<?xml version="1.0" encoding="UTF-8" standalone="yes"?>
<Project xmlns="http://schemas.microsoft.com/project">
  <SaveVersion>14</SaveVersion>
  <Name>Terminplan HOAI-Leistungsphasen</Name>
  <Title>Terminplan HOAI-Leistungsphasen</Title>
  <ScheduleFromStart>1</ScheduleFromStart>
  <StartDate>2027-01-04T08:00:00</StartDate>
  <FinishDate>2028-08-22T17:00:00</FinishDate>
  <CalendarUID>1</CalendarUID>
  <DefaultStartTime>08:00:00</DefaultStartTime>
  <DefaultFinishTime>17:00:00</DefaultFinishTime>
  <DurationFormat>7</DurationFormat>
  <NewTasksAreManual>0</NewTasksAreManual>
  <ProjectExternallyEdited>0</ProjectExternallyEdited>
  <Calendars>
    <Calendar>
      <UID>1</UID>
      <Name>Standard</Name>
      <IsBaseCalendar>1</IsBaseCalendar>
      <BaseCalendarUID>-1</BaseCalendarUID>
      <WeekDays>
        <WeekDay>
          <DayType>1</DayType>
          <DayWorking>0</DayWorking>
        </WeekDay>
        <WeekDay>
          <DayType>2</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>3</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>4</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>5</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>6</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>7</DayType>
          <DayWorking>0</DayWorking>
        </WeekDay>
      </WeekDays>
    </Calendar>
  </Calendars>
  <Tasks>
    <Task>
      <UID>1</UID>
      <ID>1</ID>
      <Name>LPH 1 Grundlagenermittlung</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-04T08:00:00</Start>
      <Finish>2027-01-22T17:00:00</Finish>
      <Duration>PT120H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>1977600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
    </Task>
    <Task>
      <UID>2</UID>
      <ID>2</ID>
      <Name>Aufgabenstellung klären und Ortsbesichtigung</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-01-04T08:00:00</Start>
      <Finish>2027-01-15T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>2001600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-01-04T08:00:00</ConstraintDate>
      <Notes>Was der Bauherr will und was das Grundstück zulässt: Bestandsunterlagen, Bebauungsplan, Ortsbesichtigung. Am Ende steht eine geklärte Aufgabenstellung.</Notes>
    </Task>
    <Task>
      <UID>3</UID>
      <ID>3</ID>
      <Name>Leistungsbedarf klären, Fachplaner vorschlagen</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-11T08:00:00</Start>
      <Finish>2027-01-22T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>1977600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-01-11T08:00:00</ConstraintDate>
      <Notes>Beraten, welche Fachplaner und Gutachter das Projekt braucht (Tragwerk, Technische Gebäudeausrüstung, Bauphysik, Baugrund); den Bedarfsplan des Bauherrn auswerten.</Notes>
    </Task>
    <Task>
      <UID>4</UID>
      <ID>4</ID>
      <Name>LPH 2 Vorplanung</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-25T08:00:00</Start>
      <Finish>2027-03-03T17:00:00</Finish>
      <Duration>PT224H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>1843200</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
    </Task>
    <Task>
      <UID>5</UID>
      <ID>5</ID>
      <Name>Planungskonzept mit Varianten erarbeiten</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>900</Priority>
      <Start>2027-01-25T08:00:00</Start>
      <Finish>2027-02-26T17:00:00</Finish>
      <Duration>PT200H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>1857600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-01-25T08:00:00</ConstraintDate>
      <Notes>Varianten nach gleichen Anforderungen, mit Lageplan, Skizzen und Flächen, bis eine Lösung empfohlen werden kann.</Notes>
    </Task>
    <Task>
      <UID>6</UID>
      <ID>6</ID>
      <Name>Vorverhandlungen mit den Behörden</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-02-08T08:00:00</Start>
      <Finish>2027-02-26T17:00:00</Finish>
      <Duration>PT120H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>1857600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-02-08T08:00:00</ConstraintDate>
      <Notes>Die Genehmigungsfähigkeit früh klären: Bauaufsicht, Brandschutz, Denkmalschutz, wo nötig eine Bauvoranfrage.</Notes>
    </Task>
    <Task>
      <UID>7</UID>
      <ID>7</ID>
      <Name>Kostenschätzung nach DIN 276 und Terminplan</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-02-22T08:00:00</Start>
      <Finish>2027-03-03T17:00:00</Finish>
      <Duration>PT64H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>1843200</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-02-22T08:00:00</ConstraintDate>
      <Notes>Die Kostenschätzung und ein erster Terminplan mit den wesentlichen Vorgängen, Grundlage für die Freigabe durch den Bauherrn.</Notes>
    </Task>
    <Task>
      <UID>8</UID>
      <ID>8</ID>
      <Name>LPH 3 Entwurfsplanung</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-08T08:00:00</Start>
      <Finish>2027-04-23T17:00:00</Finish>
      <Duration>PT280H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>1665600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
