<?xml version="1.0" encoding="UTF-8" standalone="yes"?>
<Project xmlns="http://schemas.microsoft.com/project">
  <SaveVersion>14</SaveVersion>
  <Name>Data Migration Cutover</Name>
  <Title>Data Migration Cutover</Title>
  <ScheduleFromStart>1</ScheduleFromStart>
  <StartDate>2027-01-04T08:00:00</StartDate>
  <FinishDate>2027-03-04T08:00:00</FinishDate>
  <CalendarUID>1</CalendarUID>
  <DefaultStartTime>08:00:00</DefaultStartTime>
  <DefaultFinishTime>17:00:00</DefaultFinishTime>
  <DurationFormat>7</DurationFormat>
  <NewTasksAreManual>0</NewTasksAreManual>
  <ProjectExternallyEdited>0</ProjectExternallyEdited>
  <Calendars>
    <Calendar>
      <UID>1</UID>
      <Name>Standard</Name>
      <IsBaseCalendar>1</IsBaseCalendar>
      <BaseCalendarUID>-1</BaseCalendarUID>
      <WeekDays>
        <WeekDay>
          <DayType>1</DayType>
          <DayWorking>0</DayWorking>
        </WeekDay>
        <WeekDay>
          <DayType>2</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>3</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>4</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>5</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>6</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>7</DayType>
          <DayWorking>0</DayWorking>
        </WeekDay>
      </WeekDays>
    </Calendar>
  </Calendars>
  <Tasks>
    <Task>
      <UID>1</UID>
      <ID>1</ID>
      <Name>Discovery</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-04T08:00:00</Start>
      <Finish>2027-01-13T17:00:00</Finish>
      <Duration>PT64H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>168000</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
    </Task>
    <Task>
      <UID>2</UID>
      <ID>2</ID>
      <Name>Inventory the source estate</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-01-04T08:00:00</Start>
      <Finish>2027-01-08T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>182400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-01-04T08:00:00</ConstraintDate>
      <Notes>Site collections, mailboxes, file shares, group memberships. Record volume in GB and item counts, both matter to throughput.</Notes>
    </Task>
    <Task>
      <UID>3</UID>
      <ID>3</ID>
      <Name>Name a data owner for every workload</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-06T08:00:00</Start>
      <Finish>2027-01-08T17:00:00</Finish>
      <Duration>PT24H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>182400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-01-06T08:00:00</ConstraintDate>
      <Notes>One accountable owner per site, share or mailbox group. Unowned data is what stalls a wave.</Notes>
    </Task>
    <Task>
      <UID>4</UID>
      <ID>4</ID>
      <Name>Record baseline counts for reconciliation</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-01-11T08:00:00</Start>
      <Finish>2027-01-11T17:00:00</Finish>
      <Duration>PT8H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>177600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-01-11T08:00:00</ConstraintDate>
      <Notes>Item counts and totals per workload, captured before anything moves. You cannot reconcile against a number you did not take.</Notes>
    </Task>
    <Task>
      <UID>5</UID>
      <ID>5</ID>
      <Name>Agree what does not move</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.4</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-11T08:00:00</Start>
      <Finish>2027-01-13T17:00:00</Finish>
      <Duration>PT24H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>168000</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-01-11T08:00:00</ConstraintDate>
      <Notes>Archive, leave in place, or delete. Every GB ruled out here is throughput you get back later.</Notes>
    </Task>
    <Task>
      <UID>6</UID>
      <ID>6</ID>
      <Name>Design</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-14T08:00:00</Start>
      <Finish>2027-01-22T17:00:00</Finish>
      <Duration>PT56H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>134400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
    </Task>
    <Task>
      <UID>7</UID>
      <ID>7</ID>
      <Name>Map identities and group membership</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-01-14T08:00:00</Start>
      <Finish>2027-01-18T17:00:00</Finish>
      <Duration>PT24H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>153600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-01-14T08:00:00</ConstraintDate>
      <Notes>Source accounts and groups to target accounts and groups, including the ones that will not exist on the other side.</Notes>
    </Task>
    <Task>
      <UID>8</UID>
      <ID>8</ID>
      <Name>Map permissions, and decide where inheritance breaks</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-01-18T08:00:00</Start>
      <Finish>2027-01-20T17:00:00</Finish>
      <Duration>PT24H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>144000</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-01-18T08:00:00</ConstraintDate>
      <Notes>Broken inheritance and per-item permissions rarely survive intact. Decide now which are recreated and which are dropped.</Notes>
    </Task>
    <Task>
      <UID>9</UID>
      <ID>9</ID>
      <Name>Choose the tooling and prove throughput</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-01-19T08:00:00</Start>
      <Finish>2027-01-22T17:00:00</Finish>
      <Duration>PT32H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>134400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-01-19T08:00:00</ConstraintDate>
      <Notes>Measure GB per hour against the live target, not a lab. Throttling is the number every wave plan depends on.</Notes>
    </Task>
    <Task>
      <UID>10</UID>
      <ID>10</ID>
      <Name>Pilot</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-25T08:00:00</Start>
