<Project xmlns="http://schemas.microsoft.com/project">
  <SaveVersion>14</SaveVersion>
  <Name>Phase-Gate Product Development</Name>
  <Title>Phase-Gate Product Development</Title>
  <ScheduleFromStart>1</ScheduleFromStart>
  <StartDate>2027-01-04T08:00:00</StartDate>
  <FinishDate>2027-07-02T17:00:00</FinishDate>
  <CalendarUID>1</CalendarUID>
  <DefaultStartTime>08:00:00</DefaultStartTime>
  <DefaultFinishTime>17:00:00</DefaultFinishTime>
  <DurationFormat>7</DurationFormat>
  <NewTasksAreManual>0</NewTasksAreManual>
  <ProjectExternallyEdited>0</ProjectExternallyEdited>
  <Calendars>
    <Calendar>
      <UID>1</UID>
      <Name>Standard</Name>
      <IsBaseCalendar>1</IsBaseCalendar>
      <BaseCalendarUID>-1</BaseCalendarUID>
      <WeekDays>
        <WeekDay>
          <DayType>1</DayType>
          <DayWorking>0</DayWorking>
        </WeekDay>
        <WeekDay>
          <DayType>2</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>3</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>4</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>5</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>6</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>7</DayType>
          <DayWorking>0</DayWorking>
        </WeekDay>
      </WeekDays>
    </Calendar>
  </Calendars>
  <Tasks>
    <Task>
      <UID>1</UID>
      <ID>1</ID>
      <Name>Concept</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-04T08:00:00</Start>
      <Finish>2027-01-25T17:00:00</Finish>
      <Duration>PT128H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>547200</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
    </Task>
    <Task>
      <UID>2</UID>
      <ID>2</ID>
      <Name>Define the opportunity and target cost</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>900</Priority>
      <Start>2027-01-04T08:00:00</Start>
      <Finish>2027-01-13T17:00:00</Finish>
      <Duration>PT64H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>585600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-01-04T08:00:00</ConstraintDate>
      <Notes>The customer problem, the market it sits in, and the unit cost the product has to hit to be worth building.</Notes>
    </Task>
    <Task>
      <UID>3</UID>
      <ID>3</ID>
      <Name>Draft the product requirements</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-01-11T08:00:00</Start>
      <Finish>2027-01-22T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>552000</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-01-11T08:00:00</ConstraintDate>
      <Notes>Functional and non-functional requirements, with the regulatory ones identified now rather than at validation.</Notes>
    </Task>
    <Task>
      <UID>4</UID>
      <ID>4</ID>
      <Name>Hold Gate 1, concept review</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>900</Priority>
      <Start>2027-01-25T08:00:00</Start>
      <Finish>2027-01-25T17:00:00</Finish>
      <Duration>PT8H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>547200</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-01-25T08:00:00</ConstraintDate>
      <Notes>Go, no-go, or recycle. Record the decision, the reviewers, and the conditions attached to a go.</Notes>
    </Task>
    <Task>
      <UID>5</UID>
      <ID>5</ID>
      <Name>Gate 1, concept approved</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.4</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-25T08:00:00</Start>
      <Finish>2027-01-25T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>552000</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-01-25T08:00:00</ConstraintDate>
    </Task>
    <Task>
      <UID>6</UID>
      <ID>6</ID>
      <Name>Feasibility</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-27T08:00:00</Start>
      <Finish>2027-02-26T17:00:00</Finish>
      <Duration>PT184H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>432000</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
    </Task>
    <Task>
      <UID>7</UID>
      <ID>7</ID>
      <Name>Run technical feasibility studies</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>900</Priority>
      <Start>2027-01-27T08:00:00</Start>
      <Finish>2027-02-19T17:00:00</Finish>
      <Duration>PT144H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>456000</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-01-27T08:00:00</ConstraintDate>
      <Notes>De-risk the two or three unknowns that would invalidate the concept, before committing tooling spend.</Notes>
    </Task>
    <Task>
      <UID>8</UID>
      <ID>8</ID>
      <Name>Assess supply chain and lead times</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-02-03T08:00:00</Start>
      <Finish>2027-02-22T17:00:00</Finish>
      <Duration>PT112H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>451200</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-02-03T08:00:00</ConstraintDate>
      <Notes>Long-lead components identified and second-sourced where a single supplier would gate the launch date.</Notes>
    </Task>
    <Task>
      <UID>9</UID>
      <ID>9</ID>
      <Name>Hold Gate 2, feasibility review</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>900</Priority>
      <Start>2027-02-25T08:00:00</Start>
      <Finish>2027-02-26T17:00:00</Finish>
      <Duration>PT16H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>432000</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-02-25T08:00:00</ConstraintDate>
      <Notes>Confirm the design is buildable at the target cost before development spend is released.</Notes>
    </Task>
    <Task>
      <UID>10</UID>
      <ID>10</ID>
      <Name>Gate 2, feasibility passed</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.4</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-26T08:00:00</Start>
      <Finish>2027-02-26T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>436800</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-02-26T08:00:00</ConstraintDate>
    </Task>
    <Task>
      <UID>11</UID>
      <ID>11</ID>
      <Name>Development</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-01T08:00:00</Start>
      <Finish>2027-04-23T17:00:00</Finish>
