Schedule riskThrough October 17, 2026

6% of schedules run through the free Schedule Risk Analyzer have at least even odds of finishing by their planned date

Of 230 free and anonymous schedules simulated. At least even odds means the P50 finish, the day half the runs finish by, falls on or before the finish the file states.

  • 6%

    P50 on or before the planned finish

    n = 230

  • 6%

    P80 on or before the planned finish

    n = 230

  • 12 days

    Typical P50 slip past the planned finish

    n = 230

  • 18 days

    Typical P80 slip past the planned finish

    n = 230

  • 8%

    Typical P80 slip, as a share of the planned duration

    n = 229

  • 11 days

    Typical uncertainty band, P10 to P90

    n = 230

  • 4%

    Typical uncertainty band, as a share of the planned duration

    n = 229

Slip is counted in calendar days from the planned finish (the finish the file states, or the finish its links give when it states none) to the simulated date. The uncertainty band runs from P10, the day one run in ten beats, to P90. A share of the planned duration counts from the project start to the planned finish.

Risk by plan size

Grouped by the number of tasks the simulation varied, in bands, never exact sizes.

GroupP50 on timeTypical P80 slipTypical P10 to P90 band
1 to 49 tasks4% n = 7913 d n = 7910 d n = 79
50 to 199 tasks9% n = 8819 d n = 8810 d n = 88
200 to 999 tasks6% n = 5224 d n = 5210 d n = 52

Risk by near-critical tasks

A near-critical task is on the critical path in at least 20% and under 80% of runs. The more of them, the more paths can take over the finish.

GroupP50 on timeTypical P80 slipTypical P10 to P90 band
No near-critical tasks7% n = 12413 d n = 1248 d n = 124
1 to 4 near-critical tasks8% n = 5011 d n = 5012 d n = 50
5 to 19 near-critical tasks6% n = 3223 d n = 3213 d n = 32
20 or more near-critical tasks0% n = 2451 d n = 2419 d n = 24

Risk by merge points

A merge point is a task waiting on two or more others, where a late input delays it whichever one runs over.

GroupP50 on timeTypical P80 slipTypical P10 to P90 band
No merge points5% n = 868 d n = 868 d n = 86
1 to 9 merge points3% n = 3615 d n = 367 d n = 36
10 to 49 merge points9% n = 5822 d n = 5814 d n = 58
50 or more merge points8% n = 5065 d n = 5015 d n = 50

Quality meets risk: missing links

Plans with tasks that have no links against plans where every task is linked. A task with no links cannot push anything later, so a narrow band on such a plan can be certainty it has not earned.

GroupP50 on timeTypical P80 slipTypical P10 to P90 band
Every task linked6% n = 19722 d n = 19712 d n = 197
Some tasks with no links9% n = 334 d n = 334 d n = 33

What drives the finish

Of the five tasks whose duration moves each plan's finish the most, pooled across plans, the share in each group by how often the task was critical.

  • Critical in 80% of runs or more53%
    n = 1,126
  • Near-critical (critical in 20% to 79% of runs)15%
    n = 1,126
  • Off the critical path (under 20% of runs)32%
    n = 1,126

How we counted: free and anonymous uploads to the Schedule Health Check, the MPP viewer, Onplana Schedule and the Schedule Risk Analyzer. Paying customers’ plans are never included. We read counts only, never file, task or company names. Any figure from fewer than 20 schedules is left out. Read the Privacy Policy section.