<?xml version="1.0" encoding="UTF-8" standalone="yes"?>
<Project xmlns="http://schemas.microsoft.com/project">
  <SaveVersion>14</SaveVersion>
  <Name>Plant maintenance shutdown</Name>
  <Title>Plant maintenance shutdown</Title>
  <ScheduleFromStart>1</ScheduleFromStart>
  <StartDate>2027-01-04T08:00:00</StartDate>
  <FinishDate>2027-05-03T17:00:00</FinishDate>
  <CalendarUID>1</CalendarUID>
  <DefaultStartTime>08:00:00</DefaultStartTime>
  <DefaultFinishTime>17:00:00</DefaultFinishTime>
  <DurationFormat>7</DurationFormat>
  <StatusDate>2027-02-22T17:00:00</StatusDate>
  <NewTasksAreManual>0</NewTasksAreManual>
  <ProjectExternallyEdited>0</ProjectExternallyEdited>
  <ExtendedAttributes>
    <ExtendedAttribute>
      <FieldID>188743783</FieldID>
      <FieldName>Duration1</FieldName>
      <Alias>Optimistic Duration</Alias>
    </ExtendedAttribute>
    <ExtendedAttribute>
      <FieldID>188743785</FieldID>
      <FieldName>Duration3</FieldName>
      <Alias>Pessimistic Duration</Alias>
    </ExtendedAttribute>
  </ExtendedAttributes>
  <Calendars>
    <Calendar>
      <UID>1</UID>
      <Name>Standard</Name>
      <IsBaseCalendar>1</IsBaseCalendar>
      <BaseCalendarUID>-1</BaseCalendarUID>
      <WeekDays>
        <WeekDay>
          <DayType>1</DayType>
          <DayWorking>0</DayWorking>
        </WeekDay>
        <WeekDay>
          <DayType>2</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>3</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>4</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>5</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>6</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>7</DayType>
          <DayWorking>0</DayWorking>
        </WeekDay>
      </WeekDays>
    </Calendar>
  </Calendars>
  <Tasks>
    <Task>
      <UID>0</UID>
      <ID>0</ID>
      <Name>Plant maintenance shutdown</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>0</OutlineNumber>
      <OutlineLevel>0</OutlineLevel>
      <Start>2027-01-04T08:00:00</Start>
      <Finish>2027-05-03T17:00:00</Finish>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-05-03T17:00:00</Finish>
        <Work>PT2165H36M0S</Work>
        <Cost>14152000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-01-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-05T08:00:00</Start>
        <Finish>2027-01-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-06T08:00:00</Start>
        <Finish>2027-01-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-07T08:00:00</Start>
        <Finish>2027-01-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-08T08:00:00</Start>
        <Finish>2027-01-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-11T08:00:00</Start>
        <Finish>2027-01-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-12T08:00:00</Start>
        <Finish>2027-01-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-13T08:00:00</Start>
        <Finish>2027-01-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-14T08:00:00</Start>
        <Finish>2027-01-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-15T08:00:00</Start>
        <Finish>2027-01-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-18T08:00:00</Start>
        <Finish>2027-01-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-19T08:00:00</Start>
        <Finish>2027-01-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-20T08:00:00</Start>
        <Finish>2027-01-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-21T08:00:00</Start>
        <Finish>2027-01-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-22T08:00:00</Start>
        <Finish>2027-01-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-01-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT40H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-26T08:00:00</Start>
        <Finish>2027-01-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT40H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-01-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT40H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-28T08:00:00</Start>
        <Finish>2027-01-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT40H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-01-29T08:00:00</Start>
        <Finish>2027-01-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT40H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-01T08:00:00</Start>
        <Finish>2027-02-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT28H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-02T08:00:00</Start>
        <Finish>2027-02-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT28H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-03T08:00:00</Start>
        <Finish>2027-02-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT28H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-04T08:00:00</Start>
        <Finish>2027-02-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT20H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-05T08:00:00</Start>
        <Finish>2027-02-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT20H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-08T08:00:00</Start>
        <Finish>2027-02-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-09T08:00:00</Start>
        <Finish>2027-02-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-10T08:00:00</Start>
        <Finish>2027-02-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT62H24M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-12T08:00:00</Start>
        <Finish>2027-02-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT62H24M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-15T08:00:00</Start>
        <Finish>2027-02-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT62H24M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-16T08:00:00</Start>
        <Finish>2027-02-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT52H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-17T08:00:00</Start>
        <Finish>2027-02-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT52H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-18T08:00:00</Start>
        <Finish>2027-02-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT52H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-19T08:00:00</Start>
        <Finish>2027-02-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT52H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-22T08:00:00</Start>
        <Finish>2027-02-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT52H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-23T08:00:00</Start>
        <Finish>2027-02-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT20H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-24T08:00:00</Start>
        <Finish>2027-02-25T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT20H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-25T08:00:00</Start>
        <Finish>2027-02-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-02-26T08:00:00</Start>
        <Finish>2027-02-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-01T08:00:00</Start>
        <Finish>2027-03-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-02T08:00:00</Start>
        <Finish>2027-03-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-03T08:00:00</Start>
        <Finish>2027-03-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-04T08:00:00</Start>
        <Finish>2027-03-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-05T08:00:00</Start>
        <Finish>2027-03-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-08T08:00:00</Start>
        <Finish>2027-03-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-09T08:00:00</Start>
        <Finish>2027-03-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-10T08:00:00</Start>
        <Finish>2027-03-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-11T08:00:00</Start>
        <Finish>2027-03-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT3H12M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-12T08:00:00</Start>
        <Finish>2027-03-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT3H12M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-15T08:00:00</Start>
        <Finish>2027-03-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-16T08:00:00</Start>
        <Finish>2027-03-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-17T08:00:00</Start>
        <Finish>2027-03-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-18T08:00:00</Start>
        <Finish>2027-03-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-19T08:00:00</Start>
        <Finish>2027-03-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-29T08:00:00</Start>
        <Finish>2027-03-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-30T08:00:00</Start>
        <Finish>2027-03-31T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-03-31T08:00:00</Start>
        <Finish>2027-04-01T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-01T08:00:00</Start>
        <Finish>2027-04-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT72H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-02T08:00:00</Start>
        <Finish>2027-04-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT72H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-05T08:00:00</Start>
        <Finish>2027-04-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT112H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-06T08:00:00</Start>
        <Finish>2027-04-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT120H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-07T08:00:00</Start>
        <Finish>2027-04-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT88H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-08T08:00:00</Start>
        <Finish>2027-04-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT64H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-09T08:00:00</Start>
        <Finish>2027-04-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT64H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-12T08:00:00</Start>
        <Finish>2027-04-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-13T08:00:00</Start>
        <Finish>2027-04-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-14T08:00:00</Start>
        <Finish>2027-04-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-15T08:00:00</Start>
        <Finish>2027-04-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-16T08:00:00</Start>
        <Finish>2027-04-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-19T08:00:00</Start>
        <Finish>2027-04-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-20T08:00:00</Start>
        <Finish>2027-04-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-21T08:00:00</Start>
        <Finish>2027-04-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-22T08:00:00</Start>
        <Finish>2027-04-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-23T08:00:00</Start>
        <Finish>2027-04-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-27T08:00:00</Start>
        <Finish>2027-04-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-28T08:00:00</Start>
        <Finish>2027-04-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT48H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-29T08:00:00</Start>
        <Finish>2027-04-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT48H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-04-30T08:00:00</Start>
        <Finish>2027-05-01T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT48H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>0</UID>
        <Start>2027-05-03T08:00:00</Start>
        <Finish>2027-05-03T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT48H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-01-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-05T08:00:00</Start>
        <Finish>2027-01-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-06T08:00:00</Start>
        <Finish>2027-01-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-07T08:00:00</Start>
        <Finish>2027-01-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-08T08:00:00</Start>
        <Finish>2027-01-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-11T08:00:00</Start>
        <Finish>2027-01-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-12T08:00:00</Start>
        <Finish>2027-01-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-13T08:00:00</Start>
        <Finish>2027-01-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-14T08:00:00</Start>
        <Finish>2027-01-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-15T08:00:00</Start>
        <Finish>2027-01-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-18T08:00:00</Start>
        <Finish>2027-01-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-19T08:00:00</Start>
        <Finish>2027-01-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-20T08:00:00</Start>
        <Finish>2027-01-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-21T08:00:00</Start>
        <Finish>2027-01-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-22T08:00:00</Start>
        <Finish>2027-01-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-01-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>313600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-26T08:00:00</Start>
        <Finish>2027-01-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>313600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-01-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>313600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-28T08:00:00</Start>
        <Finish>2027-01-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>313600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-01-29T08:00:00</Start>
        <Finish>2027-01-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>313600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-01T08:00:00</Start>
        <Finish>2027-02-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>228800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-02T08:00:00</Start>
        <Finish>2027-02-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>228800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-03T08:00:00</Start>
        <Finish>2027-02-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>228800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-04T08:00:00</Start>
        <Finish>2027-02-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>172800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-05T08:00:00</Start>
        <Finish>2027-02-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>172800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-08T08:00:00</Start>
        <Finish>2027-02-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>84800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-09T08:00:00</Start>
        <Finish>2027-02-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>84800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-10T08:00:00</Start>
        <Finish>2027-02-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>84800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>396800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-12T08:00:00</Start>
        <Finish>2027-02-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>396800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-15T08:00:00</Start>
        <Finish>2027-02-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>396800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-16T08:00:00</Start>
        <Finish>2027-02-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>265600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-17T08:00:00</Start>
        <Finish>2027-02-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>265600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-18T08:00:00</Start>
        <Finish>2027-02-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>265600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-19T08:00:00</Start>
        <Finish>2027-02-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>265600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-22T08:00:00</Start>
        <Finish>2027-02-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>265600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-23T08:00:00</Start>
        <Finish>2027-02-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>121600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-24T08:00:00</Start>
        <Finish>2027-02-25T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>121600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-25T08:00:00</Start>
        <Finish>2027-02-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-02-26T08:00:00</Start>
        <Finish>2027-02-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-01T08:00:00</Start>
        <Finish>2027-03-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-02T08:00:00</Start>
        <Finish>2027-03-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-03T08:00:00</Start>
        <Finish>2027-03-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-04T08:00:00</Start>
        <Finish>2027-03-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-05T08:00:00</Start>
        <Finish>2027-03-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-08T08:00:00</Start>
        <Finish>2027-03-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-09T08:00:00</Start>
        <Finish>2027-03-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-10T08:00:00</Start>
        <Finish>2027-03-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-11T08:00:00</Start>
        <Finish>2027-03-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>19200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-12T08:00:00</Start>
        <Finish>2027-03-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>19200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-15T08:00:00</Start>
        <Finish>2027-03-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-16T08:00:00</Start>
        <Finish>2027-03-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-17T08:00:00</Start>
        <Finish>2027-03-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-18T08:00:00</Start>
        <Finish>2027-03-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-19T08:00:00</Start>
        <Finish>2027-03-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-29T08:00:00</Start>