      <Finish>2027-02-01T08:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>110400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
    </Task>
    <Task>
      <UID>11</UID>
      <ID>11</ID>
      <Name>Run a pilot wave with one willing team</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-01-25T08:00:00</Start>
      <Finish>2027-01-27T17:00:00</Finish>
      <Duration>PT24H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>120000</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-01-25T08:00:00</ConstraintDate>
      <Notes>A team that will tell you what broke. Small enough to redo, representative enough to learn from.</Notes>
    </Task>
    <Task>
      <UID>12</UID>
      <ID>12</ID>
      <Name>Reconcile the pilot against the baseline</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-01-28T08:00:00</Start>
      <Finish>2027-01-29T17:00:00</Finish>
      <Duration>PT16H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>110400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-01-28T08:00:00</ConstraintDate>
      <Notes>Item counts, permissions, and a sample opened by a real user. Sign-off is the gate to wave 1.</Notes>
    </Task>
    <Task>
      <UID>13</UID>
      <ID>13</ID>
      <Name>Write the user comms and the rollback note</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-29T08:00:00</Start>
      <Finish>2027-01-29T17:00:00</Finish>
      <Duration>PT8H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>110400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-01-29T08:00:00</ConstraintDate>
      <Notes>What changes, when, what to do if it looks wrong, and what the rollback actually is. Send before the wave, not during it.</Notes>
    </Task>
    <Task>
      <UID>14</UID>
      <ID>14</ID>
      <Name>Pilot signed off</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.4</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-01T08:00:00</Start>
      <Finish>2027-02-01T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>110400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-02-01T08:00:00</ConstraintDate>
    </Task>
    <Task>
      <UID>15</UID>
      <ID>15</ID>
      <Name>Waves</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-03T08:00:00</Start>
      <Finish>2027-02-19T08:00:00</Finish>
      <Duration>PT96H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>43200</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
    </Task>
    <Task>
      <UID>16</UID>
      <ID>16</ID>
      <Name>Migrate in waves by owner, not by volume</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-02-03T08:00:00</Start>
      <Finish>2027-02-16T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>52800</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-02-03T08:00:00</ConstraintDate>
      <Notes>Group a wave around people who work together, so a half-migrated team is never trying to share a file across the boundary.</Notes>
    </Task>
    <Task>
      <UID>17</UID>
      <ID>17</ID>
      <Name>Run delta syncs behind each wave</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-02-08T08:00:00</Start>
      <Finish>2027-02-16T17:00:00</Finish>
      <Duration>PT56H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>52800</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-02-08T08:00:00</ConstraintDate>
      <Notes>Source stays live during coexistence, so everything already moved keeps changing. Delta until the final pass is small.</Notes>
    </Task>
    <Task>
      <UID>18</UID>
      <ID>18</ID>
      <Name>All waves migrated</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-19T08:00:00</Start>
      <Finish>2027-02-19T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>43200</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-02-19T08:00:00</ConstraintDate>
    </Task>
    <Task>
      <UID>19</UID>
      <ID>19</ID>
      <Name>Cutover</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-25T08:00:00</Start>
      <Finish>2027-03-04T08:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
    </Task>
    <Task>
      <UID>20</UID>
      <ID>20</ID>
      <Name>Final delta, then switch the endpoint</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>900</Priority>
      <Start>2027-02-25T08:00:00</Start>
      <Finish>2027-02-26T17:00:00</Finish>
      <Duration>PT16H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>14400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-02-25T08:00:00</ConstraintDate>
      <Notes>Freeze the source, run the last delta, then move DNS, MX or the mapped drive. The switch is the cheap part if the delta is small.</Notes>
    </Task>
    <Task>
      <UID>21</UID>
      <ID>21</ID>
      <Name>Production cutover</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-01T08:00:00</Start>
      <Finish>2027-03-01T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>14400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-03-01T08:00:00</ConstraintDate>
    </Task>
    <Task>
      <UID>22</UID>
      <ID>22</ID>
      <Name>Decommission the source and reclaim licences</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-01T08:00:00</Start>
      <Finish>2027-03-03T17:00:00</Finish>
      <Duration>PT24H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-03-01T08:00:00</ConstraintDate>
      <Notes>Read-only first, then decommission on a date you announced. Licences and storage are the savings the business was promised.</Notes>
    </Task>
    <Task>
      <UID>23</UID>
      <ID>23</ID>
      <Name>Source decommissioned</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5.4</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-04T08:00:00</Start>
      <Finish>2027-03-04T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-03-04T08:00:00</ConstraintDate>
    </Task>
  </Tasks>
</Project>