<Project xmlns="http://schemas.microsoft.com/project">
  <SaveVersion>14</SaveVersion>
  <Name>AIA Design Phases (Architecture, US)</Name>
  <Title>AIA Design Phases (Architecture, US)</Title>
  <ScheduleFromStart>1</ScheduleFromStart>
  <StartDate>2027-01-04T08:00:00</StartDate>
  <FinishDate>2028-02-08T08:00:00</FinishDate>
  <CalendarUID>1</CalendarUID>
  <DefaultStartTime>08:00:00</DefaultStartTime>
  <DefaultFinishTime>17:00:00</DefaultFinishTime>
  <DurationFormat>7</DurationFormat>
  <NewTasksAreManual>0</NewTasksAreManual>
  <ProjectExternallyEdited>0</ProjectExternallyEdited>
  <Calendars>
    <Calendar>
      <UID>1</UID>
      <Name>Standard</Name>
      <IsBaseCalendar>1</IsBaseCalendar>
      <BaseCalendarUID>-1</BaseCalendarUID>
      <WeekDays>
        <WeekDay>
          <DayType>1</DayType>
          <DayWorking>0</DayWorking>
        </WeekDay>
        <WeekDay>
          <DayType>2</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>3</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>4</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>5</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>6</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>7</DayType>
          <DayWorking>0</DayWorking>
        </WeekDay>
      </WeekDays>
    </Calendar>
  </Calendars>
  <Tasks>
    <Task>
      <UID>1</UID>
      <ID>1</ID>
      <Name>Schematic Design</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-04T08:00:00</Start>
      <Finish>2027-02-18T08:00:00</Finish>
      <Duration>PT264H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>1214400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
    </Task>
    <Task>
      <UID>2</UID>
      <ID>2</ID>
      <Name>Confirm the program, budget and site constraints</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>900</Priority>
      <Start>2027-01-04T08:00:00</Start>
      <Finish>2027-01-15T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>1324800</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-01-04T08:00:00</ConstraintDate>
      <Notes>The owner's program, budget and schedule confirmed; zoning, code and site conditions reviewed before anything is drawn.</Notes>
    </Task>
    <Task>
      <UID>3</UID>
      <ID>3</ID>
      <Name>Prepare the schematic design alternatives</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>900</Priority>
      <Start>2027-01-14T08:00:00</Start>
      <Finish>2027-02-05T17:00:00</Finish>
      <Duration>PT136H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>1252800</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-01-14T08:00:00</ConstraintDate>
      <Notes>Site plan, floor plans, massing and building sections for two or three alternatives, with a recommended scheme.</Notes>
    </Task>
    <Task>
      <UID>4</UID>
      <ID>4</ID>
      <Name>Prepare the preliminary cost estimate</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-08T08:00:00</Start>
      <Finish>2027-02-12T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>1228800</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-02-08T08:00:00</ConstraintDate>
      <Notes>The estimate against the budget, and the schedule re-baselined on the scheme.</Notes>
    </Task>
    <Task>
      <UID>5</UID>
      <ID>5</ID>
      <Name>Owner approval of schematic design</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.4</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>900</Priority>
      <Start>2027-02-16T08:00:00</Start>
      <Finish>2027-02-17T17:00:00</Finish>
      <Duration>PT16H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>1214400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-02-16T08:00:00</ConstraintDate>
      <Notes>The SD set approved in writing. The SD fee, customarily 15%, is invoiced at approval.</Notes>
    </Task>
    <Task>
      <UID>6</UID>
      <ID>6</ID>
      <Name>Schematic design approved</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.5</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-18T08:00:00</Start>
      <Finish>2027-02-18T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>1214400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-02-18T08:00:00</ConstraintDate>
    </Task>
    <Task>
      <UID>7</UID>
      <ID>7</ID>
      <Name>Design Development</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-18T08:00:00</Start>
      <Finish>2027-04-29T08:00:00</Finish>
      <Duration>PT400H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>974400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
    </Task>
    <Task>
      <UID>8</UID>
      <ID>8</ID>
      <Name>Develop the design and coordinate the engineering</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>900</Priority>
      <Start>2027-02-18T08:00:00</Start>
      <Finish>2027-04-08T17:00:00</Finish>