        <Finish>2027-03-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-30T08:00:00</Start>
        <Finish>2027-03-31T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>142400</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-03-31T08:00:00</Start>
        <Finish>2027-04-01T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>142400</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-01T08:00:00</Start>
        <Finish>2027-04-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>436800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-02T08:00:00</Start>
        <Finish>2027-04-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>436800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-05T08:00:00</Start>
        <Finish>2027-04-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>724800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-06T08:00:00</Start>
        <Finish>2027-04-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>774400</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-07T08:00:00</Start>
        <Finish>2027-04-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>600800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-08T08:00:00</Start>
        <Finish>2027-04-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>452000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-09T08:00:00</Start>
        <Finish>2027-04-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>452000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-12T08:00:00</Start>
        <Finish>2027-04-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>92800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-13T08:00:00</Start>
        <Finish>2027-04-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>139200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-14T08:00:00</Start>
        <Finish>2027-04-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>139200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-15T08:00:00</Start>
        <Finish>2027-04-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>139200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-16T08:00:00</Start>
        <Finish>2027-04-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>118400</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-19T08:00:00</Start>
        <Finish>2027-04-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>105600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-20T08:00:00</Start>
        <Finish>2027-04-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>145600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-21T08:00:00</Start>
        <Finish>2027-04-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>145600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-22T08:00:00</Start>
        <Finish>2027-04-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>145600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-23T08:00:00</Start>
        <Finish>2027-04-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>96000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-27T08:00:00</Start>
        <Finish>2027-04-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>144000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-28T08:00:00</Start>
        <Finish>2027-04-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>300000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-29T08:00:00</Start>
        <Finish>2027-04-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>300000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-04-30T08:00:00</Start>
        <Finish>2027-05-01T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>300000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>0</UID>
        <Start>2027-05-03T08:00:00</Start>
        <Finish>2027-05-03T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>300000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>1</UID>
      <ID>1</ID>
      <Name>Planning</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-04T08:00:00</Start>
      <Finish>2027-03-24T17:00:00</Finish>
      <Duration>PT464H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>9600</TotalSlack>
      <PercentComplete>76</PercentComplete>
      <Cost>4877600</Cost>
      <ActualCost>4392000</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-03-19T17:00:00</Finish>
        <Duration>PT440H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT672H48M0S</Work>
        <Cost>4848800</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-01-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-05T08:00:00</Start>
        <Finish>2027-01-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-06T08:00:00</Start>
        <Finish>2027-01-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-07T08:00:00</Start>
        <Finish>2027-01-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-08T08:00:00</Start>
        <Finish>2027-01-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-11T08:00:00</Start>
        <Finish>2027-01-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-12T08:00:00</Start>
        <Finish>2027-01-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-13T08:00:00</Start>
        <Finish>2027-01-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-14T08:00:00</Start>
        <Finish>2027-01-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-15T08:00:00</Start>
        <Finish>2027-01-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-18T08:00:00</Start>
        <Finish>2027-01-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-19T08:00:00</Start>
        <Finish>2027-01-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-20T08:00:00</Start>
        <Finish>2027-01-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-21T08:00:00</Start>
        <Finish>2027-01-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-22T08:00:00</Start>
        <Finish>2027-01-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-01-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT40H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-26T08:00:00</Start>
        <Finish>2027-01-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT40H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-01-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT40H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-28T08:00:00</Start>
        <Finish>2027-01-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT40H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-01-29T08:00:00</Start>
        <Finish>2027-01-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT40H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-02-01T08:00:00</Start>
        <Finish>2027-02-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT28H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-02-02T08:00:00</Start>
        <Finish>2027-02-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT28H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-02-03T08:00:00</Start>
        <Finish>2027-02-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT28H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-02-04T08:00:00</Start>
        <Finish>2027-02-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT20H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-02-05T08:00:00</Start>
        <Finish>2027-02-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT20H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-02-08T08:00:00</Start>
        <Finish>2027-02-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-02-09T08:00:00</Start>
        <Finish>2027-02-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-02-10T08:00:00</Start>
        <Finish>2027-02-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-02-12T08:00:00</Start>
        <Finish>2027-02-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-02-15T08:00:00</Start>
        <Finish>2027-02-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-02-16T08:00:00</Start>
        <Finish>2027-02-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-02-17T08:00:00</Start>
        <Finish>2027-02-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-02-18T08:00:00</Start>
        <Finish>2027-02-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-02-19T08:00:00</Start>
        <Finish>2027-02-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-02-22T08:00:00</Start>
        <Finish>2027-02-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-02-23T08:00:00</Start>
        <Finish>2027-02-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-02-24T08:00:00</Start>
        <Finish>2027-02-25T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-02-25T08:00:00</Start>
        <Finish>2027-02-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-02-26T08:00:00</Start>
        <Finish>2027-02-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-03-01T08:00:00</Start>
        <Finish>2027-03-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-03-02T08:00:00</Start>
        <Finish>2027-03-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-03-03T08:00:00</Start>
        <Finish>2027-03-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-03-04T08:00:00</Start>
        <Finish>2027-03-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-03-05T08:00:00</Start>
        <Finish>2027-03-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-03-08T08:00:00</Start>
        <Finish>2027-03-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-03-09T08:00:00</Start>
        <Finish>2027-03-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-03-10T08:00:00</Start>
        <Finish>2027-03-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-03-11T08:00:00</Start>
        <Finish>2027-03-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT3H12M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-03-12T08:00:00</Start>
        <Finish>2027-03-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT3H12M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-03-15T08:00:00</Start>
        <Finish>2027-03-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-03-16T08:00:00</Start>
        <Finish>2027-03-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-03-17T08:00:00</Start>
        <Finish>2027-03-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-03-18T08:00:00</Start>
        <Finish>2027-03-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>1</UID>
        <Start>2027-03-19T08:00:00</Start>
        <Finish>2027-03-19T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-01-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-05T08:00:00</Start>
        <Finish>2027-01-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-06T08:00:00</Start>
        <Finish>2027-01-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-07T08:00:00</Start>
        <Finish>2027-01-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-08T08:00:00</Start>
        <Finish>2027-01-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-11T08:00:00</Start>
        <Finish>2027-01-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-12T08:00:00</Start>
        <Finish>2027-01-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-13T08:00:00</Start>
        <Finish>2027-01-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-14T08:00:00</Start>
        <Finish>2027-01-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-15T08:00:00</Start>
        <Finish>2027-01-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-18T08:00:00</Start>
        <Finish>2027-01-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-19T08:00:00</Start>
        <Finish>2027-01-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-20T08:00:00</Start>
        <Finish>2027-01-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-21T08:00:00</Start>
        <Finish>2027-01-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-22T08:00:00</Start>
        <Finish>2027-01-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>88800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-01-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>313600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-26T08:00:00</Start>
        <Finish>2027-01-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>313600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-01-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>313600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-28T08:00:00</Start>
        <Finish>2027-01-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>313600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-01-29T08:00:00</Start>
        <Finish>2027-01-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>313600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-02-01T08:00:00</Start>
        <Finish>2027-02-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>228800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-02-02T08:00:00</Start>
        <Finish>2027-02-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>228800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-02-03T08:00:00</Start>
        <Finish>2027-02-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>228800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-02-04T08:00:00</Start>
        <Finish>2027-02-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>172800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-02-05T08:00:00</Start>
        <Finish>2027-02-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>172800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-02-08T08:00:00</Start>
        <Finish>2027-02-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>84800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-02-09T08:00:00</Start>
        <Finish>2027-02-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>84800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-02-10T08:00:00</Start>
        <Finish>2027-02-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>84800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-02-12T08:00:00</Start>
        <Finish>2027-02-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-02-15T08:00:00</Start>
        <Finish>2027-02-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-02-16T08:00:00</Start>
        <Finish>2027-02-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-02-17T08:00:00</Start>
        <Finish>2027-02-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-02-18T08:00:00</Start>
        <Finish>2027-02-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-02-19T08:00:00</Start>
        <Finish>2027-02-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-02-22T08:00:00</Start>
        <Finish>2027-02-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-02-23T08:00:00</Start>
        <Finish>2027-02-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-02-24T08:00:00</Start>
        <Finish>2027-02-25T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-02-25T08:00:00</Start>
        <Finish>2027-02-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-02-26T08:00:00</Start>
        <Finish>2027-02-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-03-01T08:00:00</Start>
        <Finish>2027-03-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-03-02T08:00:00</Start>
        <Finish>2027-03-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-03-03T08:00:00</Start>
        <Finish>2027-03-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-03-04T08:00:00</Start>
        <Finish>2027-03-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-03-05T08:00:00</Start>
        <Finish>2027-03-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-03-08T08:00:00</Start>
        <Finish>2027-03-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-03-09T08:00:00</Start>
        <Finish>2027-03-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-03-10T08:00:00</Start>
        <Finish>2027-03-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-03-11T08:00:00</Start>
        <Finish>2027-03-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>19200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-03-12T08:00:00</Start>
        <Finish>2027-03-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>19200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-03-15T08:00:00</Start>
        <Finish>2027-03-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-03-16T08:00:00</Start>
        <Finish>2027-03-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-03-17T08:00:00</Start>
        <Finish>2027-03-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-03-18T08:00:00</Start>
        <Finish>2027-03-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>1</UID>
        <Start>2027-03-19T08:00:00</Start>
        <Finish>2027-03-19T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>9600</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>2</UID>
      <ID>2</ID>
      <Name>Turnaround scope frozen</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-04T08:00:00</Start>
      <Finish>2027-01-04T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>9600</TotalSlack>
      <PercentComplete>100</PercentComplete>
      <ActualStart>2027-01-04T08:00:00</ActualStart>
      <ActualFinish>2027-01-04T08:00:00</ActualFinish>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-01-04T08:00:00</Finish>
        <Duration>PT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
      </Baseline>
    </Task>
    <Task>
      <UID>3</UID>
      <ID>3</ID>
      <Name>Work scope</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-04T08:00:00</Start>
      <Finish>2027-02-03T17:00:00</Finish>
      <Duration>PT184H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>57600</TotalSlack>
      <PercentComplete>100</PercentComplete>
      <Cost>1772000</Cost>
      <ActualCost>1772000</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-02-03T17:00:00</Finish>
        <Duration>PT184H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT244H0M0S</Work>
        <Cost>1772000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-01-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-05T08:00:00</Start>
        <Finish>2027-01-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-06T08:00:00</Start>
        <Finish>2027-01-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-07T08:00:00</Start>
        <Finish>2027-01-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-08T08:00:00</Start>
