Insights
What uploaded project schedules show
People check and open schedules with our free tools. These reports count what those schedules have in common, such as how many fail a DCMA check. We read counts only, never file, task or company names, and a figure from fewer than 20 schedules is never published.
Schedule risk
11% of schedules run through the free Schedule Risk Analyzer have at least even odds of finishing by their planned date
Through November 29, 2026 · n = 2,369
n counts runs of the free Schedule Risk Analyzer.
Read the reportWhat the Schedule Health Check finds
63% of schedules uploaded to our free tools have at least one task with no links in or out
Through November 29, 2026 · n = 2,107
n counts schedules through the Schedule Health Check's analyzers.
Read the reportMicrosoft Project versus Primavera
Microsoft Project files make up 85% of uploaded schedules, and Primavera files 9%
Through November 29, 2026 · n = 1,961
n counts uploads whose format was recorded.
Read the reportSchedules by plan size
38% of uploaded schedules have 50 to 199 tasks
Through November 29, 2026 · n = 1,961
n counts uploads with a recorded task count.
Read the reportSchedule health report
100% of plans checked against the 14 DCMA points fail at least one
Through November 29, 2026 · n = 69
n counts plans checked against the 14 DCMA points in Onplana Schedule and the MPP viewer.
Read the reportDCMA checks one by one
80% of plans checked against the 14 DCMA points fail the check for missing logic links
Through November 29, 2026 · n = 40
n counts plans checked one DCMA point at a time in Onplana Schedule and the MPP viewer.
Read the report
Still collecting data: Quarter on quarter (1 of 2 full quarters). Each is published once its figures stand on at least 20 schedules.
How we count
Each report counts its own group, so the n differ: schedules uploaded to the free tools, plans checked against the 14 DCMA points in Onplana Schedule and the MPP viewer, or runs of the Schedule Risk Analyzer. Every card names the group its n counts.
How we counted: free and anonymous uploads to the Schedule Health Check, the MPP viewer, Onplana Schedule and the Schedule Risk Analyzer. Paying customers’ plans are never included. We read counts only, never file, task or company names. Any figure from fewer than 20 schedules is left out. Read the Privacy Policy section.
Check your own schedule freeCite this data
Devsoft Solutions (2026). Onplana schedule-quality benchmark (Version 2026-Q4) [Data set]. Zenodo. https://doi.org/10.5281/zenodo.23570197
The 2026-Q4 release is a snapshot of October 22, 2026, under CC BY 4.0. The DOI above always resolves to the latest published quarter; the pages here keep updating as uploads arrive. Download the dataset