      <Duration>PT288H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>1041600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-02-18T08:00:00</ConstraintDate>
      <Notes>Refined plans, sections and elevations; structural, mechanical, electrical and plumbing systems selected and coordinated.</Notes>
    </Task>
    <Task>
      <UID>9</UID>
      <ID>9</ID>
      <Name>Select materials, finishes and major equipment</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-03-15T08:00:00</Start>
      <Finish>2027-04-13T17:00:00</Finish>
      <Duration>PT176H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>1027200</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-03-15T08:00:00</ConstraintDate>
      <Notes>Outline specifications, finish schedules, and the equipment that drives the MEP design.</Notes>
    </Task>
    <Task>
      <UID>10</UID>
      <ID>10</ID>
      <Name>Update the cost estimate and reconcile it to the budget</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-19T08:00:00</Start>
      <Finish>2027-04-26T17:00:00</Finish>
      <Duration>PT48H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>984000</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-04-19T08:00:00</ConstraintDate>
      <Notes>The DD estimate reconciled, with value-engineering decisions recorded before construction documents begin.</Notes>
    </Task>
    <Task>
      <UID>11</UID>
      <ID>11</ID>
      <Name>Owner approval of design development</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.4</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>900</Priority>
      <Start>2027-04-27T08:00:00</Start>
      <Finish>2027-04-28T17:00:00</Finish>
      <Duration>PT16H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>974400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-04-27T08:00:00</ConstraintDate>
      <Notes>The DD set approved; customarily 20% of the fee.</Notes>
    </Task>
    <Task>
      <UID>12</UID>
      <ID>12</ID>
      <Name>Design development approved</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.5</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-29T08:00:00</Start>
      <Finish>2027-04-29T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>974400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-04-29T08:00:00</ConstraintDate>
    </Task>
    <Task>
      <UID>13</UID>
      <ID>13</ID>
      <Name>Construction Documents</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-29T08:00:00</Start>
      <Finish>2027-08-27T08:00:00</Finish>
      <Duration>PT688H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>561600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
    </Task>
    <Task>
      <UID>14</UID>
      <ID>14</ID>
      <Name>Produce the construction documents</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>900</Priority>
      <Start>2027-04-29T08:00:00</Start>
      <Finish>2027-08-06T17:00:00</Finish>
      <Duration>PT576H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>628800</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-04-29T08:00:00</ConstraintDate>
      <Notes>Drawings and specifications in the detail a contractor needs to price and build, coordinated across every discipline.</Notes>
    </Task>
    <Task>
      <UID>15</UID>
      <ID>15</ID>
      <Name>Complete the code review and permit submission</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-07-08T08:00:00</Start>
      <Finish>2027-08-16T17:00:00</Finish>
      <Duration>PT224H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>600000</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-07-08T08:00:00</ConstraintDate>
      <Notes>The building department submission, reviewer comments answered, the permit obtained.</Notes>
    </Task>
    <Task>
      <UID>16</UID>
      <ID>16</ID>
      <Name>Owner approval of construction documents</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>900</Priority>
      <Start>2027-08-25T08:00:00</Start>
      <Finish>2027-08-26T17:00:00</Finish>
      <Duration>PT16H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>561600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-08-25T08:00:00</ConstraintDate>
      <Notes>The CD set approved; customarily 40% of the fee.</Notes>
    </Task>
    <Task>
      <UID>17</UID>
      <ID>17</ID>
      <Name>Construction documents approved</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.4</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-08-27T08:00:00</Start>
      <Finish>2027-08-27T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>561600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-08-27T08:00:00</ConstraintDate>
    </Task>
    <Task>
      <UID>18</UID>
      <ID>18</ID>
      <Name>Bidding and Negotiation</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-08-27T08:00:00</Start>
      <Finish>2027-09-28T17:00:00</Finish>