        <Finish>2027-01-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-11T08:00:00</Start>
        <Finish>2027-01-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-12T08:00:00</Start>
        <Finish>2027-01-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-13T08:00:00</Start>
        <Finish>2027-01-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-14T08:00:00</Start>
        <Finish>2027-01-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-15T08:00:00</Start>
        <Finish>2027-01-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-18T08:00:00</Start>
        <Finish>2027-01-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-19T08:00:00</Start>
        <Finish>2027-01-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-20T08:00:00</Start>
        <Finish>2027-01-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-21T08:00:00</Start>
        <Finish>2027-01-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-22T08:00:00</Start>
        <Finish>2027-01-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-01-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT20H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-26T08:00:00</Start>
        <Finish>2027-01-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT20H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-01-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT20H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-28T08:00:00</Start>
        <Finish>2027-01-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT20H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-01-29T08:00:00</Start>
        <Finish>2027-01-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT20H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-02-01T08:00:00</Start>
        <Finish>2027-02-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-02-02T08:00:00</Start>
        <Finish>2027-02-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>3</UID>
        <Start>2027-02-03T08:00:00</Start>
        <Finish>2027-02-03T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-01-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>60000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-05T08:00:00</Start>
        <Finish>2027-01-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>60000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-06T08:00:00</Start>
        <Finish>2027-01-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>60000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-07T08:00:00</Start>
        <Finish>2027-01-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>60000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-08T08:00:00</Start>
        <Finish>2027-01-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>60000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-11T08:00:00</Start>
        <Finish>2027-01-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>60000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-12T08:00:00</Start>
        <Finish>2027-01-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>60000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-13T08:00:00</Start>
        <Finish>2027-01-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>60000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-14T08:00:00</Start>
        <Finish>2027-01-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>60000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-15T08:00:00</Start>
        <Finish>2027-01-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>60000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-18T08:00:00</Start>
        <Finish>2027-01-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>60000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-19T08:00:00</Start>
        <Finish>2027-01-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>60000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-20T08:00:00</Start>
        <Finish>2027-01-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>60000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-21T08:00:00</Start>
        <Finish>2027-01-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>60000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-22T08:00:00</Start>
        <Finish>2027-01-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>60000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-01-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>140800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-26T08:00:00</Start>
        <Finish>2027-01-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>140800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-01-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>140800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-28T08:00:00</Start>
        <Finish>2027-01-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>140800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-01-29T08:00:00</Start>
        <Finish>2027-01-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>140800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-02-01T08:00:00</Start>
        <Finish>2027-02-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-02-02T08:00:00</Start>
        <Finish>2027-02-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>3</UID>
        <Start>2027-02-03T08:00:00</Start>
        <Finish>2027-02-03T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>4</UID>
      <ID>4</ID>
      <Name>Work list and job packs</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.2.1</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-04T08:00:00</Start>
      <Finish>2027-01-22T17:00:00</Finish>
      <Duration>PT120H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT120H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>57600</TotalSlack>
      <PercentComplete>100</PercentComplete>
      <PercentWorkComplete>100</PercentWorkComplete>
      <Cost>900000</Cost>
      <ActualStart>2027-01-04T08:00:00</ActualStart>
      <ActualFinish>2027-01-22T17:00:00</ActualFinish>
      <ActualCost>900000</ActualCost>
      <ActualWork>PT120H0M0S</ActualWork>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>2</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-01-22T17:00:00</Finish>
        <Duration>PT120H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT120H0M0S</Work>
        <Cost>900000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>4</UID>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-01-22T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT120H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>4</UID>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-01-22T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>900000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>5</UID>
      <ID>5</ID>
      <Name>Risk assessments and permit plan</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.2.2</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-25T08:00:00</Start>
      <Finish>2027-02-03T17:00:00</Finish>
      <Duration>PT64H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT64H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>115200</TotalSlack>
      <PercentComplete>100</PercentComplete>
      <PercentWorkComplete>100</PercentWorkComplete>
      <Cost>448000</Cost>
      <ActualStart>2027-01-25T08:00:00</ActualStart>
      <ActualFinish>2027-02-03T17:00:00</ActualFinish>
      <ActualCost>448000</ActualCost>
      <ActualWork>PT64H0M0S</ActualWork>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>4</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-02-03T17:00:00</Finish>
        <Duration>PT64H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT64H0M0S</Work>
        <Cost>448000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>5</UID>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-02-03T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT64H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>5</UID>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-02-03T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>448000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>6</UID>
      <ID>6</ID>
      <Name>Isolation plan</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.2.3</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-25T08:00:00</Start>
      <Finish>2027-01-29T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT60H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>192000</TotalSlack>
      <PercentComplete>100</PercentComplete>
      <PercentWorkComplete>100</PercentWorkComplete>
      <Cost>424000</Cost>
      <ActualStart>2027-01-25T08:00:00</ActualStart>
      <ActualFinish>2027-01-29T17:00:00</ActualFinish>
      <ActualCost>424000</ActualCost>
      <ActualWork>PT60H0M0S</ActualWork>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>4</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-01-29T17:00:00</Finish>
        <Duration>PT40H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT60H0M0S</Work>
        <Cost>424000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>6</UID>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-01-29T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT60H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>6</UID>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-01-29T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>424000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>7</UID>
      <ID>7</ID>
      <Name>Procurement</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-04T08:00:00</Start>
      <Finish>2027-03-24T17:00:00</Finish>
      <Duration>PT464H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>9600</TotalSlack>
      <PercentComplete>70</PercentComplete>
      <Cost>1977600</Cost>
      <ActualCost>1492000</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-03-19T17:00:00</Finish>
        <Duration>PT440H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT324H48M0S</Work>
        <Cost>1948800</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-01-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-01-05T08:00:00</Start>
        <Finish>2027-01-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-01-06T08:00:00</Start>
        <Finish>2027-01-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-01-07T08:00:00</Start>
        <Finish>2027-01-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-01-08T08:00:00</Start>
        <Finish>2027-01-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-01-11T08:00:00</Start>
        <Finish>2027-01-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-01-12T08:00:00</Start>
        <Finish>2027-01-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-01-13T08:00:00</Start>
        <Finish>2027-01-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-01-14T08:00:00</Start>
        <Finish>2027-01-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-01-15T08:00:00</Start>
        <Finish>2027-01-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-01-18T08:00:00</Start>
        <Finish>2027-01-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-01-19T08:00:00</Start>
        <Finish>2027-01-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-01-20T08:00:00</Start>
        <Finish>2027-01-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-01-21T08:00:00</Start>
        <Finish>2027-01-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-01-22T08:00:00</Start>
        <Finish>2027-01-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-01-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-01-26T08:00:00</Start>
        <Finish>2027-01-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-01-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-01-28T08:00:00</Start>
        <Finish>2027-01-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-01-29T08:00:00</Start>
        <Finish>2027-01-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-02-01T08:00:00</Start>
        <Finish>2027-02-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-02-02T08:00:00</Start>
        <Finish>2027-02-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-02-03T08:00:00</Start>
        <Finish>2027-02-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-02-04T08:00:00</Start>
        <Finish>2027-02-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-02-05T08:00:00</Start>
        <Finish>2027-02-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT12H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-02-08T08:00:00</Start>
        <Finish>2027-02-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-02-09T08:00:00</Start>
        <Finish>2027-02-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-02-10T08:00:00</Start>
        <Finish>2027-02-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-02-12T08:00:00</Start>
        <Finish>2027-02-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-02-15T08:00:00</Start>
        <Finish>2027-02-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-02-16T08:00:00</Start>
        <Finish>2027-02-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-02-17T08:00:00</Start>
        <Finish>2027-02-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-02-18T08:00:00</Start>
        <Finish>2027-02-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-02-19T08:00:00</Start>
        <Finish>2027-02-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-02-22T08:00:00</Start>
        <Finish>2027-02-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-02-23T08:00:00</Start>
        <Finish>2027-02-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-02-24T08:00:00</Start>
        <Finish>2027-02-25T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-02-25T08:00:00</Start>
        <Finish>2027-02-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-02-26T08:00:00</Start>
        <Finish>2027-02-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-03-01T08:00:00</Start>
        <Finish>2027-03-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-03-02T08:00:00</Start>
        <Finish>2027-03-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-03-03T08:00:00</Start>
        <Finish>2027-03-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-03-04T08:00:00</Start>
        <Finish>2027-03-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-03-05T08:00:00</Start>
        <Finish>2027-03-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-03-08T08:00:00</Start>
        <Finish>2027-03-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-03-09T08:00:00</Start>
        <Finish>2027-03-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-03-10T08:00:00</Start>
        <Finish>2027-03-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT4H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-03-11T08:00:00</Start>
        <Finish>2027-03-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT3H12M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-03-12T08:00:00</Start>
        <Finish>2027-03-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT3H12M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-03-15T08:00:00</Start>
        <Finish>2027-03-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-03-16T08:00:00</Start>
        <Finish>2027-03-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-03-17T08:00:00</Start>
        <Finish>2027-03-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-03-18T08:00:00</Start>
        <Finish>2027-03-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>7</UID>
        <Start>2027-03-19T08:00:00</Start>
        <Finish>2027-03-19T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT1H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-01-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-01-05T08:00:00</Start>
        <Finish>2027-01-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-01-06T08:00:00</Start>
        <Finish>2027-01-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-01-07T08:00:00</Start>
        <Finish>2027-01-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-01-08T08:00:00</Start>
        <Finish>2027-01-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-01-11T08:00:00</Start>
        <Finish>2027-01-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-01-12T08:00:00</Start>
        <Finish>2027-01-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-01-13T08:00:00</Start>
        <Finish>2027-01-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-01-14T08:00:00</Start>
        <Finish>2027-01-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-01-15T08:00:00</Start>
        <Finish>2027-01-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-01-18T08:00:00</Start>
        <Finish>2027-01-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-01-19T08:00:00</Start>
        <Finish>2027-01-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-01-20T08:00:00</Start>
        <Finish>2027-01-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-01-21T08:00:00</Start>
        <Finish>2027-01-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-01-22T08:00:00</Start>
        <Finish>2027-01-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-01-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>76800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-01-26T08:00:00</Start>
        <Finish>2027-01-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>76800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-01-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>76800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-01-28T08:00:00</Start>
        <Finish>2027-01-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>76800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-01-29T08:00:00</Start>
        <Finish>2027-01-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>76800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-02-01T08:00:00</Start>
        <Finish>2027-02-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>76800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-02-02T08:00:00</Start>
        <Finish>2027-02-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>76800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-02-03T08:00:00</Start>
        <Finish>2027-02-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>76800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-02-04T08:00:00</Start>
