<?xml version="1.0" encoding="UTF-8" standalone="yes"?>
<Project xmlns="http://schemas.microsoft.com/project">
  <SaveVersion>14</SaveVersion>
  <Name>RIBA Plan of Work (Architecture)</Name>
  <Title>RIBA Plan of Work (Architecture)</Title>
  <ScheduleFromStart>1</ScheduleFromStart>
  <StartDate>2027-01-04T08:00:00</StartDate>
  <FinishDate>2028-02-23T17:00:00</FinishDate>
  <CalendarUID>1</CalendarUID>
  <DefaultStartTime>08:00:00</DefaultStartTime>
  <DefaultFinishTime>17:00:00</DefaultFinishTime>
  <DurationFormat>7</DurationFormat>
  <NewTasksAreManual>0</NewTasksAreManual>
  <ProjectExternallyEdited>0</ProjectExternallyEdited>
  <Calendars>
    <Calendar>
      <UID>1</UID>
      <Name>Standard</Name>
      <IsBaseCalendar>1</IsBaseCalendar>
      <BaseCalendarUID>-1</BaseCalendarUID>
      <WeekDays>
        <WeekDay>
          <DayType>1</DayType>
          <DayWorking>0</DayWorking>
        </WeekDay>
        <WeekDay>
          <DayType>2</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>3</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>4</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>5</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>6</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>7</DayType>
          <DayWorking>0</DayWorking>
        </WeekDay>
      </WeekDays>
    </Calendar>
  </Calendars>
  <Tasks>
    <Task>
      <UID>1</UID>
      <ID>1</ID>
      <Name>Stage 0, Strategic Definition</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-04T08:00:00</Start>
      <Finish>2027-01-15T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>1382400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
    </Task>
    <Task>
      <UID>2</UID>
      <ID>2</ID>
      <Name>Confirm the business case and the outline brief</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>900</Priority>
      <Start>2027-01-04T08:00:00</Start>
      <Finish>2027-01-13T17:00:00</Finish>
      <Duration>PT64H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>1392000</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-01-04T08:00:00</ConstraintDate>
      <Notes>The client requirements, whether a building is the answer at all, and the outline project brief. Record the appointment scope and the fee basis alongside.</Notes>
    </Task>
    <Task>
      <UID>3</UID>
      <ID>3</ID>
      <Name>Agree the appointment and the fee schedule by stage</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>1.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-01-11T08:00:00</Start>
      <Finish>2027-01-15T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>1382400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-01-11T08:00:00</ConstraintDate>
      <Notes>Scope per stage, fee per stage as a share of the total, and what counts as an additional service. This is the record every later change is priced against.</Notes>
    </Task>
    <Task>
      <UID>4</UID>
      <ID>4</ID>
      <Name>Stage 1, Preparation and Briefing</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-18T08:00:00</Start>
      <Finish>2027-02-15T17:00:00</Finish>
      <Duration>PT168H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>1281600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
    </Task>
    <Task>
      <UID>5</UID>
      <ID>5</ID>
      <Name>Develop the project brief and the site information</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-01-18T08:00:00</Start>
      <Finish>2027-02-05T17:00:00</Finish>
      <Duration>PT120H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>1310400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-01-18T08:00:00</ConstraintDate>
      <Notes>Spatial requirements, quality and sustainability outcomes, site surveys and constraints, the planning context.</Notes>
    </Task>
    <Task>
      <UID>6</UID>
      <ID>6</ID>
      <Name>Prepare the project programme and procurement strategy</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-01-28T08:00:00</Start>
      <Finish>2027-02-05T17:00:00</Finish>
      <Duration>PT56H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>1310400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-01-28T08:00:00</ConstraintDate>
      <Notes>Stage durations, the procurement route, and the consultants the project needs and when.</Notes>
    </Task>
    <Task>
      <UID>7</UID>
      <ID>7</ID>
      <Name>Stage 1 client sign-off</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>900</Priority>
      <Start>2027-02-15T08:00:00</Start>
      <Finish>2027-02-15T17:00:00</Finish>
      <Duration>PT8H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>1281600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-02-15T08:00:00</ConstraintDate>
      <Notes>Brief and programme approved. The Stage 1 fee becomes invoiceable on sign-off.</Notes>
