-14T17:00:00</ActualFinish>
      <ActualStart>2027-01-08T08:00:00</ActualStart>
      <ActualWork>PT40H0M0S</ActualWork>
      <Finish>2027-01-14T17:00:00</Finish>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <Start>2027-01-08T08:00:00</Start>
      <Units>1</Units>
      <Work>PT40H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>3</UID>
      <TaskUID>5</TaskUID>
      <ResourceUID>3</ResourceUID>
      <PercentWorkComplete>100</PercentWorkComplete>
      <ActualFinish>2027-01-14T17:00:00</ActualFinish>
      <ActualStart>2027-01-08T08:00:00</ActualStart>
      <ActualWork>PT20H0M0S</ActualWork>
      <Finish>2027-01-14T17:00:00</Finish>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <Start>2027-01-08T08:00:00</Start>
      <Units>0.5</Units>
      <Work>PT20H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>4</UID>
      <TaskUID>6</TaskUID>
      <ResourceUID>2</ResourceUID>
      <PercentWorkComplete>100</PercentWorkComplete>
      <ActualFinish>2027-01-19T17:00:00</ActualFinish>
      <ActualStart>2027-01-15T08:00:00</ActualStart>
      <ActualWork>PT24H0M0S</ActualWork>
      <Finish>2027-01-19T17:00:00</Finish>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <Start>2027-01-15T08:00:00</Start>
      <Units>1</Units>
      <Work>PT24H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>5</UID>
      <TaskUID>8</TaskUID>
      <ResourceUID>1</ResourceUID>
      <PercentWorkComplete>100</PercentWorkComplete>
      <ActualFinish>2027-01-26T17:00:00</ActualFinish>
      <ActualStart>2027-01-20T08:00:00</ActualStart>
      <ActualWork>PT40H0M0S</ActualWork>
      <Finish>2027-01-26T17:00:00</Finish>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <Start>2027-01-20T08:00:00</Start>
      <Units>1</Units>
      <Work>PT40H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>6</UID>
      <TaskUID>8</TaskUID>
      <ResourceUID>2</ResourceUID>
      <PercentWorkComplete>100</PercentWorkComplete>
      <ActualFinish>2027-01-26T17:00:00</ActualFinish>
      <ActualStart>2027-01-20T08:00:00</ActualStart>
      <ActualWork>PT10H0M0S</ActualWork>
      <Finish>2027-01-26T17:00:00</Finish>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <Start>2027-01-20T08:00:00</Start>
      <Units>0.25</Units>
      <Work>PT10H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>7</UID>
      <TaskUID>9</TaskUID>
      <ResourceUID>6</ResourceUID>
      <PercentWorkComplete>100</PercentWorkComplete>
      <ActualFinish>2027-02-05T17:00:00</ActualFinish>
      <ActualStart>2027-01-27T08:00:00</ActualStart>
      <ActualWork>PT64H0M0S</ActualWork>
      <Finish>2027-02-05T17:00:00</Finish>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <Start>2027-01-27T08:00:00</Start>
      <Units>1</Units>
      <Work>PT64H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>8</UID>
      <TaskUID>10</TaskUID>
      <ResourceUID>1</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-02-11T17:00:00</Finish>
      <RemainingWork>PT32H0M0S</RemainingWork>
      <Start>2027-02-08T08:00:00</Start>
      <Units>1</Units>
      <Work>PT32H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>9</UID>
      <TaskUID>13</TaskUID>
      <ResourceUID>6</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-02-18T17:00:00</Finish>
      <RemainingWork>PT80H0M0S</RemainingWork>
      <Start>2027-02-12T08:00:00</Start>
      <Units>2</Units>
      <Work>PT80H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>10</UID>
      <TaskUID>14</TaskUID>
      <ResourceUID>6</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-03-02T17:00:00</Finish>
      <RemainingWork>PT192H0M0S</RemainingWork>
      <Start>2027-02-19T08:00:00</Start>
      <Units>3</Units>
      <Work>PT192H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>11</UID>
      <TaskUID>15</TaskUID>
      <ResourceUID>6</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-02-26T17:00:00</Finish>
      <RemainingWork>PT48H0M0S</RemainingWork>
      <Start>2027-02-19T08:00:00</Start>
      <Units>1</Units>
      <Work>PT48H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>12</UID>
      <TaskUID>16</TaskUID>
      <ResourceUID>5</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-03-02T17:00:00</Finish>
      <RemainingWork>PT80H0M0S</RemainingWork>
      <Start>2027-02-24T08:00:00</Start>
      <Units>2</Units>