        <Finish>2027-02-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>76800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-02-05T08:00:00</Start>
        <Finish>2027-02-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>76800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-02-08T08:00:00</Start>
        <Finish>2027-02-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-02-09T08:00:00</Start>
        <Finish>2027-02-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-02-10T08:00:00</Start>
        <Finish>2027-02-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-02-12T08:00:00</Start>
        <Finish>2027-02-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-02-15T08:00:00</Start>
        <Finish>2027-02-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-02-16T08:00:00</Start>
        <Finish>2027-02-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-02-17T08:00:00</Start>
        <Finish>2027-02-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-02-18T08:00:00</Start>
        <Finish>2027-02-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-02-19T08:00:00</Start>
        <Finish>2027-02-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-02-22T08:00:00</Start>
        <Finish>2027-02-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-02-23T08:00:00</Start>
        <Finish>2027-02-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-02-24T08:00:00</Start>
        <Finish>2027-02-25T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-02-25T08:00:00</Start>
        <Finish>2027-02-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-02-26T08:00:00</Start>
        <Finish>2027-02-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-03-01T08:00:00</Start>
        <Finish>2027-03-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-03-02T08:00:00</Start>
        <Finish>2027-03-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-03-03T08:00:00</Start>
        <Finish>2027-03-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-03-04T08:00:00</Start>
        <Finish>2027-03-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-03-05T08:00:00</Start>
        <Finish>2027-03-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-03-08T08:00:00</Start>
        <Finish>2027-03-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-03-09T08:00:00</Start>
        <Finish>2027-03-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-03-10T08:00:00</Start>
        <Finish>2027-03-11T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>28800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-03-11T08:00:00</Start>
        <Finish>2027-03-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>19200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-03-12T08:00:00</Start>
        <Finish>2027-03-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>19200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-03-15T08:00:00</Start>
        <Finish>2027-03-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-03-16T08:00:00</Start>
        <Finish>2027-03-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-03-17T08:00:00</Start>
        <Finish>2027-03-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-03-18T08:00:00</Start>
        <Finish>2027-03-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>9600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>7</UID>
        <Start>2027-03-19T08:00:00</Start>
        <Finish>2027-03-19T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>9600</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>8</UID>
      <ID>8</ID>
      <Name>Long-lead: heat exchanger bundle</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.3.1</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-04T08:00:00</Start>
      <Finish>2027-03-24T17:00:00</Finish>
      <Duration>PT464H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT92H48M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>9600</TotalSlack>
      <PercentComplete>61</PercentComplete>
      <PercentWorkComplete>61</PercentWorkComplete>
      <Cost>556800</Cost>
      <ActualStart>2027-01-04T08:00:00</ActualStart>
      <ActualCost>339600</ActualCost>
      <ActualWork>PT56H36M0S</ActualWork>
      <RemainingWork>PT36H12M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>2</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-03-19T17:00:00</Finish>
        <Duration>PT440H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT88H0M0S</Work>
        <Cost>528000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>8</UID>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-03-19T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT88H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>8</UID>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-03-19T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>528000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>9</UID>
      <ID>9</ID>
      <Name>Long-lead: compressor spares</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.3.2</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-04T08:00:00</Start>
      <Finish>2027-03-12T17:00:00</Finish>
      <Duration>PT400H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT80H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>48000</TotalSlack>
      <PercentComplete>70</PercentComplete>
      <PercentWorkComplete>70</PercentWorkComplete>
      <Cost>480000</Cost>
      <ActualStart>2027-01-04T08:00:00</ActualStart>
      <ActualCost>336000</ActualCost>
      <ActualWork>PT56H0M0S</ActualWork>
      <RemainingWork>PT24H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>2</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-03-12T17:00:00</Finish>
        <Duration>PT400H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT80H0M0S</Work>
        <Cost>480000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>9</UID>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-03-12T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT80H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>9</UID>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-03-12T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>480000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>10</UID>
      <ID>10</ID>
      <Name>Long-lead: valves and gaskets</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.3.3</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-04T08:00:00</Start>
      <Finish>2027-03-10T17:00:00</Finish>
      <Duration>PT384H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT76H48M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>57600</TotalSlack>
      <PercentComplete>73</PercentComplete>
      <PercentWorkComplete>73</PercentWorkComplete>
      <Cost>460800</Cost>
      <ActualStart>2027-01-04T08:00:00</ActualStart>
      <ActualCost>336400</ActualCost>
      <ActualWork>PT56H4M0S</ActualWork>
      <RemainingWork>PT20H44M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>4</PredecessorUID>
        <Type>3</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-03-10T17:00:00</Finish>
        <Duration>PT384H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT76H48M0S</Work>
        <Cost>460800</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>10</UID>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-03-10T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT76H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>10</UID>
        <Start>2027-01-04T08:00:00</Start>
        <Finish>2027-03-10T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>460800</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>11</UID>
      <ID>11</ID>
      <Name>Consumables and scaffold material</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.3.4</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-25T08:00:00</Start>
      <Finish>2027-02-05T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT80H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>129600</TotalSlack>
      <PercentComplete>100</PercentComplete>
      <PercentWorkComplete>100</PercentWorkComplete>
      <Cost>480000</Cost>
      <ActualStart>2027-01-25T08:00:00</ActualStart>
      <ActualFinish>2027-02-05T17:00:00</ActualFinish>
      <ActualCost>480000</ActualCost>
      <ActualWork>PT80H0M0S</ActualWork>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>4</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-02-05T17:00:00</Finish>
        <Duration>PT80H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT80H0M0S</Work>
        <Cost>480000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>11</UID>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-02-05T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT80H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>11</UID>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-02-05T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>480000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>12</UID>
      <ID>12</ID>
      <Name>All materials on site</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.3.5</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-24T17:00:00</Start>
      <Finish>2027-03-24T17:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>9600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>8</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>9</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>10</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>11</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-03-19T17:00:00</Start>
        <Finish>2027-03-19T17:00:00</Finish>
        <Duration>PT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
      </Baseline>
    </Task>
    <Task>
      <UID>13</UID>
      <ID>13</ID>
      <Name>Contractors</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.4</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-25T08:00:00</Start>
      <Finish>2027-02-10T17:00:00</Finish>
      <Duration>PT104H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>105600</TotalSlack>
      <PercentComplete>100</PercentComplete>
      <Cost>1128000</Cost>
      <ActualCost>1128000</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-02-10T17:00:00</Finish>
        <Duration>PT104H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT104H0M0S</Work>
        <Cost>1128000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>13</UID>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-01-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>13</UID>
        <Start>2027-01-26T08:00:00</Start>
        <Finish>2027-01-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>13</UID>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-01-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>13</UID>
        <Start>2027-01-28T08:00:00</Start>
        <Finish>2027-01-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>13</UID>
        <Start>2027-01-29T08:00:00</Start>
        <Finish>2027-01-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>13</UID>
        <Start>2027-02-01T08:00:00</Start>
        <Finish>2027-02-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>13</UID>
        <Start>2027-02-02T08:00:00</Start>
        <Finish>2027-02-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>13</UID>
        <Start>2027-02-03T08:00:00</Start>
        <Finish>2027-02-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>13</UID>
        <Start>2027-02-04T08:00:00</Start>
        <Finish>2027-02-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>13</UID>
        <Start>2027-02-05T08:00:00</Start>
        <Finish>2027-02-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>13</UID>
        <Start>2027-02-08T08:00:00</Start>
        <Finish>2027-02-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>13</UID>
        <Start>2027-02-09T08:00:00</Start>
        <Finish>2027-02-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>13</UID>
        <Start>2027-02-10T08:00:00</Start>
        <Finish>2027-02-10T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>13</UID>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-01-26T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>96000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>13</UID>
        <Start>2027-01-26T08:00:00</Start>
        <Finish>2027-01-27T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>96000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>13</UID>
        <Start>2027-01-27T08:00:00</Start>
        <Finish>2027-01-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>96000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>13</UID>
        <Start>2027-01-28T08:00:00</Start>
        <Finish>2027-01-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>96000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>13</UID>
        <Start>2027-01-29T08:00:00</Start>
        <Finish>2027-01-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>96000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>13</UID>
        <Start>2027-02-01T08:00:00</Start>
        <Finish>2027-02-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>96000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>13</UID>
        <Start>2027-02-02T08:00:00</Start>
        <Finish>2027-02-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>96000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>13</UID>
        <Start>2027-02-03T08:00:00</Start>
        <Finish>2027-02-04T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>96000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>13</UID>
        <Start>2027-02-04T08:00:00</Start>
        <Finish>2027-02-05T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>96000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>13</UID>
        <Start>2027-02-05T08:00:00</Start>
        <Finish>2027-02-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>96000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>13</UID>
        <Start>2027-02-08T08:00:00</Start>
        <Finish>2027-02-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>13</UID>
        <Start>2027-02-09T08:00:00</Start>
        <Finish>2027-02-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>13</UID>
        <Start>2027-02-10T08:00:00</Start>
        <Finish>2027-02-10T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>14</UID>
      <ID>14</ID>
      <Name>Award contractor packages</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.4.1</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-25T08:00:00</Start>
      <Finish>2027-02-05T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT80H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>105600</TotalSlack>
      <PercentComplete>100</PercentComplete>
      <PercentWorkComplete>100</PercentWorkComplete>
      <Cost>960000</Cost>
      <ActualStart>2027-01-25T08:00:00</ActualStart>
      <ActualFinish>2027-02-05T17:00:00</ActualFinish>
      <ActualCost>960000</ActualCost>
      <ActualWork>PT80H0M0S</ActualWork>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>4</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-02-05T17:00:00</Finish>
        <Duration>PT80H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT80H0M0S</Work>
        <Cost>960000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>14</UID>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-02-05T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT80H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>14</UID>
        <Start>2027-01-25T08:00:00</Start>
        <Finish>2027-02-05T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>960000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>15</UID>
      <ID>15</ID>
      <Name>Contractor inductions</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.4.2</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-08T08:00:00</Start>
      <Finish>2027-02-10T17:00:00</Finish>
      <Duration>PT24H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT24H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>105600</TotalSlack>
      <PercentComplete>100</PercentComplete>
      <PercentWorkComplete>100</PercentWorkComplete>
      <Cost>168000</Cost>
      <ActualStart>2027-02-08T08:00:00</ActualStart>
      <ActualFinish>2027-02-10T17:00:00</ActualFinish>
      <ActualCost>168000</ActualCost>
      <ActualWork>PT24H0M0S</ActualWork>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>14</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>5</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-02-08T08:00:00</Start>
        <Finish>2027-02-10T17:00:00</Finish>
        <Duration>PT24H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT24H0M0S</Work>
        <Cost>168000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>15</UID>
        <Start>2027-02-08T08:00:00</Start>
        <Finish>2027-02-10T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>15</UID>
        <Start>2027-02-08T08:00:00</Start>
        <Finish>2027-02-10T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>168000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>16</UID>
      <ID>16</ID>
      <Name>Pre-shutdown</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-11T08:00:00</Start>
      <Finish>2027-03-29T08:00:00</Finish>
      <Duration>PT256H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>86</PercentComplete>
      <Cost>2473600</Cost>
      <ActualCost>2195200</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-03-29T08:00:00</Finish>
        <Duration>PT256H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT444H48M0S</Work>
        <Cost>2473600</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>16</UID>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT57H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>16</UID>
        <Start>2027-02-12T08:00:00</Start>
        <Finish>2027-02-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT57H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>16</UID>
        <Start>2027-02-15T08:00:00</Start>
        <Finish>2027-02-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT57H36M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>16</UID>
        <Start>2027-02-16T08:00:00</Start>
        <Finish>2027-02-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT48H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>16</UID>
        <Start>2027-02-17T08:00:00</Start>
        <Finish>2027-02-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT48H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>16</UID>