    </Task>
    <Task>
      <UID>9</UID>
      <ID>9</ID>
      <Name>Entwurf mit den Fachplanern durcharbeiten</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>900</Priority>
      <Start>2027-03-08T08:00:00</Start>
      <Finish>2027-04-23T17:00:00</Finish>
      <Duration>PT280H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>1665600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-03-08T08:00:00</ConstraintDate>
      <Notes>Das Planungskonzept bis zum vollständigen Entwurf, mit Tragwerk, Technischer Gebäudeausrüstung und Brandschutz abgestimmt, meist im Maßstab 1:100.</Notes>
    </Task>
    <Task>
      <UID>10</UID>
      <ID>10</ID>
      <Name>Vorplanung freigegeben</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-08T08:00:00</Start>
      <Finish>2027-03-08T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>1833600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-03-08T08:00:00</ConstraintDate>
    </Task>
    <Task>
      <UID>11</UID>
      <ID>11</ID>
      <Name>Kostenberechnung nach DIN 276</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-04-12T08:00:00</Start>
      <Finish>2027-04-23T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>1665600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-04-12T08:00:00</ConstraintDate>
      <Notes>Die Kostenberechnung auf Grundlage des Entwurfs, verglichen mit der Kostenschätzung.</Notes>
    </Task>
    <Task>
      <UID>12</UID>
      <ID>12</ID>
      <Name>Terminplan fortschreiben</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.4</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-19T08:00:00</Start>
      <Finish>2027-04-23T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>1665600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-04-19T08:00:00</ConstraintDate>
      <Notes>Der Terminplan aus der Vorplanung, fortgeschrieben bis zur Vergabe und zum Baubeginn.</Notes>
    </Task>
    <Task>
      <UID>13</UID>
      <ID>13</ID>
      <Name>LPH 4 Genehmigungsplanung</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-05-03T08:00:00</Start>
      <Finish>2027-08-02T08:00:00</Finish>
      <Duration>PT520H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>1329600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
    </Task>
    <Task>
      <UID>14</UID>
      <ID>14</ID>
      <Name>Bauantrag erarbeiten und einreichen</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>900</Priority>
      <Start>2027-05-03T08:00:00</Start>
      <Finish>2027-05-21T17:00:00</Finish>
      <Duration>PT120H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>1569600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-05-03T08:00:00</ConstraintDate>
      <Notes>Die Bauvorlagen nach der Landesbauordnung: Pläne, Baubeschreibung, die Nachweise der Fachplaner und die Antragsformulare.</Notes>
    </Task>
    <Task>
      <UID>15</UID>
      <ID>15</ID>
      <Name>Entwurf freigegeben</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-05-03T08:00:00</Start>
      <Finish>2027-05-03T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>1641600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-05-03T08:00:00</ConstraintDate>
    </Task>
    <Task>
      <UID>16</UID>
      <ID>16</ID>
      <Name>Genehmigungsverfahren begleiten</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-05-24T08:00:00</Start>
      <Finish>2027-07-30T17:00:00</Finish>
      <Duration>PT400H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>1329600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-05-24T08:00:00</ConstraintDate>
      <Notes>Nachforderungen der Behörde beantworten und Unterlagen ergänzen, bis die Baugenehmigung erteilt ist. Die Dauer hängt vom Bauamt ab; setzen Sie Ihre eigene ein.</Notes>
    </Task>
    <Task>
      <UID>17</UID>
      <ID>17</ID>
      <Name>Bauantrag eingereicht</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.4</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-05-24T08:00:00</Start>
      <Finish>2027-05-24T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>1569600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-05-24T08:00:00</ConstraintDate>
    </Task>
    <Task>
      <UID>18</UID>
      <ID>18</ID>
      <Name>Baugenehmigung erteilt</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.5</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-08-02T08:00:00</Start>
      <Finish>2027-08-02T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>1329600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-08-02T08:00:00</ConstraintDate>
    </Task>
    <Task>
      <UID>19</UID>
      <ID>19</ID>
      <Name>LPH 5 Ausführungsplanung</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-05-24T08:00:00</Start>
      <Finish>2027-08-13T17:00:00</Finish>
      <Duration>PT480H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>1281600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
    </Task>
    <Task>
      <UID>20</UID>
      <ID>20</ID>
      <Name>Ausführungsplanung erarbeiten</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>900</Priority>
      <Start>2027-05-24T08:00:00</Start>
