Free RIBA Plan of Work Project Template

Architecture practices lose fees between stages, not inside them: the concept change reworked into Stage 3 without a variation, the construction-stage hours that outrun the Stage 5 share. This template lays the RIBA Plan of Work 2020 out as eight phases with a sign-off at the end of each, so the fee schedule, the programme and the hours are one record from Stage 0 to handover.

No credit card. Opens as a real project on the Free plan.

What’s inside

All 22 tasks are below, across Stages 0 to 7. Each stage ends in a short client sign-off task, because the sign-off is where the fee becomes invoiceable and where the scope stops moving for free.

22

Scheduled tasks

8

Phases

6

Milestones

~60

Weeks end to end

Why the stage sign-off is the unit that matters

The RIBA Plan of Work is a sequence of decisions, and each stage ends with one: the client approves the brief, the concept, the coordinated design, the technical design. A practice that treats those sign-offs as the moments its fee becomes invoiceable, and its scope becomes fixed, keeps two things straight that otherwise drift: what has been paid for, and what has been agreed. This template puts a milestone at each of them.

Every task carries estimated hours because that is how the phase gets measured. Progress on a stage is the share of its estimate that has been approved on timesheets, so a Stage 3 that has consumed 80 percent of its hours at 40 percent of its deliverables is visible in the week it happens rather than at the fee reconciliation. The estimates are a starting shape for a mid-sized project; resize them once the appointment is agreed.

Fees are quoted per stage, as the RIBA appointment expects. In Onplana that is one milestone line per stage on the deal, which becomes the project's milestone schedule and is recognised as each sign-off completes, and it is why the sign-offs are milestones rather than tasks. What the template does not do is invoice: the invoice and the ledger posting still happen in your accounting system.

The plan, phase by phase

Stage 0, Strategic Definition2 tasks

Confirm the business case and the outline brief

The client requirements, whether a building is the answer at all, and the outline project brief. Record the appointment scope and the fee basis alongside.

10 daysCritical

Agree the appointment and the fee schedule by stage

Scope per stage, fee per stage as a share of the total, and what counts as an additional service. This is the record every later change is priced against.

9 daysHigh

Stage 1, Preparation and Briefing3 tasks

Develop the project brief and the site information

Spatial requirements, quality and sustainability outcomes, site surveys and constraints, the planning context.

20 daysHigh

Prepare the project programme and procurement strategy

Stage durations, the procurement route, and the consultants the project needs and when.

10 daysHigh

Stage 1 client sign-off

Brief and programme approved. The Stage 1 fee becomes invoiceable on sign-off.

2 daysCritical

Stage 2, Concept Design4 tasks

Prepare the concept design options

Massing, layout and appearance options tested against the brief, with a preferred option recommended.

35 daysCritical

Coordinate the structural and services strategy

Outline structural and MEP strategies aligned with the architectural concept before it is fixed.

28 daysHigh

Prepare the Stage 2 cost plan and programme update

Order-of-cost estimate against the budget; the programme re-baselined on the concept.

10 daysMedium

Stage 2 client sign-off

Concept approved. Changes from here are priced and scheduled, never absorbed.

2 daysCritical

Stage 3, Spatial Coordination3 tasks

Develop the spatially coordinated design

Architectural, structural and services information coordinated in one model and clash-checked, with the planning drawings derived from it.

50 daysCritical

Prepare and submit the planning application

Planning drawings, the design and access statement, supporting reports; submitted and validated.

20 daysHigh

Stage 3 client sign-off

Coordinated design approved and the planning application submitted.

2 daysCritical

Stage 4, Technical Design4 tasks

Produce the technical design

Construction-level information: details, specifications and schedules, coordinated with every designer.

70 daysCritical

Discharge the pre-commencement planning conditions

The conditions that gate a start on site, tracked to discharge.

30 daysHigh

Prepare the tender documentation and run the tender

Pricing documents, the tender period, returns analysed and a contractor recommended.

28 daysHigh

Stage 4 client sign-off and contract award

Technical design complete and the contractor appointed. The construction-stage fee starts here.

2 daysCritical

Stage 5, Manufacturing and Construction3 tasks

Administer the building contract

Site inspections, instructions, valuations and certificates through construction.

105 daysCritical

Respond to contractor queries and design changes

Queries answered, changes assessed for cost and programme, and instructed formally.

100 daysHigh

Inspect and certify practical completion

Snagging, the completion inspection and the certificate.

6 daysCritical

Stage 6, Handover2 tasks

Hand over the building and plan the defects period

The building manual, as-built information and the defects inspection schedule.

20 daysHigh

Issue the final account and close the appointment

Final certificate, final account, and the fee reconciled against the stage schedule.

10 daysHigh

Stage 7, Use1 task

Plan the post-occupancy evaluation

What will be measured a year in, by whom, and how the lessons feed the next brief.

10 daysMedium

Milestones

Six milestones: four stage sign-offs, practical completion and handover. They render as diamonds on the Gantt chart, which makes the gap between the Stage 4 sign-off and practical completion, the part of the fee most exposed to contractor performance, visible at a glance.

Stage 1 sign-off, brief agreed

Day 42 of the plan

Stage 2 sign-off, concept approved

Day 98 of the plan

Stage 3 sign-off, planning submitted

Day 168 of the plan

Stage 4 sign-off, contract awarded

Day 266 of the plan

Practical completion

Day 378 of the plan

Handover complete

Day 406 of the plan

Frequently asked

Is this the 2020 Plan of Work or the 2013 one?

The 2020 edition: Stage 3 is Spatial Coordination rather than Developed Design, Stage 5 is Manufacturing and Construction, and the sustainability and planning tasks sit where the 2020 Plan puts them. Rename a stage if your appointment still uses 2013 wording; the structure is the same.

How do I quote a fee per stage?

On the deal, add one milestone line per stage with its share of the fee, send it as the quote, and when the client accepts it the lines become the project's milestone schedule. Each amount is recognised when its sign-off milestone completes, so the margin report shows stage revenue against the hours that earned it.

Where do the customary percentages per stage come from?

From practice rather than from a rule: Stages 2 to 5 carry most of the fee and Stage 4 is usually the largest single share. The template names the sign-offs and leaves the split to your appointment, because it varies by procurement route and by client.

How is progress on a stage measured?

By hours. Each stage's progress is the share of its estimate that has been approved on timesheets, and a project manager can override it with a percentage when the hours and the deliverables disagree. That is why every task in the template carries an estimate.

We are migrating from Microsoft Project. Do our stages become these phases?

A migrated schedule arrives with its stages as summary tasks, and Onplana imports them intact with dependencies, baselines and costs. Use this template for new appointments; an imported plan keeps its own structure.

Start with the plan already built

Open the RIBA Plan of Work (Architecture) template free and your phases, tasks, and milestones are scheduled before the kickoff meeting. No credit card, no time limit.