        <Start>2027-02-18T08:00:00</Start>
        <Finish>2027-02-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT48H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>16</UID>
        <Start>2027-02-19T08:00:00</Start>
        <Finish>2027-02-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT48H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>16</UID>
        <Start>2027-02-22T08:00:00</Start>
        <Finish>2027-02-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT48H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>16</UID>
        <Start>2027-02-23T08:00:00</Start>
        <Finish>2027-02-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>16</UID>
        <Start>2027-02-24T08:00:00</Start>
        <Finish>2027-02-24T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>16</UID>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-12T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>368000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>16</UID>
        <Start>2027-02-12T08:00:00</Start>
        <Finish>2027-02-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>368000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>16</UID>
        <Start>2027-02-15T08:00:00</Start>
        <Finish>2027-02-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>368000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>16</UID>
        <Start>2027-02-16T08:00:00</Start>
        <Finish>2027-02-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>236800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>16</UID>
        <Start>2027-02-17T08:00:00</Start>
        <Finish>2027-02-18T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>236800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>16</UID>
        <Start>2027-02-18T08:00:00</Start>
        <Finish>2027-02-19T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>236800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>16</UID>
        <Start>2027-02-19T08:00:00</Start>
        <Finish>2027-02-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>236800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>16</UID>
        <Start>2027-02-22T08:00:00</Start>
        <Finish>2027-02-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>236800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>16</UID>
        <Start>2027-02-23T08:00:00</Start>
        <Finish>2027-02-24T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>92800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>16</UID>
        <Start>2027-02-24T08:00:00</Start>
        <Finish>2027-02-24T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>92800</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>17</UID>
      <ID>17</ID>
      <Name>Pre-erect scaffolding</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-11T08:00:00</Start>
      <Finish>2027-02-22T17:00:00</Finish>
      <Duration>PT64H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT256H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>115200</TotalSlack>
      <PercentComplete>100</PercentComplete>
      <PercentWorkComplete>100</PercentWorkComplete>
      <Cost>1152000</Cost>
      <ActualStart>2027-02-11T08:00:00</ActualStart>
      <ActualFinish>2027-02-22T17:00:00</ActualFinish>
      <ActualCost>1152000</ActualCost>
      <ActualWork>PT256H0M0S</ActualWork>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>15</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>11</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-22T17:00:00</Finish>
        <Duration>PT64H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT256H0M0S</Work>
        <Cost>1152000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>17</UID>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-22T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT256H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>17</UID>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-22T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>1152000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>18</UID>
      <ID>18</ID>
      <Name>Prefabricate pipe spools</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-11T08:00:00</Start>
      <Finish>2027-02-24T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT160H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>105600</TotalSlack>
      <PercentComplete>70</PercentComplete>
      <PercentWorkComplete>70</PercentWorkComplete>
      <Cost>928000</Cost>
      <ActualStart>2027-02-11T08:00:00</ActualStart>
      <ActualCost>649600</ActualCost>
      <ActualWork>PT112H0M0S</ActualWork>
      <RemainingWork>PT48H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>15</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-24T17:00:00</Finish>
        <Duration>PT80H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT160H0M0S</Work>
        <Cost>928000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>18</UID>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-24T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT160H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>18</UID>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-24T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>928000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>19</UID>
      <ID>19</ID>
      <Name>Crane lift plan and mobilisation</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-11T08:00:00</Start>
      <Finish>2027-02-15T17:00:00</Finish>
      <Duration>PT24H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT28H48M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>139200</TotalSlack>
      <PercentComplete>100</PercentComplete>
      <PercentWorkComplete>100</PercentWorkComplete>
      <Cost>393600</Cost>
      <ActualStart>2027-02-11T08:00:00</ActualStart>
      <ActualFinish>2027-02-15T17:00:00</ActualFinish>
      <ActualCost>393600</ActualCost>
      <ActualWork>PT28H48M0S</ActualWork>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>15</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-15T17:00:00</Finish>
        <Duration>PT24H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT28H48M0S</Work>
        <Cost>393600</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>19</UID>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-15T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT28H48M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>19</UID>
        <Start>2027-02-11T08:00:00</Start>
        <Finish>2027-02-15T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>393600</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>20</UID>
      <ID>20</ID>
      <Name>Shutdown starts</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.4</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-29T08:00:00</Start>
      <Finish>2027-03-29T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-03-29T08:00:00</ConstraintDate>
      <PredecessorLink>
        <PredecessorUID>12</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>17</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>18</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>19</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>6</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-03-29T08:00:00</Start>
        <Finish>2027-03-29T08:00:00</Finish>
        <Duration>PT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
      </Baseline>
    </Task>
    <Task>
      <UID>21</UID>
      <ID>21</ID>
      <Name>Shutdown window</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-29T08:00:00</Start>
      <Finish>2027-04-23T17:00:00</Finish>
      <Duration>PT160H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <Cost>5485600</Cost>
      <ActualCost>0</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-03-29T08:00:00</Start>
        <Finish>2027-04-23T17:00:00</Finish>
        <Duration>PT160H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT824H0M0S</Work>
        <Cost>5485600</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>21</UID>
        <Start>2027-03-29T08:00:00</Start>
        <Finish>2027-03-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>21</UID>
        <Start>2027-03-30T08:00:00</Start>
        <Finish>2027-03-31T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>21</UID>
        <Start>2027-03-31T08:00:00</Start>
        <Finish>2027-04-01T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>21</UID>
        <Start>2027-04-01T08:00:00</Start>
        <Finish>2027-04-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT72H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>21</UID>
        <Start>2027-04-02T08:00:00</Start>
        <Finish>2027-04-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT72H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>21</UID>
        <Start>2027-04-05T08:00:00</Start>
        <Finish>2027-04-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT112H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>21</UID>
        <Start>2027-04-06T08:00:00</Start>
        <Finish>2027-04-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT120H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>21</UID>
        <Start>2027-04-07T08:00:00</Start>
        <Finish>2027-04-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT88H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>21</UID>
        <Start>2027-04-08T08:00:00</Start>
        <Finish>2027-04-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT64H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>21</UID>
        <Start>2027-04-09T08:00:00</Start>
        <Finish>2027-04-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT64H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>21</UID>
        <Start>2027-04-12T08:00:00</Start>
        <Finish>2027-04-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>21</UID>
        <Start>2027-04-13T08:00:00</Start>
        <Finish>2027-04-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>21</UID>
        <Start>2027-04-14T08:00:00</Start>
        <Finish>2027-04-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>21</UID>
        <Start>2027-04-15T08:00:00</Start>
        <Finish>2027-04-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>21</UID>
        <Start>2027-04-16T08:00:00</Start>
        <Finish>2027-04-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>21</UID>
        <Start>2027-04-19T08:00:00</Start>
        <Finish>2027-04-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>21</UID>
        <Start>2027-04-20T08:00:00</Start>
        <Finish>2027-04-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>21</UID>
        <Start>2027-04-21T08:00:00</Start>
        <Finish>2027-04-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>21</UID>
        <Start>2027-04-22T08:00:00</Start>
        <Finish>2027-04-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>21</UID>
        <Start>2027-04-23T08:00:00</Start>
        <Finish>2027-04-23T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>21</UID>
        <Start>2027-03-29T08:00:00</Start>
        <Finish>2027-03-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>21</UID>
        <Start>2027-03-30T08:00:00</Start>
        <Finish>2027-03-31T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>142400</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>21</UID>
        <Start>2027-03-31T08:00:00</Start>
        <Finish>2027-04-01T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>142400</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>21</UID>
        <Start>2027-04-01T08:00:00</Start>
        <Finish>2027-04-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>436800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>21</UID>
        <Start>2027-04-02T08:00:00</Start>
        <Finish>2027-04-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>436800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>21</UID>
        <Start>2027-04-05T08:00:00</Start>
        <Finish>2027-04-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>724800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>21</UID>
        <Start>2027-04-06T08:00:00</Start>
        <Finish>2027-04-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>774400</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>21</UID>
        <Start>2027-04-07T08:00:00</Start>
        <Finish>2027-04-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>600800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>21</UID>
        <Start>2027-04-08T08:00:00</Start>
        <Finish>2027-04-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>452000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>21</UID>
        <Start>2027-04-09T08:00:00</Start>
        <Finish>2027-04-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>452000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>21</UID>
        <Start>2027-04-12T08:00:00</Start>
        <Finish>2027-04-13T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>92800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>21</UID>
        <Start>2027-04-13T08:00:00</Start>
        <Finish>2027-04-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>139200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>21</UID>
        <Start>2027-04-14T08:00:00</Start>
        <Finish>2027-04-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>139200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>21</UID>
        <Start>2027-04-15T08:00:00</Start>
        <Finish>2027-04-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>139200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>21</UID>
        <Start>2027-04-16T08:00:00</Start>
        <Finish>2027-04-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>118400</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>21</UID>
        <Start>2027-04-19T08:00:00</Start>
        <Finish>2027-04-20T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>105600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>21</UID>
        <Start>2027-04-20T08:00:00</Start>
        <Finish>2027-04-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>145600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>21</UID>
        <Start>2027-04-21T08:00:00</Start>
        <Finish>2027-04-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>145600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>21</UID>
        <Start>2027-04-22T08:00:00</Start>
        <Finish>2027-04-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>145600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>21</UID>
        <Start>2027-04-23T08:00:00</Start>
        <Finish>2027-04-23T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>96000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>22</UID>
      <ID>22</ID>
      <Name>Shut down and isolate</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-29T08:00:00</Start>
      <Finish>2027-04-06T17:00:00</Finish>
      <Duration>PT56H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <Cost>824000</Cost>
      <ActualCost>0</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-03-29T08:00:00</Start>
        <Finish>2027-04-06T17:00:00</Finish>
        <Duration>PT56H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT136H0M0S</Work>
        <Cost>824000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>22</UID>
        <Start>2027-03-29T08:00:00</Start>
        <Finish>2027-03-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>22</UID>
        <Start>2027-03-30T08:00:00</Start>
        <Finish>2027-03-31T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>22</UID>
        <Start>2027-03-31T08:00:00</Start>
        <Finish>2027-04-01T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>22</UID>
        <Start>2027-04-01T08:00:00</Start>
        <Finish>2027-04-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>22</UID>
        <Start>2027-04-02T08:00:00</Start>
        <Finish>2027-04-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>22</UID>
        <Start>2027-04-05T08:00:00</Start>
        <Finish>2027-04-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>22</UID>
        <Start>2027-04-06T08:00:00</Start>
        <Finish>2027-04-06T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>22</UID>
        <Start>2027-03-29T08:00:00</Start>
        <Finish>2027-03-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>22</UID>
        <Start>2027-03-30T08:00:00</Start>
        <Finish>2027-03-31T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>142400</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>22</UID>
        <Start>2027-03-31T08:00:00</Start>
        <Finish>2027-04-01T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>142400</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>22</UID>
        <Start>2027-04-01T08:00:00</Start>
        <Finish>2027-04-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>148800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>22</UID>
        <Start>2027-04-02T08:00:00</Start>
        <Finish>2027-04-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>148800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>22</UID>
        <Start>2027-04-05T08:00:00</Start>
        <Finish>2027-04-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>92800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>22</UID>
        <Start>2027-04-06T08:00:00</Start>
        <Finish>2027-04-06T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>92800</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>23</UID>
      <ID>23</ID>
      <Name>Permit to work briefing</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.1.1</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-29T08:00:00</Start>
      <Finish>2027-03-29T17:00:00</Finish>
      <Duration>PT8H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT8H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>56000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT8H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>20</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <ExtendedAttribute>
        <FieldID>188743783</FieldID>
        <Value>PT8H0M0S</Value>
      </ExtendedAttribute>
      <ExtendedAttribute>
        <FieldID>188743785</FieldID>
        <Value>PT12H0M0S</Value>
      </ExtendedAttribute>
      <Baseline>
        <Number>0</Number>
        <Start>2027-03-29T08:00:00</Start>
