<?xml version="1.0" encoding="UTF-8" standalone="yes"?>
<Project xmlns="http://schemas.microsoft.com/project">
  <SaveVersion>14</SaveVersion>
  <Name>Client Engagement</Name>
  <Title>Client Engagement</Title>
  <ScheduleFromStart>1</ScheduleFromStart>
  <StartDate>2027-01-04T08:00:00</StartDate>
  <FinishDate>2027-03-05T17:00:00</FinishDate>
  <CalendarUID>1</CalendarUID>
  <DefaultStartTime>08:00:00</DefaultStartTime>
  <DefaultFinishTime>17:00:00</DefaultFinishTime>
  <DurationFormat>7</DurationFormat>
  <NewTasksAreManual>0</NewTasksAreManual>
  <ProjectExternallyEdited>0</ProjectExternallyEdited>
  <Calendars>
    <Calendar>
      <UID>1</UID>
      <Name>Standard</Name>
      <IsBaseCalendar>1</IsBaseCalendar>
      <BaseCalendarUID>-1</BaseCalendarUID>
      <WeekDays>
        <WeekDay>
          <DayType>1</DayType>
          <DayWorking>0</DayWorking>
        </WeekDay>
        <WeekDay>
          <DayType>2</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>3</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>4</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>5</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>6</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>7</DayType>
          <DayWorking>0</DayWorking>
        </WeekDay>
      </WeekDays>
    </Calendar>
  </Calendars>
  <Tasks>
    <Task>
      <UID>1</UID>
      <ID>1</ID>
      <Name>Scope &amp; contract</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-04T08:00:00</Start>
      <Finish>2027-01-11T17:00:00</Finish>
      <Duration>PT48H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>187200</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
    </Task>
    <Task>
      <UID>2</UID>
      <ID>2</ID>
      <Name>Confirm scope and acceptance criteria</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>900</Priority>
      <Start>2027-01-04T08:00:00</Start>
      <Finish>2027-01-07T17:00:00</Finish>
      <Duration>PT32H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>196800</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-01-04T08:00:00</ConstraintDate>
      <Notes>What is in, what is explicitly out, and how the client will judge each deliverable done.</Notes>
    </Task>
    <Task>
      <UID>3</UID>
      <ID>3</ID>
      <Name>Agree rate card and billing schedule</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-01-06T08:00:00</Start>
      <Finish>2027-01-08T17:00:00</Finish>
      <Duration>PT24H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>192000</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-01-06T08:00:00</ConstraintDate>
      <Notes>Rates by grade, invoicing cadence, expenses policy, and the purchase-order reference to quote.</Notes>
    </Task>
    <Task>
      <UID>4</UID>
      <ID>4</ID>
      <Name>Sign the statement of work</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>900</Priority>
      <Start>2027-01-11T08:00:00</Start>
      <Finish>2027-01-11T17:00:00</Finish>
      <Duration>PT8H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>187200</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-01-11T08:00:00</ConstraintDate>
      <Notes>Countersigned SOW filed, project marked billable, and the billing code set before anyone logs an hour.</Notes>
    </Task>
    <Task>
      <UID>5</UID>
      <ID>5</ID>
      <Name>SOW signed</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.4</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-11T08:00:00</Start>
      <Finish>2027-01-11T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>192000</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-01-11T08:00:00</ConstraintDate>
    </Task>
    <Task>
      <UID>6</UID>
      <ID>6</ID>
      <Name>Discovery</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-11T08:00:00</Start>
      <Finish>2027-01-25T17:00:00</Finish>
      <Duration>PT88H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>139200</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
    </Task>
    <Task>
      <UID>7</UID>
      <ID>7</ID>
      <Name>Run stakeholder interviews</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-01-11T08:00:00</Start>
      <Finish>2027-01-18T17:00:00</Finish>
      <Duration>PT48H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>163200</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-01-11T08:00:00</ConstraintDate>
      <Notes>Six to ten conversations across the client side. Record who decides, who blocks, and who is merely consulted.</Notes>
    </Task>
    <Task>
      <UID>8</UID>
      <ID>8</ID>
      <Name>Assess the current state</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-01-14T08:00:00</Start>
      <Finish>2027-01-22T17:00:00</Finish>
      <Duration>PT56H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>144000</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-01-14T08:00:00</ConstraintDate>
      <Notes>Document what exists today against what the SOW assumes exists. The gap is where change requests come from.</Notes>
    </Task>
    <Task>
      <UID>9</UID>
      <ID>9</ID>
      <Name>Present the discovery readout</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-01-25T08:00:00</Start>
      <Finish>2027-01-25T17:00:00</Finish>