      <Finish>2027-08-13T17:00:00</Finish>
      <Duration>PT480H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>1281600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-05-24T08:00:00</ConstraintDate>
      <Notes>Ausführungs-, Detail- und Konstruktionszeichnungen auf Grundlage des Entwurfs, je nach Bauteil im Maßstab 1:50 bis 1:1.</Notes>
    </Task>
    <Task>
      <UID>21</UID>
      <ID>21</ID>
      <Name>Ausführungsplanung mit den Fachplanern abstimmen</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-07-19T08:00:00</Start>
      <Finish>2027-08-13T17:00:00</Finish>
      <Duration>PT160H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>1281600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-07-19T08:00:00</ConstraintDate>
      <Notes>Die Pläne der Fachplaner einarbeiten, Schlitze und Durchbrüche abstimmen.</Notes>
    </Task>
    <Task>
      <UID>22</UID>
      <ID>22</ID>
      <Name>LPH 6 Vorbereitung der Vergabe</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>6</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-07-05T08:00:00</Start>
      <Finish>2027-08-06T17:00:00</Finish>
      <Duration>PT200H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>1305600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
    </Task>
    <Task>
      <UID>23</UID>
      <ID>23</ID>
      <Name>Vergabeterminplan aufstellen</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>6.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-07-05T08:00:00</Start>
      <Finish>2027-07-09T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>1401600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-07-05T08:00:00</ConstraintDate>
      <Notes>Die Termine der Vergabe festlegen, Gewerk für Gewerk, abgestimmt auf den Bauablauf.</Notes>
    </Task>
    <Task>
      <UID>24</UID>
      <ID>24</ID>
      <Name>Mengen ermitteln und Leistungsverzeichnisse aufstellen</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>6.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>900</Priority>
      <Start>2027-07-05T08:00:00</Start>
      <Finish>2027-08-06T17:00:00</Finish>
      <Duration>PT200H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>1305600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-07-05T08:00:00</ConstraintDate>
      <Notes>Leistungsbeschreibungen mit Leistungsverzeichnissen nach Gewerken, die Mengen aus der Ausführungsplanung.</Notes>
    </Task>
    <Task>
      <UID>25</UID>
      <ID>25</ID>
      <Name>Bepreiste Leistungsverzeichnisse gegen die Kostenberechnung prüfen</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>6.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-08-02T08:00:00</Start>
      <Finish>2027-08-06T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>1305600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-08-02T08:00:00</ConstraintDate>
      <Notes>Die vom Planer bepreisten Leistungsverzeichnisse mit der Kostenberechnung vergleichen, bevor ausgeschrieben wird.</Notes>
    </Task>
    <Task>
      <UID>26</UID>
      <ID>26</ID>
      <Name>LPH 7 Mitwirkung bei der Vergabe</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>7</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-08-09T08:00:00</Start>
      <Finish>2027-09-20T08:00:00</Finish>
      <Duration>PT240H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>1161600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
    </Task>
    <Task>
      <UID>27</UID>
      <ID>27</ID>
      <Name>Angebote einholen, prüfen und werten</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>7.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>900</Priority>
      <Start>2027-08-09T08:00:00</Start>
      <Finish>2027-09-10T17:00:00</Finish>
      <Duration>PT200H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>1185600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-08-09T08:00:00</ConstraintDate>
      <Notes>Angebote einholen, prüfen und werten, mit einem Preisspiegel nach Einzelpositionen.</Notes>
    </Task>
    <Task>
      <UID>28</UID>
      <ID>28</ID>
      <Name>Bietergespräche und Vergabevorschlag</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>7.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-09-06T08:00:00</Start>
      <Finish>2027-09-15T17:00:00</Finish>
      <Duration>PT64H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>1171200</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-09-06T08:00:00</ConstraintDate>
      <Notes>Gespräche mit den Bietern, der Vergabevorschlag und die Dokumentation des Vergabeverfahrens.</Notes>
    </Task>
    <Task>
      <UID>29</UID>
      <ID>29</ID>
      <Name>Vertragsunterlagen zusammenstellen</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>7.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-09-13T08:00:00</Start>
      <Finish>2027-09-17T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>1161600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-09-13T08:00:00</ConstraintDate>
      <Notes>Die Vertragsunterlagen für die Gewerke zusammenstellen und die Ausschreibungsergebnisse mit der Kostenberechnung vergleichen.</Notes>