        <Finish>2027-03-29T17:00:00</Finish>
        <Duration>PT8H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT8H0M0S</Work>
        <Cost>56000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>23</UID>
        <Start>2027-03-29T08:00:00</Start>
        <Finish>2027-03-29T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>23</UID>
        <Start>2027-03-29T08:00:00</Start>
        <Finish>2027-03-29T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>56000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>24</UID>
      <ID>24</ID>
      <Name>Controlled shutdown and depressurise</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.1.2</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-30T08:00:00</Start>
      <Finish>2027-03-31T17:00:00</Finish>
      <Duration>PT16H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT48H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>284800</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT48H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>23</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <ExtendedAttribute>
        <FieldID>188743783</FieldID>
        <Value>PT12H0M0S</Value>
      </ExtendedAttribute>
      <ExtendedAttribute>
        <FieldID>188743785</FieldID>
        <Value>PT24H0M0S</Value>
      </ExtendedAttribute>
      <Baseline>
        <Number>0</Number>
        <Start>2027-03-30T08:00:00</Start>
        <Finish>2027-03-31T17:00:00</Finish>
        <Duration>PT16H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT48H0M0S</Work>
        <Cost>284800</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>24</UID>
        <Start>2027-03-30T08:00:00</Start>
        <Finish>2027-03-31T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT48H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>24</UID>
        <Start>2027-03-30T08:00:00</Start>
        <Finish>2027-03-31T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>284800</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>25</UID>
      <ID>25</ID>
      <Name>Isolate and purge</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.1.3</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-01T08:00:00</Start>
      <Finish>2027-04-02T17:00:00</Finish>
      <Duration>PT16H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT48H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>297600</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT48H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>24</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <ExtendedAttribute>
        <FieldID>188743783</FieldID>
        <Value>PT12H0M0S</Value>
      </ExtendedAttribute>
      <ExtendedAttribute>
        <FieldID>188743785</FieldID>
        <Value>PT24H0M0S</Value>
      </ExtendedAttribute>
      <Baseline>
        <Number>0</Number>
        <Start>2027-04-01T08:00:00</Start>
        <Finish>2027-04-02T17:00:00</Finish>
        <Duration>PT16H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT48H0M0S</Work>
        <Cost>297600</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>25</UID>
        <Start>2027-04-01T08:00:00</Start>
        <Finish>2027-04-02T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT48H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>25</UID>
        <Start>2027-04-01T08:00:00</Start>
        <Finish>2027-04-02T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>297600</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>26</UID>
      <ID>26</ID>
      <Name>Fit blinds and break lines</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.1.4</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-05T08:00:00</Start>
      <Finish>2027-04-06T17:00:00</Finish>
      <Duration>PT16H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT32H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>4800</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>185600</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT32H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>25</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-04-05T08:00:00</Start>
        <Finish>2027-04-06T17:00:00</Finish>
        <Duration>PT16H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT32H0M0S</Work>
        <Cost>185600</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>26</UID>
        <Start>2027-04-05T08:00:00</Start>
        <Finish>2027-04-06T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>26</UID>
        <Start>2027-04-05T08:00:00</Start>
        <Finish>2027-04-06T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>185600</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>27</UID>
      <ID>27</ID>
      <Name>Mechanical</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-01T08:00:00</Start>
      <Finish>2027-04-12T17:00:00</Finish>
      <Duration>PT64H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <Cost>2508000</Cost>
      <ActualCost>0</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-04-01T08:00:00</Start>
        <Finish>2027-04-12T17:00:00</Finish>
        <Duration>PT64H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT368H0M0S</Work>
        <Cost>2508000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-04-01T08:00:00</Start>
        <Finish>2027-04-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-04-02T08:00:00</Start>
        <Finish>2027-04-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-04-05T08:00:00</Start>
        <Finish>2027-04-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT64H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-04-06T08:00:00</Start>
        <Finish>2027-04-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT64H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-04-07T08:00:00</Start>
        <Finish>2027-04-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT64H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-04-08T08:00:00</Start>
        <Finish>2027-04-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT64H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-04-09T08:00:00</Start>
        <Finish>2027-04-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT64H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>27</UID>
        <Start>2027-04-12T08:00:00</Start>
        <Finish>2027-04-12T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-04-01T08:00:00</Start>
        <Finish>2027-04-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>92800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-04-02T08:00:00</Start>
        <Finish>2027-04-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>92800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-04-05T08:00:00</Start>
        <Finish>2027-04-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>436800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-04-06T08:00:00</Start>
        <Finish>2027-04-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>436800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-04-07T08:00:00</Start>
        <Finish>2027-04-08T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>452000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-04-08T08:00:00</Start>
        <Finish>2027-04-09T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>452000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-04-09T08:00:00</Start>
        <Finish>2027-04-10T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>452000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>27</UID>
        <Start>2027-04-12T08:00:00</Start>
        <Finish>2027-04-12T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>92800</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>28</UID>
      <ID>28</ID>
      <Name>Replace the heat exchanger bundle</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.2.1</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-05T08:00:00</Start>
      <Finish>2027-04-09T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT160H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>4800</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>1256000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT160H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>25</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-04-05T08:00:00</Start>
        <Finish>2027-04-09T17:00:00</Finish>
        <Duration>PT40H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT160H0M0S</Work>
        <Cost>1256000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>28</UID>
        <Start>2027-04-05T08:00:00</Start>
        <Finish>2027-04-09T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT160H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>28</UID>
        <Start>2027-04-05T08:00:00</Start>
        <Finish>2027-04-09T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>1256000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>29</UID>
      <ID>29</ID>
      <Name>Compressor overhaul</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.2.2</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-05T08:00:00</Start>
      <Finish>2027-04-12T17:00:00</Finish>
      <Duration>PT48H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT96H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>556800</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT96H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>25</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <ExtendedAttribute>
        <FieldID>188743783</FieldID>
        <Value>PT40H0M0S</Value>
      </ExtendedAttribute>
      <ExtendedAttribute>
        <FieldID>188743785</FieldID>
        <Value>PT76H0M0S</Value>
      </ExtendedAttribute>
      <Baseline>
        <Number>0</Number>
        <Start>2027-04-05T08:00:00</Start>
        <Finish>2027-04-12T17:00:00</Finish>
        <Duration>PT48H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT96H0M0S</Work>
        <Cost>556800</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>29</UID>
        <Start>2027-04-05T08:00:00</Start>
        <Finish>2027-04-12T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT96H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>29</UID>
        <Start>2027-04-05T08:00:00</Start>
        <Finish>2027-04-12T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>556800</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>30</UID>
      <ID>30</ID>
      <Name>Valve replacement</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.2.3</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-01T08:00:00</Start>
      <Finish>2027-04-06T17:00:00</Finish>
      <Duration>PT32H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT64H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>19200</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>371200</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT64H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>25</PredecessorUID>
        <Type>3</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-04-01T08:00:00</Start>
        <Finish>2027-04-06T17:00:00</Finish>
        <Duration>PT32H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT64H0M0S</Work>
        <Cost>371200</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>30</UID>
        <Start>2027-04-01T08:00:00</Start>
        <Finish>2027-04-06T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT64H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>30</UID>
        <Start>2027-04-01T08:00:00</Start>
        <Finish>2027-04-06T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>371200</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>31</UID>
      <ID>31</ID>
      <Name>Vessel internal inspection</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.2.4</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-07T08:00:00</Start>
      <Finish>2027-04-09T17:00:00</Finish>
      <Duration>PT24H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT48H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>4800</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>324000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT48H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>26</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-04-07T08:00:00</Start>
        <Finish>2027-04-09T17:00:00</Finish>
        <Duration>PT24H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT48H0M0S</Work>
        <Cost>324000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>31</UID>
        <Start>2027-04-07T08:00:00</Start>
        <Finish>2027-04-09T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT48H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>31</UID>
        <Start>2027-04-07T08:00:00</Start>
        <Finish>2027-04-09T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>324000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>32</UID>
      <ID>32</ID>
      <Name>Electrical and instruments</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-01T08:00:00</Start>
      <Finish>2027-04-07T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>33600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <Cost>979200</Cost>
      <ActualCost>0</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-04-01T08:00:00</Start>
        <Finish>2027-04-07T17:00:00</Finish>
        <Duration>PT40H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT160H0M0S</Work>
        <Cost>979200</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>32</UID>
        <Start>2027-04-01T08:00:00</Start>
        <Finish>2027-04-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>32</UID>
        <Start>2027-04-02T08:00:00</Start>
        <Finish>2027-04-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>32</UID>
        <Start>2027-04-05T08:00:00</Start>
        <Finish>2027-04-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>32</UID>
        <Start>2027-04-06T08:00:00</Start>
        <Finish>2027-04-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT40H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>32</UID>
        <Start>2027-04-07T08:00:00</Start>
        <Finish>2027-04-07T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>32</UID>
        <Start>2027-04-01T08:00:00</Start>
        <Finish>2027-04-02T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>195200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>32</UID>
        <Start>2027-04-02T08:00:00</Start>
        <Finish>2027-04-03T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>195200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>32</UID>
        <Start>2027-04-05T08:00:00</Start>
        <Finish>2027-04-06T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>195200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>32</UID>
        <Start>2027-04-06T08:00:00</Start>
        <Finish>2027-04-07T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>244800</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>32</UID>
        <Start>2027-04-07T08:00:00</Start>
        <Finish>2027-04-07T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>148800</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>33</UID>
      <ID>33</ID>
      <Name>Motor and switchgear maintenance</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.3.1</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-01T08:00:00</Start>
      <Finish>2027-04-06T17:00:00</Finish>
      <Duration>PT32H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT64H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>38400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>384000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT64H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>25</PredecessorUID>
        <Type>3</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-04-01T08:00:00</Start>
        <Finish>2027-04-06T17:00:00</Finish>
        <Duration>PT32H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT64H0M0S</Work>
        <Cost>384000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>33</UID>
        <Start>2027-04-01T08:00:00</Start>
        <Finish>2027-04-06T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT64H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>33</UID>
        <Start>2027-04-01T08:00:00</Start>
        <Finish>2027-04-06T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>384000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>34</UID>
      <ID>34</ID>
      <Name>Instrument calibration</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.3.2</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-01T08:00:00</Start>
      <Finish>2027-04-07T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT80H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>33600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>496000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT80H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>25</PredecessorUID>
        <Type>3</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-04-01T08:00:00</Start>
        <Finish>2027-04-07T17:00:00</Finish>
        <Duration>PT40H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT80H0M0S</Work>
        <Cost>496000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>34</UID>
        <Start>2027-04-01T08:00:00</Start>
        <Finish>2027-04-07T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT80H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>34</UID>
        <Start>2027-04-01T08:00:00</Start>
        <Finish>2027-04-07T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>496000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>35</UID>
      <ID>35</ID>
      <Name>Trip and alarm testing</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.3.3</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-06T08:00:00</Start>
      <Finish>2027-04-07T17:00:00</Finish>
      <Duration>PT16H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT16H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>33600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>99200</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT16H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>34</PredecessorUID>
        <Type>0</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-04-06T08:00:00</Start>
        <Finish>2027-04-07T17:00:00</Finish>
        <Duration>PT16H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT16H0M0S</Work>
        <Cost>99200</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>35</UID>