      <Duration>PT8H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>139200</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-01-25T08:00:00</ConstraintDate>
      <Notes>Findings, revised approach, and any assumption that turned out false. Get it acknowledged in writing.</Notes>
    </Task>
    <Task>
      <UID>10</UID>
      <ID>10</ID>
      <Name>Discovery readout</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.4</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-25T08:00:00</Start>
      <Finish>2027-01-25T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>144000</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-01-25T08:00:00</ConstraintDate>
    </Task>
    <Task>
      <UID>11</UID>
      <ID>11</ID>
      <Name>Delivery</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-26T08:00:00</Start>
      <Finish>2027-03-01T17:00:00</Finish>
      <Duration>PT200H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>19200</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
    </Task>
    <Task>
      <UID>12</UID>
      <ID>12</ID>
      <Name>Deliver workstream one</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-01-26T08:00:00</Start>
      <Finish>2027-02-12T17:00:00</Finish>
      <Duration>PT112H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>72000</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-01-26T08:00:00</ConstraintDate>
      <Notes>The first substantive deliverable. Log hours against this task so utilisation and margin stay real.</Notes>
    </Task>
    <Task>
      <UID>13</UID>
      <ID>13</ID>
      <Name>Deliver workstream two</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-02-03T08:00:00</Start>
      <Finish>2027-02-19T17:00:00</Finish>
      <Duration>PT104H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>48000</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-02-03T08:00:00</ConstraintDate>
      <Notes>The second deliverable, usually overlapping the first. Watch the capacity view before committing anyone else.</Notes>
    </Task>
    <Task>
      <UID>14</UID>
      <ID>14</ID>
      <Name>Hold the weekly client status</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-26T08:00:00</Start>
      <Finish>2027-03-01T17:00:00</Finish>
      <Duration>PT200H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>19200</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-01-26T08:00:00</ConstraintDate>
      <Notes>One recurring slot: progress, decisions needed, and anything trending toward a change request.</Notes>
    </Task>
    <Task>
      <UID>15</UID>
      <ID>15</ID>
      <Name>Log and price change requests</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.4</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-01-29T08:00:00</Start>
      <Finish>2027-02-26T17:00:00</Finish>
      <Duration>PT168H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>24000</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-01-29T08:00:00</ConstraintDate>
      <Notes>Anything outside the signed scope gets written down and priced before it gets worked, not after.</Notes>
    </Task>
    <Task>
      <UID>16</UID>
      <ID>16</ID>
      <Name>Handover &amp; close</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-22T08:00:00</Start>
      <Finish>2027-03-05T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
    </Task>
    <Task>
      <UID>17</UID>
      <ID>17</ID>
      <Name>Hand over documentation and training</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-02-22T08:00:00</Start>
      <Finish>2027-03-01T17:00:00</Finish>
      <Duration>PT48H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>19200</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-02-22T08:00:00</ConstraintDate>
      <Notes>Runbooks, access, and a working session so the client team can operate it without you.</Notes>
    </Task>
    <Task>
      <UID>18</UID>
      <ID>18</ID>
      <Name>Obtain final acceptance sign-off</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>900</Priority>
      <Start>2027-03-02T08:00:00</Start>
      <Finish>2027-03-04T17:00:00</Finish>
      <Duration>PT24H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>4800</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-03-02T08:00:00</ConstraintDate>
      <Notes>Written acceptance against the criteria agreed in week one. This is what unlocks the final invoice.</Notes>
    </Task>
    <Task>
      <UID>19</UID>
      <ID>19</ID>
      <Name>Run the margin and lessons review</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-05T08:00:00</Start>
      <Finish>2027-03-05T17:00:00</Finish>
      <Duration>PT8H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-03-05T08:00:00</ConstraintDate>
      <Notes>Planned versus actual hours, realised margin, and what to price differently next time.</Notes>
    </Task>
    <Task>
      <UID>20</UID>
      <ID>20</ID>
      <Name>Final acceptance</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.4</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-05T08:00:00</Start>
      <Finish>2027-03-05T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>4800</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-03-05T08:00:00</ConstraintDate>
    </Task>
  </Tasks>
</Project>