    </Task>
    <Task>
      <UID>30</UID>
      <ID>30</ID>
      <Name>Bauaufträge vergeben</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>7.4</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-09-20T08:00:00</Start>
      <Finish>2027-09-20T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>1161600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-09-20T08:00:00</ConstraintDate>
    </Task>
    <Task>
      <UID>31</UID>
      <ID>31</ID>
      <Name>LPH 8 Objektüberwachung – Bauüberwachung und Dokumentation</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>8</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-09-20T08:00:00</Start>
      <Finish>2028-08-14T08:00:00</Finish>
      <Duration>PT1880H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>33600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
    </Task>
    <Task>
      <UID>32</UID>
      <ID>32</ID>
      <Name>Bauausführung überwachen</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>8.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>900</Priority>
      <Start>2027-09-20T08:00:00</Start>
      <Finish>2028-07-14T17:00:00</Finish>
      <Duration>PT1720H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>129600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-09-20T08:00:00</ConstraintDate>
      <Notes>Die Ausführung auf Übereinstimmung mit Baugenehmigung, Ausführungsplanung und Verträgen überwachen, die Gewerke koordinieren, ein Bautagebuch führen.</Notes>
    </Task>
    <Task>
      <UID>33</UID>
      <ID>33</ID>
      <Name>Termine, Rechnungen und Kosten kontrollieren</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>8.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-09-20T08:00:00</Start>
      <Finish>2028-07-14T17:00:00</Finish>
      <Duration>PT1720H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>129600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-09-20T08:00:00</ConstraintDate>
      <Notes>Den Terminplan fortschreiben und überwachen, Aufmaße und Rechnungen prüfen, die Kostenfeststellung vorbereiten.</Notes>
    </Task>
    <Task>
      <UID>34</UID>
      <ID>34</ID>
      <Name>Abnahme organisieren</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>8.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>900</Priority>
      <Start>2028-07-17T08:00:00</Start>
      <Finish>2028-07-21T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>105600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2028-07-17T08:00:00</ConstraintDate>
      <Notes>Die Abnahme mit den ausführenden Firmen organisieren, Mängel protokollieren und dem Bauherrn die Abnahme empfehlen.</Notes>
    </Task>
    <Task>
      <UID>35</UID>
      <ID>35</ID>
      <Name>Mängelbeseitigung überwachen und Unterlagen übergeben</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>8.4</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2028-07-24T08:00:00</Start>
      <Finish>2028-08-11T17:00:00</Finish>
      <Duration>PT120H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>33600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2028-07-24T08:00:00</ConstraintDate>
      <Notes>Die Beseitigung der Mängel aus der Abnahme überwachen, Kostenfeststellung, Dokumentation und die Liste der Verjährungsfristen an den Bauherrn übergeben.</Notes>
    </Task>
    <Task>
      <UID>36</UID>
      <ID>36</ID>
      <Name>Abnahme</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>8.5</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2028-07-24T08:00:00</Start>
      <Finish>2028-07-24T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>105600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2028-07-24T08:00:00</ConstraintDate>
    </Task>
    <Task>
      <UID>37</UID>
      <ID>37</ID>
      <Name>Übergabe an den Bauherrn</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>8.6</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2028-08-14T08:00:00</Start>
      <Finish>2028-08-14T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>33600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2028-08-14T08:00:00</ConstraintDate>
    </Task>
    <Task>
      <UID>38</UID>
      <ID>38</ID>
      <Name>LPH 9 Objektbetreuung</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>9</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2028-08-14T08:00:00</Start>
      <Finish>2028-08-22T17:00:00</Finish>
      <Duration>PT56H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
    </Task>
    <Task>
      <UID>39</UID>
      <ID>39</ID>
      <Name>Objektbegehung vor Ablauf der Verjährungsfristen</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>9.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2028-08-14T08:00:00</Start>
      <Finish>2028-08-22T17:00:00</Finish>
      <Duration>PT56H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2028-08-14T08:00:00</ConstraintDate>
      <Notes>Begehung zur Mängelfeststellung und Mitwirken bei der Freigabe von Sicherheitsleistungen. Hier direkt nach der Übergabe eingetragen; legen Sie den Termin vor das Ende Ihrer Verjährungsfrist.</Notes>
    </Task>
  </Tasks>
</Project>