        <Start>2027-04-06T08:00:00</Start>
        <Finish>2027-04-07T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>35</UID>
        <Start>2027-04-06T08:00:00</Start>
        <Finish>2027-04-07T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>99200</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>36</UID>
      <ID>36</ID>
      <Name>Box-up</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.4</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-13T08:00:00</Start>
      <Finish>2027-04-19T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <Cost>641600</Cost>
      <ActualCost>0</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-04-13T08:00:00</Start>
        <Finish>2027-04-19T17:00:00</Finish>
        <Duration>PT40H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT104H0M0S</Work>
        <Cost>641600</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>36</UID>
        <Start>2027-04-13T08:00:00</Start>
        <Finish>2027-04-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>36</UID>
        <Start>2027-04-14T08:00:00</Start>
        <Finish>2027-04-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>36</UID>
        <Start>2027-04-15T08:00:00</Start>
        <Finish>2027-04-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT24H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>36</UID>
        <Start>2027-04-16T08:00:00</Start>
        <Finish>2027-04-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>36</UID>
        <Start>2027-04-19T08:00:00</Start>
        <Finish>2027-04-19T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>36</UID>
        <Start>2027-04-13T08:00:00</Start>
        <Finish>2027-04-14T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>139200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>36</UID>
        <Start>2027-04-14T08:00:00</Start>
        <Finish>2027-04-15T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>139200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>36</UID>
        <Start>2027-04-15T08:00:00</Start>
        <Finish>2027-04-16T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>139200</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>36</UID>
        <Start>2027-04-16T08:00:00</Start>
        <Finish>2027-04-17T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>118400</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>36</UID>
        <Start>2027-04-19T08:00:00</Start>
        <Finish>2027-04-19T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>105600</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>37</UID>
      <ID>37</ID>
      <Name>Box-up and reinstate</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.4.1</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-13T08:00:00</Start>
      <Finish>2027-04-15T17:00:00</Finish>
      <Duration>PT24H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT72H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>417600</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT72H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>28</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>29</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>30</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>31</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <ExtendedAttribute>
        <FieldID>188743783</FieldID>
        <Value>PT20H0M0S</Value>
      </ExtendedAttribute>
      <ExtendedAttribute>
        <FieldID>188743785</FieldID>
        <Value>PT40H0M0S</Value>
      </ExtendedAttribute>
      <Baseline>
        <Number>0</Number>
        <Start>2027-04-13T08:00:00</Start>
        <Finish>2027-04-15T17:00:00</Finish>
        <Duration>PT24H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT72H0M0S</Work>
        <Cost>417600</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>37</UID>
        <Start>2027-04-13T08:00:00</Start>
        <Finish>2027-04-15T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT72H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>37</UID>
        <Start>2027-04-13T08:00:00</Start>
        <Finish>2027-04-15T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>417600</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>38</UID>
      <ID>38</ID>
      <Name>Leak test</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.4.2</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-16T08:00:00</Start>
      <Finish>2027-04-16T17:00:00</Finish>
      <Duration>PT8H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT16H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>118400</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT16H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>37</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <ExtendedAttribute>
        <FieldID>188743783</FieldID>
        <Value>PT8H0M0S</Value>
      </ExtendedAttribute>
      <ExtendedAttribute>
        <FieldID>188743785</FieldID>
        <Value>PT12H0M0S</Value>
      </ExtendedAttribute>
      <Baseline>
        <Number>0</Number>
        <Start>2027-04-16T08:00:00</Start>
        <Finish>2027-04-16T17:00:00</Finish>
        <Duration>PT8H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT16H0M0S</Work>
        <Cost>118400</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>38</UID>
        <Start>2027-04-16T08:00:00</Start>
        <Finish>2027-04-16T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>38</UID>
        <Start>2027-04-16T08:00:00</Start>
        <Finish>2027-04-16T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>118400</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>39</UID>
      <ID>39</ID>
      <Name>Remove isolations</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.4.3</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-19T08:00:00</Start>
      <Finish>2027-04-19T17:00:00</Finish>
      <Duration>PT8H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT16H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>105600</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT16H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>38</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>35</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>33</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <ExtendedAttribute>
        <FieldID>188743783</FieldID>
        <Value>PT8H0M0S</Value>
      </ExtendedAttribute>
      <ExtendedAttribute>
        <FieldID>188743785</FieldID>
        <Value>PT12H0M0S</Value>
      </ExtendedAttribute>
      <Baseline>
        <Number>0</Number>
        <Start>2027-04-19T08:00:00</Start>
        <Finish>2027-04-19T17:00:00</Finish>
        <Duration>PT8H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT16H0M0S</Work>
        <Cost>105600</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>39</UID>
        <Start>2027-04-19T08:00:00</Start>
        <Finish>2027-04-19T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>39</UID>
        <Start>2027-04-19T08:00:00</Start>
        <Finish>2027-04-19T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>105600</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>40</UID>
      <ID>40</ID>
      <Name>Restart</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.5</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-20T08:00:00</Start>
      <Finish>2027-04-23T17:00:00</Finish>
      <Duration>PT32H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <Cost>532800</Cost>
      <ActualCost>0</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-04-20T08:00:00</Start>
        <Finish>2027-04-23T17:00:00</Finish>
        <Duration>PT32H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT56H0M0S</Work>
        <Cost>532800</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>40</UID>
        <Start>2027-04-20T08:00:00</Start>
        <Finish>2027-04-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>40</UID>
        <Start>2027-04-21T08:00:00</Start>
        <Finish>2027-04-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>40</UID>
        <Start>2027-04-22T08:00:00</Start>
        <Finish>2027-04-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT16H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>40</UID>
        <Start>2027-04-23T08:00:00</Start>
        <Finish>2027-04-23T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>40</UID>
        <Start>2027-04-20T08:00:00</Start>
        <Finish>2027-04-21T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>145600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>40</UID>
        <Start>2027-04-21T08:00:00</Start>
        <Finish>2027-04-22T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>145600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>40</UID>
        <Start>2027-04-22T08:00:00</Start>
        <Finish>2027-04-23T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>145600</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>40</UID>
        <Start>2027-04-23T08:00:00</Start>
        <Finish>2027-04-23T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>96000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>41</UID>
      <ID>41</ID>
      <Name>Start-up and commissioning</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.5.1</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-20T08:00:00</Start>
      <Finish>2027-04-22T17:00:00</Finish>
      <Duration>PT24H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT48H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>436800</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT48H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>39</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <ExtendedAttribute>
        <FieldID>188743783</FieldID>
        <Value>PT20H0M0S</Value>
      </ExtendedAttribute>
      <ExtendedAttribute>
        <FieldID>188743785</FieldID>
        <Value>PT40H0M0S</Value>
      </ExtendedAttribute>
      <Baseline>
        <Number>0</Number>
        <Start>2027-04-20T08:00:00</Start>
        <Finish>2027-04-22T17:00:00</Finish>
        <Duration>PT24H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT48H0M0S</Work>
        <Cost>436800</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>41</UID>
        <Start>2027-04-20T08:00:00</Start>
        <Finish>2027-04-22T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT48H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>41</UID>
        <Start>2027-04-20T08:00:00</Start>
        <Finish>2027-04-22T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>436800</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>42</UID>
      <ID>42</ID>
      <Name>Hand back to operations</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.5.2</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-23T08:00:00</Start>
      <Finish>2027-04-23T17:00:00</Finish>
      <Duration>PT8H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT8H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>96000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT8H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>41</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <ExtendedAttribute>
        <FieldID>188743783</FieldID>
        <Value>PT8H0M0S</Value>
      </ExtendedAttribute>
      <ExtendedAttribute>
        <FieldID>188743785</FieldID>
        <Value>PT12H0M0S</Value>
      </ExtendedAttribute>
      <Baseline>
        <Number>0</Number>
        <Start>2027-04-23T08:00:00</Start>
        <Finish>2027-04-23T17:00:00</Finish>
        <Duration>PT8H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT8H0M0S</Work>
        <Cost>96000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>42</UID>
        <Start>2027-04-23T08:00:00</Start>
        <Finish>2027-04-23T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT8H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>42</UID>
        <Start>2027-04-23T08:00:00</Start>
        <Finish>2027-04-23T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>96000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>43</UID>
      <ID>43</ID>
      <Name>Plant back online</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.5.3</OutlineNumber>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-23T17:00:00</Start>
      <Finish>2027-04-23T17:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
      <Deadline>2027-04-30T17:00:00</Deadline>
      <PredecessorLink>
        <PredecessorUID>42</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-04-23T17:00:00</Start>
        <Finish>2027-04-23T17:00:00</Finish>
        <Duration>PT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
      </Baseline>
    </Task>
    <Task>
      <UID>44</UID>
      <ID>44</ID>
      <Name>Post-shutdown</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-27T08:00:00</Start>
      <Finish>2027-05-03T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <Cost>1344000</Cost>
      <ActualCost>0</ActualCost>
      <ConstraintType>0</ConstraintType>
      <Baseline>
        <Number>0</Number>
        <Start>2027-04-27T08:00:00</Start>
        <Finish>2027-05-03T17:00:00</Finish>
        <Duration>PT40H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT224H0M0S</Work>
        <Cost>1344000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>44</UID>
        <Start>2027-04-27T08:00:00</Start>
        <Finish>2027-04-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT32H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>44</UID>
        <Start>2027-04-28T08:00:00</Start>
        <Finish>2027-04-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT48H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>44</UID>
        <Start>2027-04-29T08:00:00</Start>
        <Finish>2027-04-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT48H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>44</UID>
        <Start>2027-04-30T08:00:00</Start>
        <Finish>2027-05-01T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT48H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>9</Type>
        <UID>44</UID>
        <Start>2027-05-03T08:00:00</Start>
        <Finish>2027-05-03T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT48H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>44</UID>
        <Start>2027-04-27T08:00:00</Start>
        <Finish>2027-04-28T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>144000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>44</UID>
        <Start>2027-04-28T08:00:00</Start>
        <Finish>2027-04-29T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>300000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>44</UID>
        <Start>2027-04-29T08:00:00</Start>
        <Finish>2027-04-30T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>300000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>44</UID>
        <Start>2027-04-30T08:00:00</Start>
        <Finish>2027-05-01T08:00:00</Finish>
        <Unit>1</Unit>
        <Value>300000</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>44</UID>
        <Start>2027-05-03T08:00:00</Start>
        <Finish>2027-05-03T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>300000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>45</UID>
      <ID>45</ID>
      <Name>Strike scaffolding and demobilise</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-27T08:00:00</Start>
      <Finish>2027-05-03T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT160H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>720000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT160H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>43</PredecessorUID>
        <Type>3</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>4800</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <ExtendedAttribute>
        <FieldID>188743783</FieldID>
        <Value>PT32H0M0S</Value>
      </ExtendedAttribute>
      <ExtendedAttribute>
        <FieldID>188743785</FieldID>
        <Value>PT64H0M0S</Value>
      </ExtendedAttribute>
      <Baseline>
        <Number>0</Number>
        <Start>2027-04-27T08:00:00</Start>
        <Finish>2027-05-03T17:00:00</Finish>
        <Duration>PT40H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT160H0M0S</Work>
        <Cost>720000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>45</UID>
        <Start>2027-04-27T08:00:00</Start>
        <Finish>2027-05-03T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT160H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>45</UID>
        <Start>2027-04-27T08:00:00</Start>
        <Finish>2027-05-03T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>720000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>46</UID>
      <ID>46</ID>
      <Name>Turnaround close-out report</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-28T08:00:00</Start>
      <Finish>2027-05-03T17:00:00</Finish>
      <Duration>PT32H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT64H0M0S</Work>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <PercentWorkComplete>0</PercentWorkComplete>
      <Cost>624000</Cost>
      <ActualCost>0</ActualCost>
      <ActualWork>PT0H0M0S</ActualWork>
      <RemainingWork>PT64H0M0S</RemainingWork>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>45</PredecessorUID>
        <Type>0</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>43</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <ExtendedAttribute>
        <FieldID>188743783</FieldID>
        <Value>PT24H0M0S</Value>
      </ExtendedAttribute>
      <ExtendedAttribute>
        <FieldID>188743785</FieldID>
        <Value>PT52H0M0S</Value>
      </ExtendedAttribute>
      <Baseline>
        <Number>0</Number>
        <Start>2027-04-28T08:00:00</Start>
        <Finish>2027-05-03T17:00:00</Finish>
        <Duration>PT32H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <Work>PT64H0M0S</Work>
        <Cost>624000</Cost>
      </Baseline>
      <TimephasedData>
        <Type>9</Type>
        <UID>46</UID>
        <Start>2027-04-28T08:00:00</Start>
        <Finish>2027-05-03T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>PT64H0M0S</Value>
      </TimephasedData>
      <TimephasedData>
        <Type>10</Type>
        <UID>46</UID>
        <Start>2027-04-28T08:00:00</Start>
        <Finish>2027-05-03T17:00:00</Finish>
        <Unit>1</Unit>
        <Value>624000</Value>
      </TimephasedData>
    </Task>
    <Task>