      <Work>PT80H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>13</UID>
      <TaskUID>17</TaskUID>
      <ResourceUID>6</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-03-10T17:00:00</Finish>
      <RemainingWork>PT144H0M0S</RemainingWork>
      <Start>2027-03-03T08:00:00</Start>
      <Units>3</Units>
      <Work>PT144H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>14</UID>
      <TaskUID>19</TaskUID>
      <ResourceUID>1</ResourceUID>
      <PercentWorkComplete>100</PercentWorkComplete>
      <ActualFinish>2027-01-20T17:00:00</ActualFinish>
      <ActualStart>2027-01-15T08:00:00</ActualStart>
      <ActualWork>PT32H0M0S</ActualWork>
      <Finish>2027-01-20T17:00:00</Finish>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <Start>2027-01-15T08:00:00</Start>
      <Units>1</Units>
      <Work>PT32H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>15</UID>
      <TaskUID>20</TaskUID>
      <ResourceUID>7</ResourceUID>
      <PercentWorkComplete>64</PercentWorkComplete>
      <ActualStart>2027-01-21T08:00:00</ActualStart>
      <ActualWork>PT24H19M0S</ActualWork>
      <Finish>2027-02-16T17:00:00</Finish>
      <RemainingWork>PT13H41M0S</RemainingWork>
      <Start>2027-01-21T08:00:00</Start>
      <Units>0.25</Units>
      <Work>PT38H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>16</UID>
      <TaskUID>21</TaskUID>
      <ResourceUID>7</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-03-16T17:00:00</Finish>
      <RemainingWork>PT64H0M0S</RemainingWork>
      <Start>2027-03-11T08:00:00</Start>
      <Units>2</Units>
      <Work>PT64H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>17</UID>
      <TaskUID>25</TaskUID>
      <ResourceUID>4</ResourceUID>
      <PercentWorkComplete>40</PercentWorkComplete>
      <ActualStart>2027-01-27T08:00:00</ActualStart>
      <ActualWork>PT16H0M0S</ActualWork>
      <Finish>2027-02-23T17:00:00</Finish>
      <RemainingWork>PT24H0M0S</RemainingWork>
      <Start>2027-01-27T08:00:00</Start>
      <Units>0.25</Units>
      <Work>PT40H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>18</UID>
      <TaskUID>26</TaskUID>
      <ResourceUID>4</ResourceUID>
      <PercentWorkComplete>100</PercentWorkComplete>
      <ActualFinish>2027-02-01T17:00:00</ActualFinish>
      <ActualStart>2027-01-27T08:00:00</ActualStart>
      <ActualWork>PT32H0M0S</ActualWork>
      <Finish>2027-02-01T17:00:00</Finish>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <Start>2027-01-27T08:00:00</Start>
      <Units>1</Units>
      <Work>PT32H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>19</UID>
      <TaskUID>27</TaskUID>
      <ResourceUID>5</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-03-05T17:00:00</Finish>
      <RemainingWork>PT48H0M0S</RemainingWork>
      <Start>2027-03-03T08:00:00</Start>
      <Units>2</Units>
      <Work>PT48H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>20</UID>
      <TaskUID>28</TaskUID>
      <ResourceUID>4</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-03-08T17:00:00</Finish>
      <RemainingWork>PT8H0M0S</RemainingWork>
      <Start>2027-03-08T08:00:00</Start>
      <Units>1</Units>
      <Work>PT8H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>21</UID>
      <TaskUID>30</TaskUID>
      <ResourceUID>5</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-03-10T17:00:00</Finish>
      <RemainingWork>PT24H0M0S</RemainingWork>
      <Start>2027-03-08T08:00:00</Start>
      <Units>1</Units>
      <Work>PT24H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>22</UID>
      <TaskUID>31</TaskUID>
      <ResourceUID>5</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-03-09T17:00:00</Finish>
      <RemainingWork>PT16H0M0S</RemainingWork>
      <Start>2027-03-08T08:00:00</Start>
      <Units>1</Units>
      <Work>PT16H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>23</UID>
      <TaskUID>32</TaskUID>
      <ResourceUID>4</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-03-12T17:00:00</Finish>
      <RemainingWork>PT16H0M0S</RemainingWork>
      <Start>2027-03-11T08:00:00</Start>
      <Units>1</Units>
      <Work>PT16H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>24</UID>
      <TaskUID>32</TaskUID>
      <ResourceUID>5</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-03-12T17:00:00</Finish>
      <RemainingWork>PT16H0M0S</RemainingWork>
      <Start>2027-03-11T08:00:00</Start>
      <Units>1</Units>