      <Duration>PT320H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>240000</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
    </Task>
    <Task>
      <UID>12</UID>
      <ID>12</ID>
      <Name>Build the engineering prototype</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>900</Priority>
      <Start>2027-03-01T08:00:00</Start>
      <Finish>2027-04-08T17:00:00</Finish>
      <Duration>PT232H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>292800</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-03-01T08:00:00</ConstraintDate>
      <Notes>First integrated build. Expect it to fail somewhere useful; that is what it is for.</Notes>
    </Task>
    <Task>
      <UID>13</UID>
      <ID>13</ID>
      <Name>Design for manufacture and assembly</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-03-22T08:00:00</Start>
      <Finish>2027-04-16T17:00:00</Finish>
      <Duration>PT160H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>264000</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-03-22T08:00:00</ConstraintDate>
      <Notes>Rework the design for the production process, tolerances, and the assembly line that will actually build it.</Notes>
    </Task>
    <Task>
      <UID>14</UID>
      <ID>14</ID>
      <Name>Hold Gate 3, design freeze</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>900</Priority>
      <Start>2027-04-22T08:00:00</Start>
      <Finish>2027-04-23T17:00:00</Finish>
      <Duration>PT16H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>240000</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-04-22T08:00:00</ConstraintDate>
      <Notes>Freeze the design. Every change after this point goes through formal change control, priced and scheduled.</Notes>
    </Task>
    <Task>
      <UID>15</UID>
      <ID>15</ID>
      <Name>Gate 3, design freeze</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.4</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-23T08:00:00</Start>
      <Finish>2027-04-23T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>244800</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-04-23T08:00:00</ConstraintDate>
    </Task>
    <Task>
      <UID>16</UID>
      <ID>16</ID>
      <Name>Validation</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-26T08:00:00</Start>
      <Finish>2027-06-14T08:00:00</Finish>
      <Duration>PT280H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>72000</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
    </Task>
    <Task>
      <UID>17</UID>
      <ID>17</ID>
      <Name>Run verification and validation testing</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>900</Priority>
      <Start>2027-04-26T08:00:00</Start>
      <Finish>2027-05-28T17:00:00</Finish>
      <Duration>PT200H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>120000</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-04-26T08:00:00</ConstraintDate>
      <Notes>Test against the requirements written in concept, including the regulatory set. Record evidence as you go.</Notes>
    </Task>
    <Task>
      <UID>18</UID>
      <ID>18</ID>
      <Name>Complete the pilot production run</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-05-14T08:00:00</Start>
      <Finish>2027-06-07T17:00:00</Finish>
      <Duration>PT136H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>91200</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-05-14T08:00:00</ConstraintDate>
      <Notes>Build a small batch on production tooling to prove the process, not just the product.</Notes>
    </Task>
    <Task>
      <UID>19</UID>
      <ID>19</ID>
      <Name>Hold Gate 4, launch readiness</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>900</Priority>
      <Start>2027-06-11T08:00:00</Start>
      <Finish>2027-06-11T17:00:00</Finish>
      <Duration>PT8H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>72000</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-06-11T08:00:00</ConstraintDate>
      <Notes>Evidence pack reviewed, open defects triaged, and the launch date confirmed or moved on the facts.</Notes>
    </Task>
    <Task>
      <UID>20</UID>
      <ID>20</ID>
      <Name>Gate 4, launch readiness</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.4</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-06-14T08:00:00</Start>
      <Finish>2027-06-14T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>72000</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-06-14T08:00:00</ConstraintDate>
    </Task>
    <Task>
      <UID>21</UID>
      <ID>21</ID>
      <Name>Launch</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-06-15T08:00:00</Start>
      <Finish>2027-07-02T17:00:00</Finish>
      <Duration>PT112H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
    </Task>
    <Task>
      <UID>22</UID>
      <ID>22</ID>
      <Name>Ramp production and release to market</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>900</Priority>
      <Start>2027-06-15T08:00:00</Start>
      <Finish>2027-06-29T17:00:00</Finish>
      <Duration>PT88H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>14400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-06-15T08:00:00</ConstraintDate>
      <Notes>Scale the line, release channel inventory, and hand support the documentation they need on day one.</Notes>
    </Task>
    <Task>
      <UID>23</UID>
      <ID>23</ID>
      <Name>Run the post-launch review</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-06-29T08:00:00</Start>
      <Finish>2027-07-02T17:00:00</Finish>
      <Duration>PT32H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-06-29T08:00:00</ConstraintDate>
      <Notes>Actual cost against target, schedule against plan, and the gate decisions worth making differently.</Notes>
    </Task>
    <Task>
      <UID>24</UID>
      <ID>24</ID>
      <Name>Market launch</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-06-30T08:00:00</Start>
      <Finish>2027-06-30T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>14400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-06-30T08:00:00</ConstraintDate>
    </Task>
  </Tasks>
</Project>