      <UID>47</UID>
      <ID>47</ID>
      <Name>Turnaround closed</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-05-03T17:00:00</Start>
      <Finish>2027-05-03T17:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
      <PredecessorLink>
        <PredecessorUID>46</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <Baseline>
        <Number>0</Number>
        <Start>2027-05-03T17:00:00</Start>
        <Finish>2027-05-03T17:00:00</Finish>
        <Duration>PT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
      </Baseline>
    </Task>
  </Tasks>
  <Resources>
    <Resource>
      <UID>1</UID>
      <ID>1</ID>
      <Name>Turnaround manager</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <Initials>TM</Initials>
      <Group>Management</Group>
      <MaxUnits>1</MaxUnits>
      <StandardRate>120</StandardRate>
    </Resource>
    <Resource>
      <UID>2</UID>
      <ID>2</ID>
      <Name>Maintenance planner</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <Initials>MP</Initials>
      <Group>Management</Group>
      <MaxUnits>1</MaxUnits>
      <StandardRate>75</StandardRate>
    </Resource>
    <Resource>
      <UID>3</UID>
      <ID>3</ID>
      <Name>Procurement</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <Initials>PR</Initials>
      <Group>Supply</Group>
      <MaxUnits>1</MaxUnits>
      <StandardRate>60</StandardRate>
    </Resource>
    <Resource>
      <UID>4</UID>
      <ID>4</ID>
      <Name>Safety advisor</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <Initials>SA</Initials>
      <Group>Safety</Group>
      <MaxUnits>1</MaxUnits>
      <StandardRate>70</StandardRate>
    </Resource>
    <Resource>
      <UID>5</UID>
      <ID>5</ID>
      <Name>Mechanical fitters</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <Initials>MF</Initials>
      <Group>Trades</Group>
      <MaxUnits>6</MaxUnits>
      <StandardRate>58</StandardRate>
    </Resource>
    <Resource>
      <UID>6</UID>
      <ID>6</ID>
      <Name>Electricians</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <Initials>EL</Initials>
      <Group>Trades</Group>
      <MaxUnits>3</MaxUnits>
      <StandardRate>60</StandardRate>
    </Resource>
    <Resource>
      <UID>7</UID>
      <ID>7</ID>
      <Name>Instrument technicians</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <Initials>IT</Initials>
      <Group>Trades</Group>
      <MaxUnits>3</MaxUnits>
      <StandardRate>62</StandardRate>
    </Resource>
    <Resource>
      <UID>8</UID>
      <ID>8</ID>
      <Name>Scaffolders</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <Initials>SC</Initials>
      <Group>Contractors</Group>
      <MaxUnits>4</MaxUnits>
      <StandardRate>45</StandardRate>
    </Resource>
    <Resource>
      <UID>9</UID>
      <ID>9</ID>
      <Name>Inspection engineer</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <Initials>IE</Initials>
      <Group>Engineering</Group>
      <MaxUnits>1</MaxUnits>
      <StandardRate>90</StandardRate>
    </Resource>
    <Resource>
      <UID>10</UID>
      <ID>10</ID>
      <Name>Mobile crane</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <Initials>MC</Initials>
      <Group>Plant</Group>
      <MaxUnits>1</MaxUnits>
      <StandardRate>140</StandardRate>
    </Resource>
  </Resources>
  <Assignments>
    <Assignment>
      <UID>1</UID>
      <TaskUID>4</TaskUID>
      <ResourceUID>2</ResourceUID>
      <PercentWorkComplete>100</PercentWorkComplete>
      <ActualFinish>2027-01-22T17:00:00</ActualFinish>
      <ActualStart>2027-01-04T08:00:00</ActualStart>
      <ActualWork>PT120H0M0S</ActualWork>
      <Finish>2027-01-22T17:00:00</Finish>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <Start>2027-01-04T08:00:00</Start>
      <Units>1</Units>
      <Work>PT120H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>2</UID>
      <TaskUID>5</TaskUID>
      <ResourceUID>4</ResourceUID>
      <PercentWorkComplete>100</PercentWorkComplete>
      <ActualFinish>2027-02-03T17:00:00</ActualFinish>
      <ActualStart>2027-01-25T08:00:00</ActualStart>
      <ActualWork>PT64H0M0S</ActualWork>
      <Finish>2027-02-03T17:00:00</Finish>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <Start>2027-01-25T08:00:00</Start>
      <Units>1</Units>
      <Work>PT64H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>3</UID>
      <TaskUID>6</TaskUID>
      <ResourceUID>2</ResourceUID>
      <PercentWorkComplete>100</PercentWorkComplete>
      <ActualFinish>2027-01-29T17:00:00</ActualFinish>
      <ActualStart>2027-01-25T08:00:00</ActualStart>
      <ActualWork>PT40H0M0S</ActualWork>
      <Finish>2027-01-29T17:00:00</Finish>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <Start>2027-01-25T08:00:00</Start>
      <Units>1</Units>
      <Work>PT40H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>4</UID>
      <TaskUID>6</TaskUID>
      <ResourceUID>7</ResourceUID>
      <PercentWorkComplete>100</PercentWorkComplete>
      <ActualFinish>2027-01-29T17:00:00</ActualFinish>
      <ActualStart>2027-01-25T08:00:00</ActualStart>
      <ActualWork>PT20H0M0S</ActualWork>
      <Finish>2027-01-29T17:00:00</Finish>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <Start>2027-01-25T08:00:00</Start>
      <Units>0.5</Units>
      <Work>PT20H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>5</UID>
      <TaskUID>8</TaskUID>
      <ResourceUID>3</ResourceUID>
      <PercentWorkComplete>61</PercentWorkComplete>
      <ActualStart>2027-01-04T08:00:00</ActualStart>
      <ActualWork>PT56H36M0S</ActualWork>
      <Finish>2027-03-24T17:00:00</Finish>
      <RemainingWork>PT36H12M0S</RemainingWork>
      <Start>2027-01-04T08:00:00</Start>
      <Units>0.2</Units>
      <Work>PT92H48M0S</Work>
    </Assignment>
    <Assignment>
      <UID>6</UID>
      <TaskUID>9</TaskUID>
      <ResourceUID>3</ResourceUID>
      <PercentWorkComplete>70</PercentWorkComplete>
      <ActualStart>2027-01-04T08:00:00</ActualStart>
      <ActualWork>PT56H0M0S</ActualWork>
      <Finish>2027-03-12T17:00:00</Finish>
      <RemainingWork>PT24H0M0S</RemainingWork>
      <Start>2027-01-04T08:00:00</Start>
      <Units>0.2</Units>
      <Work>PT80H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>7</UID>
      <TaskUID>10</TaskUID>
      <ResourceUID>3</ResourceUID>
      <PercentWorkComplete>73</PercentWorkComplete>
      <ActualStart>2027-01-04T08:00:00</ActualStart>
      <ActualWork>PT56H4M0S</ActualWork>
      <Finish>2027-03-10T17:00:00</Finish>
      <RemainingWork>PT20H44M0S</RemainingWork>
      <Start>2027-01-04T08:00:00</Start>
      <Units>0.2</Units>
      <Work>PT76H48M0S</Work>
    </Assignment>
    <Assignment>
      <UID>8</UID>
      <TaskUID>11</TaskUID>
      <ResourceUID>3</ResourceUID>
      <PercentWorkComplete>100</PercentWorkComplete>
      <ActualFinish>2027-02-05T17:00:00</ActualFinish>
      <ActualStart>2027-01-25T08:00:00</ActualStart>
      <ActualWork>PT80H0M0S</ActualWork>
      <Finish>2027-02-05T17:00:00</Finish>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <Start>2027-01-25T08:00:00</Start>
      <Units>1</Units>
      <Work>PT80H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>9</UID>
      <TaskUID>14</TaskUID>
      <ResourceUID>1</ResourceUID>
      <PercentWorkComplete>100</PercentWorkComplete>
      <ActualFinish>2027-02-05T17:00:00</ActualFinish>
      <ActualStart>2027-01-25T08:00:00</ActualStart>
      <ActualWork>PT80H0M0S</ActualWork>
      <Finish>2027-02-05T17:00:00</Finish>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <Start>2027-01-25T08:00:00</Start>
      <Units>1</Units>
      <Work>PT80H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>10</UID>
      <TaskUID>15</TaskUID>
      <ResourceUID>4</ResourceUID>
      <PercentWorkComplete>100</PercentWorkComplete>
      <ActualFinish>2027-02-10T17:00:00</ActualFinish>
      <ActualStart>2027-02-08T08:00:00</ActualStart>
      <ActualWork>PT24H0M0S</ActualWork>
      <Finish>2027-02-10T17:00:00</Finish>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <Start>2027-02-08T08:00:00</Start>
      <Units>1</Units>
      <Work>PT24H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>11</UID>
      <TaskUID>17</TaskUID>
      <ResourceUID>8</ResourceUID>
      <PercentWorkComplete>100</PercentWorkComplete>
      <ActualFinish>2027-02-22T17:00:00</ActualFinish>
      <ActualStart>2027-02-11T08:00:00</ActualStart>
      <ActualWork>PT256H0M0S</ActualWork>
      <Finish>2027-02-22T17:00:00</Finish>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <Start>2027-02-11T08:00:00</Start>
      <Units>4</Units>
      <Work>PT256H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>12</UID>
      <TaskUID>18</TaskUID>
      <ResourceUID>5</ResourceUID>
      <PercentWorkComplete>70</PercentWorkComplete>
      <ActualStart>2027-02-11T08:00:00</ActualStart>
      <ActualWork>PT112H0M0S</ActualWork>
      <Finish>2027-02-24T17:00:00</Finish>
      <RemainingWork>PT48H0M0S</RemainingWork>
      <Start>2027-02-11T08:00:00</Start>
      <Units>2</Units>
      <Work>PT160H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>13</UID>
      <TaskUID>19</TaskUID>
      <ResourceUID>10</ResourceUID>
      <PercentWorkComplete>100</PercentWorkComplete>
      <ActualFinish>2027-02-15T17:00:00</ActualFinish>
      <ActualStart>2027-02-11T08:00:00</ActualStart>
      <ActualWork>PT24H0M0S</ActualWork>
      <Finish>2027-02-15T17:00:00</Finish>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <Start>2027-02-11T08:00:00</Start>
      <Units>1</Units>
      <Work>PT24H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>14</UID>
      <TaskUID>19</TaskUID>
      <ResourceUID>1</ResourceUID>
      <PercentWorkComplete>100</PercentWorkComplete>
      <ActualFinish>2027-02-15T17:00:00</ActualFinish>
      <ActualStart>2027-02-11T08:00:00</ActualStart>
      <ActualWork>PT4H48M0S</ActualWork>
      <Finish>2027-02-15T17:00:00</Finish>
      <RemainingWork>PT0H0M0S</RemainingWork>
      <Start>2027-02-11T08:00:00</Start>
      <Units>0.2</Units>
      <Work>PT4H48M0S</Work>
    </Assignment>
    <Assignment>
      <UID>15</UID>
      <TaskUID>23</TaskUID>
      <ResourceUID>4</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-03-29T17:00:00</Finish>
      <RemainingWork>PT8H0M0S</RemainingWork>
      <Start>2027-03-29T08:00:00</Start>
      <Units>1</Units>
      <Work>PT8H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>16</UID>
      <TaskUID>24</TaskUID>
      <ResourceUID>7</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-03-31T17:00:00</Finish>
      <RemainingWork>PT16H0M0S</RemainingWork>
      <Start>2027-03-30T08:00:00</Start>
      <Units>1</Units>
      <Work>PT16H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>17</UID>
      <TaskUID>24</TaskUID>
      <ResourceUID>5</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-03-31T17:00:00</Finish>
      <RemainingWork>PT32H0M0S</RemainingWork>
      <Start>2027-03-30T08:00:00</Start>
      <Units>2</Units>
      <Work>PT32H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>18</UID>
      <TaskUID>25</TaskUID>
      <ResourceUID>5</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-04-02T17:00:00</Finish>
      <RemainingWork>PT32H0M0S</RemainingWork>
      <Start>2027-04-01T08:00:00</Start>
      <Units>2</Units>
      <Work>PT32H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>19</UID>
      <TaskUID>25</TaskUID>
      <ResourceUID>4</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-04-02T17:00:00</Finish>
      <RemainingWork>PT16H0M0S</RemainingWork>
      <Start>2027-04-01T08:00:00</Start>
      <Units>1</Units>
      <Work>PT16H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>20</UID>
      <TaskUID>26</TaskUID>
      <ResourceUID>5</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-04-06T17:00:00</Finish>
      <RemainingWork>PT32H0M0S</RemainingWork>
      <Start>2027-04-05T08:00:00</Start>
      <Units>2</Units>
      <Work>PT32H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>21</UID>
      <TaskUID>28</TaskUID>
      <ResourceUID>5</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-04-09T17:00:00</Finish>
      <RemainingWork>PT120H0M0S</RemainingWork>
      <Start>2027-04-05T08:00:00</Start>
      <Units>3</Units>
      <Work>PT120H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>22</UID>
      <TaskUID>28</TaskUID>
      <ResourceUID>10</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-04-09T17:00:00</Finish>
      <RemainingWork>PT40H0M0S</RemainingWork>
      <Start>2027-04-05T08:00:00</Start>
      <Units>1</Units>
      <Work>PT40H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>23</UID>
      <TaskUID>29</TaskUID>
      <ResourceUID>5</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-04-12T17:00:00</Finish>
      <RemainingWork>PT96H0M0S</RemainingWork>
      <Start>2027-04-05T08:00:00</Start>
      <Units>2</Units>
      <Work>PT96H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>24</UID>
      <TaskUID>30</TaskUID>
      <ResourceUID>5</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-04-06T17:00:00</Finish>
      <RemainingWork>PT64H0M0S</RemainingWork>
      <Start>2027-04-01T08:00:00</Start>
      <Units>2</Units>
      <Work>PT64H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>25</UID>
      <TaskUID>31</TaskUID>
      <ResourceUID>9</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-04-09T17:00:00</Finish>
      <RemainingWork>PT24H0M0S</RemainingWork>
      <Start>2027-04-07T08:00:00</Start>
      <Units>1</Units>
      <Work>PT24H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>26</UID>
      <TaskUID>31</TaskUID>
      <ResourceUID>8</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-04-09T17:00:00</Finish>
      <RemainingWork>PT24H0M0S</RemainingWork>
      <Start>2027-04-07T08:00:00</Start>
      <Units>1</Units>
      <Work>PT24H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>27</UID>
      <TaskUID>33</TaskUID>
      <ResourceUID>6</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-04-06T17:00:00</Finish>
      <RemainingWork>PT64H0M0S</RemainingWork>
      <Start>2027-04-01T08:00:00</Start>
      <Units>2</Units>
      <Work>PT64H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>28</UID>
      <TaskUID>34</TaskUID>
      <ResourceUID>7</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-04-07T17:00:00</Finish>
      <RemainingWork>PT80H0M0S</RemainingWork>
      <Start>2027-04-01T08:00:00</Start>
      <Units>2</Units>
      <Work>PT80H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>29</UID>
      <TaskUID>35</TaskUID>
      <ResourceUID>7</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-04-07T17:00:00</Finish>
      <RemainingWork>PT16H0M0S</RemainingWork>
      <Start>2027-04-06T08:00:00</Start>
      <Units>1</Units>
      <Work>PT16H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>30</UID>
      <TaskUID>37</TaskUID>
      <ResourceUID>5</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-04-15T17:00:00</Finish>
      <RemainingWork>PT72H0M0S</RemainingWork>
      <Start>2027-04-13T08:00:00</Start>
      <Units>3</Units>
      <Work>PT72H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>31</UID>
      <TaskUID>38</TaskUID>
      <ResourceUID>9</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-04-16T17:00:00</Finish>
      <RemainingWork>PT8H0M0S</RemainingWork>
      <Start>2027-04-16T08:00:00</Start>
      <Units>1</Units>
      <Work>PT8H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>32</UID>
      <TaskUID>38</TaskUID>
      <ResourceUID>5</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-04-16T17:00:00</Finish>
      <RemainingWork>PT8H0M0S</RemainingWork>
      <Start>2027-04-16T08:00:00</Start>
      <Units>1</Units>
      <Work>PT8H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>33</UID>
      <TaskUID>39</TaskUID>
      <ResourceUID>4</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-04-19T17:00:00</Finish>
      <RemainingWork>PT8H0M0S</RemainingWork>
      <Start>2027-04-19T08:00:00</Start>
      <Units>1</Units>
      <Work>PT8H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>34</UID>
      <TaskUID>39</TaskUID>
      <ResourceUID>7</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-04-19T17:00:00</Finish>
      <RemainingWork>PT8H0M0S</RemainingWork>
      <Start>2027-04-19T08:00:00</Start>
      <Units>1</Units>
      <Work>PT8H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>35</UID>
      <TaskUID>41</TaskUID>
      <ResourceUID>7</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-04-22T17:00:00</Finish>
      <RemainingWork>PT24H0M0S</RemainingWork>
      <Start>2027-04-20T08:00:00</Start>
      <Units>1</Units>
      <Work>PT24H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>36</UID>
      <TaskUID>41</TaskUID>
      <ResourceUID>1</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-04-22T17:00:00</Finish>
      <RemainingWork>PT24H0M0S</RemainingWork>
      <Start>2027-04-20T08:00:00</Start>
      <Units>1</Units>
      <Work>PT24H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>37</UID>
      <TaskUID>42</TaskUID>
      <ResourceUID>1</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-04-23T17:00:00</Finish>
      <RemainingWork>PT8H0M0S</RemainingWork>
      <Start>2027-04-23T08:00:00</Start>
      <Units>1</Units>
      <Work>PT8H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>38</UID>
      <TaskUID>45</TaskUID>
      <ResourceUID>8</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-05-03T17:00:00</Finish>
      <RemainingWork>PT160H0M0S</RemainingWork>
      <Start>2027-04-27T08:00:00</Start>
      <Units>4</Units>
      <Work>PT160H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>39</UID>
      <TaskUID>46</TaskUID>
      <ResourceUID>1</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-05-03T17:00:00</Finish>
      <RemainingWork>PT32H0M0S</RemainingWork>
      <Start>2027-04-28T08:00:00</Start>
      <Units>1</Units>
      <Work>PT32H0M0S</Work>
    </Assignment>
    <Assignment>
      <UID>40</UID>
      <TaskUID>46</TaskUID>
      <ResourceUID>2</ResourceUID>
      <PercentWorkComplete>0</PercentWorkComplete>
      <ActualWork>PT0H0M0S</ActualWork>
      <Finish>2027-05-03T17:00:00</Finish>
      <RemainingWork>PT32H0M0S</RemainingWork>
      <Start>2027-04-28T08:00:00</Start>
      <Units>1</Units>
      <Work>PT32H0M0S</Work>
    </Assignment>
  </Assignments>
</Project>