Free template

Free Agile Project Management Template

A nine-week agile project: a short sprint 0 to write the vision, build the first backlog and agree the definition of done, three two-week sprints with planning, delivery and a review and retrospective, then a release sprint to harden, ship and refine the backlog for what comes next.

No credit card. Import the spreadsheet as a new project on the Free plan.

The spreadsheet is a 17-task plan with phases, durations and milestones, ready for Excel or Google Sheets. It carries no dates, so set your own start, or paste it into the Gantt chart generator to have the schedule built for you. Want to compare the plans side by side first? Every one of them is on the project plan template page, with the rows shown before you download.

What’s inside

All 17 tasks are below, from the product vision to the release review, each with its description, duration and priority. The three sprints repeat on purpose: planning, delivery, review and retrospective, every two weeks.

17

Scheduled tasks

5

Phases

5

Milestones

~9

Weeks end to end

Agile still has a plan, just a shorter one

Agile teams plan constantly; they just commit to less at a time. This template shows that shape: the dates are fixed in two-week boxes, the scope inside each box is decided at its planning meeting, and every sprint ends with something shown to the people who asked for it. The backlog items are not listed here because they are yours, so each sprint carries one delivery task to rename or split into your stories.

Sprint 0 is short and earns its place. A vision the team can repeat, a first backlog ranked by value, a definition of done everyone signs up to and a board set up before sprint 1 save the first real sprint from being spent arguing about how to work. The release sprint at the end is the same idea from the other side: hardening and release get their own time instead of being squeezed into the last afternoon.

In the spreadsheet each sprint is a phase, so the file reads as a sprint plan in Excel or Sheets. Onplana has real sprints with a board and a backlog on the Professional plan and up, which is the better home once the stories are written; the agile project management page shows how that works.

The plan, phase by phase

Sprint 0: Set Up4 tasks

Write the product vision and goals

Who it is for, the problem it solves and how you will know it worked, in a paragraph the team can repeat.

3 daysHigh

Build and rank the first backlog

The work written as user stories, ranked by value, with the top items small enough for one sprint.

5 daysCritical

Agree the definition of done

The checks every item passes before it counts as done: reviewed, tested, documented, deployable.

1 dayHigh

Set up the board and the working agreement

The board columns, sprint length, meeting times and how the team handles interruptions.

2 daysMedium

Sprint 13 tasks

Plan sprint 1

Pick the top backlog items the team can finish in two weeks and agree the sprint goal.

1 dayHigh

Build the sprint 1 backlog items

Rename or split this into the stories chosen at planning. Each one meets the definition of done.

12 daysCritical

Hold the sprint 1 review and retrospective

Show the working result to stakeholders, then agree one thing the team will do better next sprint.

1 dayMedium

Sprint 23 tasks

Plan sprint 2

Re-rank the backlog with what sprint 1 taught you, then commit to the next sprint goal.

1 dayHigh

Build the sprint 2 backlog items

Rename or split this into the stories chosen at planning. Each one meets the definition of done.

12 daysCritical

Hold the sprint 2 review and retrospective

Show the result, collect feedback into the backlog, and check last sprint's improvement happened.

1 dayMedium

Sprint 33 tasks

Plan sprint 3

Use the team's velocity from two sprints to commit to a goal it can actually finish.

1 dayHigh

Build the sprint 3 backlog items

Rename or split this into the stories chosen at planning. Each one meets the definition of done.

12 daysCritical

Hold the sprint 3 review and retrospective

Show the result and decide with the product owner what must be in the release.

1 dayMedium

Release Sprint4 tasks

Plan the release sprint

Agree what ships, what waits, and the checks the release must pass.

1 dayHigh

Harden, test and fix

End-to-end testing, performance and security checks, and fixes, with no new features added.

8 daysHigh

Release to customers

Ship, announce and watch the first hours closely, with a way back ready.

1 dayCritical

Review the release and refine the backlog

What customers did with it, what the team learned, and a re-ranked backlog for the next cycle.

2 daysMedium

Milestones

Five milestones: the backlog ready at the end of sprint 0, the end of each of the three sprints, and the release. On a Gantt chart they are the heartbeat of the project, evenly spaced every two weeks.

Backlog ready

Day 9 of the plan

Sprint 1 done

Day 24 of the plan

Sprint 2 done

Day 38 of the plan

Sprint 3 done

Day 52 of the plan

Released

Day 62 of the plan

Frequently asked

What is in the download?

A CSV file with the 17 tasks, one sprint per phase, each with its duration in days, priority and notes, and the five milestones as zero-day rows. Excel opens it directly and Google Sheets imports it.

Why are there no user stories in it?

Because they are yours, and a template full of someone else's stories is a list to delete. Each sprint has one delivery task to rename or split into the stories chosen at its planning meeting. Sprint 0 is where the first backlog gets written.

Can I change the sprint length?

Yes. Two weeks is the most common length, and the template uses it. For one-week sprints halve the delivery tasks; for three-week sprints add a week to each. Keep the length the same from sprint to sprint, or velocity stops meaning anything.

Is this Scrum?

It follows the Scrum rhythm of planning, delivery, review and retrospective, and adds a sprint 0 and a release sprint, which many teams use and Scrum itself does not require. If your team runs Kanban, keep sprint 0 and the release work and drop the sprint boundaries.

Start with the plan already built

Import the Agile Project spreadsheet into a free Onplana project and your phases, tasks, and milestones are scheduled from the start date you pick. No credit card, no time limit.