      <Work>PT16H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>25</UID>
      <TaskUID>35</TaskUID>
      <ResourceUID>1</ResourceUID>
      <PercentWorkComplete>100</PercentWorkComplete>
      <ActualFinish>2027-01-21T17:00:00</ActualFinish>
      <ActualStart>2027-01-20T08:00:00</ActualStart>
      <ActualWork>PT16H0M0S</ActualWork>
      <Finish>2027-01-21T17:00:00</Finish>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <Start>2027-01-20T08:00:00</Start>
      <Units>1</Units>
      <Work>PT16H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>26</UID>
      <TaskUID>36</TaskUID>
      <ResourceUID>1</ResourceUID>
      <PercentWorkComplete>100</PercentWorkComplete>
      <ActualFinish>2027-01-14T17:00:00</ActualFinish>
      <ActualStart>2027-01-08T08:00:00</ActualStart>
      <ActualWork>PT20H0M0S</ActualWork>
      <Finish>2027-01-14T17:00:00</Finish>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <Start>2027-01-08T08:00:00</Start>
      <Units>0.5</Units>
      <Work>PT20H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>27</UID>
      <TaskUID>37</TaskUID>
      <ResourceUID>3</ResourceUID>
      <PercentWorkComplete>20</PercentWorkComplete>
      <ActualStart>2027-02-11T08:00:00</ActualStart>
      <ActualWork>PT8H0M0S</ActualWork>
      <Finish>2027-02-17T17:00:00</Finish>
      <RemainingWork>PT32H0M0S</RemainingWork>
      <Start>2027-02-11T08:00:00</Start>
      <Units>1</Units>
      <Work>PT40H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>28</UID>
      <TaskUID>38</TaskUID>
      <ResourceUID>8</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-03-19T17:00:00</Finish>
      <RemainingWork>PT48H0M0S</RemainingWork>
      <Start>2027-03-17T08:00:00</Start>
      <Units>2</Units>
      <Work>PT48H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>29</UID>
      <TaskUID>40</TaskUID>
      <ResourceUID>8</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-03-23T17:00:00</Finish>
      <RemainingWork>PT96H0M0S</RemainingWork>
      <Start>2027-03-22T08:00:00</Start>
      <Units>6</Units>
      <Work>PT96H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>30</UID>
      <TaskUID>41</TaskUID>
      <ResourceUID>5</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-03-23T17:00:00</Finish>
      <RemainingWork>PT48H0M0S</RemainingWork>
      <Start>2027-03-22T08:00:00</Start>
      <Units>3</Units>
      <Work>PT48H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>31</UID>
      <TaskUID>42</TaskUID>
      <ResourceUID>3</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-03-25T17:00:00</Finish>
      <RemainingWork>PT16H0M0S</RemainingWork>
      <Start>2027-03-24T08:00:00</Start>
      <Units>1</Units>
      <Work>PT16H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>32</UID>
      <TaskUID>42</TaskUID>
      <ResourceUID>8</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-03-25T17:00:00</Finish>
      <RemainingWork>PT16H0M0S</RemainingWork>
      <Start>2027-03-24T08:00:00</Start>
      <Units>1</Units>
      <Work>PT16H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>33</UID>
      <TaskUID>45</TaskUID>
      <ResourceUID>9</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-03-30T17:00:00</Finish>
      <RemainingWork>PT120H0M0S</RemainingWork>
      <Start>2027-03-24T08:00:00</Start>
      <Units>3</Units>
      <Work>PT120H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>34</UID>
      <TaskUID>46</TaskUID>
      <ResourceUID>1</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-03-31T17:00:00</Finish>
      <RemainingWork>PT8H0M0S</RemainingWork>
      <Start>2027-03-31T08:00:00</Start>
      <Units>1</Units>
      <Work>PT8H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>35</UID>
      <TaskUID>47</TaskUID>
      <ResourceUID>2</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-04-01T17:00:00</Finish>
      <RemainingWork>PT8H0M0S</RemainingWork>
      <Start>2027-04-01T08:00:00</Start>
      <Units>1</Units>
      <Work>PT8H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>36</UID>
      <TaskUID>48</TaskUID>
      <ResourceUID>1</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-04-05T17:00:00</Finish>
      <RemainingWork>PT16H0M0S</RemainingWork>
      <Start>2027-04-02T08:00:00</Start>
      <Units>1</Units>
      <Work>PT16H0M0S</Work>
    </Assignment>
  </Assignments>
</Project>