    </Task>
    <Task>
      <UID>8</UID>
      <ID>8</ID>
      <Name>Stage 1 sign-off, brief agreed</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>2.4</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-15T08:00:00</Start>
      <Finish>2027-02-15T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>1286400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-02-15T08:00:00</ConstraintDate>
    </Task>
    <Task>
      <UID>9</UID>
      <ID>9</ID>
      <Name>Stage 2, Concept Design</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-15T08:00:00</Start>
      <Finish>2027-04-12T17:00:00</Finish>
      <Duration>PT328H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>1089600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
    </Task>
    <Task>
      <UID>10</UID>
      <ID>10</ID>
      <Name>Prepare the concept design options</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>900</Priority>
      <Start>2027-02-15T08:00:00</Start>
      <Finish>2027-03-19T17:00:00</Finish>
      <Duration>PT200H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>1166400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-02-15T08:00:00</ConstraintDate>
      <Notes>Massing, layout and appearance options tested against the brief, with a preferred option recommended.</Notes>
    </Task>
    <Task>
      <UID>11</UID>
      <ID>11</ID>
      <Name>Coordinate the structural and services strategy</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-03-01T08:00:00</Start>
      <Finish>2027-03-26T17:00:00</Finish>
      <Duration>PT160H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>1142400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-03-01T08:00:00</ConstraintDate>
      <Notes>Outline structural and MEP strategies aligned with the architectural concept before it is fixed.</Notes>
    </Task>
    <Task>
      <UID>12</UID>
      <ID>12</ID>
      <Name>Prepare the Stage 2 cost plan and programme update</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-29T08:00:00</Start>
      <Finish>2027-04-07T17:00:00</Finish>
      <Duration>PT64H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>1104000</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-03-29T08:00:00</ConstraintDate>
      <Notes>Order-of-cost estimate against the budget; the programme re-baselined on the concept.</Notes>
    </Task>
    <Task>
      <UID>13</UID>
      <ID>13</ID>
      <Name>Stage 2 client sign-off</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.4</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>900</Priority>
      <Start>2027-04-12T08:00:00</Start>
      <Finish>2027-04-12T17:00:00</Finish>
      <Duration>PT8H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>1089600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-04-12T08:00:00</ConstraintDate>
      <Notes>Concept approved. Changes from here are priced and scheduled, never absorbed.</Notes>
    </Task>
    <Task>
      <UID>14</UID>
      <ID>14</ID>
      <Name>Stage 2 sign-off, concept approved</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>3.5</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-12T08:00:00</Start>
      <Finish>2027-04-12T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>1094400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-04-12T08:00:00</ConstraintDate>
    </Task>
    <Task>
      <UID>15</UID>
      <ID>15</ID>
      <Name>Stage 3, Spatial Coordination</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-12T08:00:00</Start>
      <Finish>2027-06-21T17:00:00</Finish>
      <Duration>PT408H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>849600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
    </Task>
    <Task>
      <UID>16</UID>
      <ID>16</ID>
      <Name>Develop the spatially coordinated design</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>900</Priority>
      <Start>2027-04-12T08:00:00</Start>
      <Finish>2027-05-31T17:00:00</Finish>
      <Duration>PT288H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>921600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-04-12T08:00:00</ConstraintDate>
      <Notes>Architectural, structural and services information coordinated in one model and clash-checked, with the planning drawings derived from it.</Notes>
    </Task>
    <Task>
      <UID>17</UID>
      <ID>17</ID>
      <Name>Prepare and submit the planning application</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-05-24T08:00:00</Start>
      <Finish>2027-06-11T17:00:00</Finish>
      <Duration>PT120H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>878400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-05-24T08:00:00</ConstraintDate>
      <Notes>Planning drawings, the design and access statement, supporting reports; submitted and validated.</Notes>