      <Duration>PT184H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>451200</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
    </Task>
    <Task>
      <UID>19</UID>
      <ID>19</ID>
      <Name>Issue the bid documents and run the bid period</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-08-27T08:00:00</Start>
      <Finish>2027-09-20T17:00:00</Finish>
      <Duration>PT136H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>480000</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-08-27T08:00:00</ConstraintDate>
      <Notes>The bid set issued, the pre-bid meeting held, questions answered by addendum.</Notes>
    </Task>
    <Task>
      <UID>20</UID>
      <ID>20</ID>
      <Name>Evaluate the bids and recommend the award</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-09-21T08:00:00</Start>
      <Finish>2027-09-28T17:00:00</Finish>
      <Duration>PT48H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>451200</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-09-21T08:00:00</ConstraintDate>
      <Notes>Bid tabulation, qualifications reviewed, the owner-contractor agreement prepared. Customarily 5% of the fee.</Notes>
    </Task>
    <Task>
      <UID>21</UID>
      <ID>21</ID>
      <Name>Construction Administration</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-10-01T08:00:00</Start>
      <Finish>2028-02-08T08:00:00</Finish>
      <Duration>PT736H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
    </Task>
    <Task>
      <UID>22</UID>
      <ID>22</ID>
      <Name>Administer the construction contract</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>900</Priority>
      <Start>2027-10-01T08:00:00</Start>
      <Finish>2028-01-21T17:00:00</Finish>
      <Duration>PT648H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>52800</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-10-01T08:00:00</ConstraintDate>
      <Notes>Site visits, pay application review and certification, change orders, RFIs and submittals. Customarily 20% of the fee.</Notes>
    </Task>
    <Task>
      <UID>23</UID>
      <ID>23</ID>
      <Name>Contract awarded</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-10-01T08:00:00</Start>
      <Finish>2027-10-01T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>441600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-10-01T08:00:00</ConstraintDate>
    </Task>
    <Task>
      <UID>24</UID>
      <ID>24</ID>
      <Name>Review submittals and respond to RFIs</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-10-06T08:00:00</Start>
      <Finish>2028-01-13T17:00:00</Finish>
      <Duration>PT576H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>81600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-10-06T08:00:00</ConstraintDate>
      <Notes>Turnaround tracked; a response that changes scope is routed as a change order, never absorbed.</Notes>
    </Task>
    <Task>
      <UID>25</UID>
      <ID>25</ID>
      <Name>Conduct the substantial completion inspection and punch list</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5.4</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>900</Priority>
      <Start>2028-01-24T08:00:00</Start>
      <Finish>2028-01-31T17:00:00</Finish>
      <Duration>PT48H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>24000</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2028-01-24T08:00:00</ConstraintDate>
      <Notes>The inspection, the punch list issued and closed, the certificate of substantial completion.</Notes>
    </Task>
    <Task>
      <UID>26</UID>
      <ID>26</ID>
      <Name>Close out the project and reconcile the fee</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5.5</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2028-01-31T08:00:00</Start>
      <Finish>2028-02-07T17:00:00</Finish>
      <Duration>PT48H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2028-01-31T08:00:00</ConstraintDate>
      <Notes>Final completion, record documents, the final pay application, and the fee reconciled against the phase schedule.</Notes>
    </Task>
    <Task>
      <UID>27</UID>
      <ID>27</ID>
      <Name>Substantial completion</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5.6</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2028-02-01T08:00:00</Start>
      <Finish>2028-02-01T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>24000</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2028-02-01T08:00:00</ConstraintDate>
    </Task>
    <Task>
      <UID>28</UID>
      <ID>28</ID>
      <Name>Final completion</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5.7</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2028-02-08T08:00:00</Start>
      <Finish>2028-02-08T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2028-02-08T08:00:00</ConstraintDate>
    </Task>
  </Tasks>
</Project>