    </Task>
    <Task>
      <UID>18</UID>
      <ID>18</ID>
      <Name>Stage 3 client sign-off</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>900</Priority>
      <Start>2027-06-21T08:00:00</Start>
      <Finish>2027-06-21T17:00:00</Finish>
      <Duration>PT8H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>849600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-06-21T08:00:00</ConstraintDate>
      <Notes>Coordinated design approved and the planning application submitted.</Notes>
    </Task>
    <Task>
      <UID>19</UID>
      <ID>19</ID>
      <Name>Stage 3 sign-off, planning submitted</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>4.4</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-06-21T08:00:00</Start>
      <Finish>2027-06-21T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>854400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-06-21T08:00:00</ConstraintDate>
    </Task>
    <Task>
      <UID>20</UID>
      <ID>20</ID>
      <Name>Stage 4, Technical Design</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-06-21T08:00:00</Start>
      <Finish>2027-09-27T17:00:00</Finish>
      <Duration>PT568H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>513600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
    </Task>
    <Task>
      <UID>21</UID>
      <ID>21</ID>
      <Name>Produce the technical design</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>900</Priority>
      <Start>2027-06-21T08:00:00</Start>
      <Finish>2027-08-27T17:00:00</Finish>
      <Duration>PT400H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>614400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-06-21T08:00:00</ConstraintDate>
      <Notes>Construction-level information: details, specifications and schedules, coordinated with every designer.</Notes>
    </Task>
    <Task>
      <UID>22</UID>
      <ID>22</ID>
      <Name>Discharge the pre-commencement planning conditions</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-08-12T08:00:00</Start>
      <Finish>2027-09-10T17:00:00</Finish>
      <Duration>PT176H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>566400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-08-12T08:00:00</ConstraintDate>
      <Notes>The conditions that gate a start on site, tracked to discharge.</Notes>
    </Task>
    <Task>
      <UID>23</UID>
      <ID>23</ID>
      <Name>Prepare the tender documentation and run the tender</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-08-30T08:00:00</Start>
      <Finish>2027-09-24T17:00:00</Finish>
      <Duration>PT160H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>518400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-08-30T08:00:00</ConstraintDate>
      <Notes>Pricing documents, the tender period, returns analysed and a contractor recommended.</Notes>
    </Task>
    <Task>
      <UID>24</UID>
      <ID>24</ID>
      <Name>Stage 4 client sign-off and contract award</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5.4</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>900</Priority>
      <Start>2027-09-27T08:00:00</Start>
      <Finish>2027-09-27T17:00:00</Finish>
      <Duration>PT8H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>513600</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-09-27T08:00:00</ConstraintDate>
      <Notes>Technical design complete and the contractor appointed. The construction-stage fee starts here.</Notes>
    </Task>
    <Task>
      <UID>25</UID>
      <ID>25</ID>
      <Name>Stage 4 sign-off, contract awarded</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>5.5</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-09-27T08:00:00</Start>
      <Finish>2027-09-27T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>518400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-09-27T08:00:00</ConstraintDate>
    </Task>
    <Task>
      <UID>26</UID>
      <ID>26</ID>
      <Name>Stage 5, Manufacturing and Construction</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>6</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-09-27T08:00:00</Start>
      <Finish>2028-01-17T08:00:00</Finish>
      <Duration>PT640H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>134400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
    </Task>
    <Task>
      <UID>27</UID>
      <ID>27</ID>
      <Name>Administer the building contract</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>6.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>900</Priority>
      <Start>2027-09-27T08:00:00</Start>
      <Finish>2028-01-07T17:00:00</Finish>
      <Duration>PT600H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>158400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-09-27T08:00:00</ConstraintDate>
      <Notes>Site inspections, instructions, valuations and certificates through construction.</Notes>
    </Task>
    <Task>
      <UID>28</UID>
      <ID>28</ID>
      <Name>Respond to contractor queries and design changes</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>6.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2027-10-01T08:00:00</Start>
      <Finish>2028-01-07T17:00:00</Finish>
      <Duration>PT568H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>158400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2027-10-01T08:00:00</ConstraintDate>
      <Notes>Queries answered, changes assessed for cost and programme, and instructed formally.</Notes>
    </Task>
    <Task>
      <UID>29</UID>
      <ID>29</ID>
      <Name>Inspect and certify practical completion</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>6.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>900</Priority>
      <Start>2028-01-11T08:00:00</Start>
      <Finish>2028-01-14T17:00:00</Finish>
      <Duration>PT32H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>134400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2028-01-11T08:00:00</ConstraintDate>
      <Notes>Snagging, the completion inspection and the certificate.</Notes>
    </Task>
    <Task>
      <UID>30</UID>
      <ID>30</ID>
      <Name>Practical completion</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>6.4</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2028-01-17T08:00:00</Start>
      <Finish>2028-01-17T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>134400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2028-01-17T08:00:00</ConstraintDate>
    </Task>
    <Task>
      <UID>31</UID>
      <ID>31</ID>
      <Name>Stage 6, Handover</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>7</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2028-01-17T08:00:00</Start>
      <Finish>2028-02-14T08:00:00</Finish>
      <Duration>PT160H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>0</Critical>
      <TotalSlack>38400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
    </Task>
    <Task>
      <UID>32</UID>
      <ID>32</ID>
      <Name>Hand over the building and plan the defects period</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>7.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2028-01-17T08:00:00</Start>
      <Finish>2028-02-04T17:00:00</Finish>
      <Duration>PT120H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>62400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2028-01-17T08:00:00</ConstraintDate>
      <Notes>The building manual, as-built information and the defects inspection schedule.</Notes>
    </Task>
    <Task>
      <UID>33</UID>
      <ID>33</ID>
      <Name>Issue the final account and close the appointment</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>7.2</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>700</Priority>
      <Start>2028-02-04T08:00:00</Start>
      <Finish>2028-02-11T17:00:00</Finish>
      <Duration>PT48H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>38400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2028-02-04T08:00:00</ConstraintDate>
      <Notes>Final certificate, final account, and the fee reconciled against the stage schedule.</Notes>
    </Task>
    <Task>
      <UID>34</UID>
      <ID>34</ID>
      <Name>Handover complete</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>7.3</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2028-02-14T08:00:00</Start>
      <Finish>2028-02-14T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <Critical>0</Critical>
      <TotalSlack>38400</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2028-02-14T08:00:00</ConstraintDate>
    </Task>
    <Task>
      <UID>35</UID>
      <ID>35</ID>
      <Name>Stage 7, Use</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>8</OutlineNumber>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2028-02-14T08:00:00</Start>
      <Finish>2028-02-23T17:00:00</Finish>
      <Duration>PT64H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>0</ConstraintType>
    </Task>
    <Task>
      <UID>36</UID>
      <ID>36</ID>
      <Name>Plan the post-occupancy evaluation</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineNumber>8.1</OutlineNumber>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2028-02-14T08:00:00</Start>
      <Finish>2028-02-23T17:00:00</Finish>
      <Duration>PT64H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <Critical>1</Critical>
      <TotalSlack>0</TotalSlack>
      <PercentComplete>0</PercentComplete>
      <ConstraintType>4</ConstraintType>
      <ConstraintDate>2028-02-14T08:00:00</ConstraintDate>
      <Notes>What will be measured a year in, by whom, and how the lessons feed the next brief.</Notes>
    </Task>
  </Tasks>
</Project>