WBS generator
Type or paste the deliverables of your project and indent each one under the one it belongs to. The work breakdown structure is numbered 1, 1.1, 1.1.1 as you go, and downloads as a CSV for Excel or as Project XML.
The numbers and the files are made in this browser; nothing you type is sent anywhere. Start from one of the examples or clear it and type your own.
Import the CSV into a free Onplana workspace and the tree arrives with its WBS numbers, ready for dates and links (how the import reads a WBS). Or open the Project XML in Onplana Schedule, the free Windows and Mac app, or in Microsoft Project.
Work breakdown structure template
An office fit-out broken down into four deliverables and their work packages. Download it as a work breakdown structure template for Excel, or as Project XML; the generator above opens with the same tree.
| WBS | Deliverable or work package | Days |
|---|---|---|
| 1 | Design | |
| 1.1 | Site survey report | 3 |
| 1.2 | Space plan | 5 |
| 1.3 | Approved design package | 4 |
| 2 | Building works | |
| 2.1 | Partitions and ceilings | 10 |
| 2.2 | Electrical installation | 8 |
| 2.3 | Data cabling | 5 |
| 2.4 | Finishes and decoration | 6 |
| 3 | Furniture and equipment | |
| 3.1 | Furniture order | 2 |
| 3.2 | Installed furniture | 3 |
| 3.3 | Configured meeting rooms | 2 |
| 4 | Handover | |
| 4.1 | Snagging list closed | 3 |
| 4.2 | Operation and maintenance manual | 2 |
| 4.3 | Move-in plan | 1 |
How to read a work breakdown structure
A WBS breaks the project down by what it delivers. The top level is the main deliverables; each is split into the smaller deliverables that make it up, down to work packages: pieces small enough to estimate, give to one owner and track. The numbers say where each piece sits, so 2.3 is the third piece of the second deliverable.
The 100 percent rule keeps it honest: the children of every item add up to all of that item's work, no more and no less. Write each item as a noun, the thing handed over, and keep the verbs for the schedule, where each work package becomes the tasks that produce it.
For where work packages and control accounts sit in cost control, read work packages and control accounts; for building one step by step, the work breakdown structure guide. Once the WBS has durations and links, the critical path calculator finds which work packages set the finish date.
Updated .
Frequently asked questions
What is a WBS generator?
A tool that turns a list of deliverables into a numbered work breakdown structure. Here you type or paste the items, indent each one under the deliverable it belongs to, and the WBS numbers (1, 1.1, 1.1.1) follow as you go. Download it as a CSV for Excel or as Project XML.
Is this WBS generator free?
Yes, with no account and nothing to install. Build the structure, then download the CSV or the Project XML.
Is what I type uploaded?
No. The numbers and both files are made in your browser. Nothing you type is sent to Onplana.
Can I paste an outline from Word, Excel or a list?
Yes. Open Paste an outline and paste one item per line. Indent with tabs or spaces, or start each line with its number (1, 1.1, 1.1.1); list bullets are removed. After a tab you can add the working days and a note.
Is there a work breakdown structure template in Excel?
Yes. The template below downloads as a CSV that Excel opens, with the columns Level, WBS, Task Name, Duration and Notes. Change it in Excel, or load it here, change it and download it again.
What is the 100 percent rule?
The children of every item add up to all of that item's work, no more and no less, and the top level adds up to the whole project. Nothing is left out and nothing is counted twice.
Should a WBS list deliverables or tasks?
Deliverables: what the project hands over, written as nouns ("Site survey report"). The tasks that produce them belong in the schedule. The lowest items, the work packages, are small enough to estimate and give to one owner.
Can I turn the WBS into a schedule?
Yes. Import the CSV into a free Onplana workspace, and the tree arrives with its WBS numbers, ready for dates and links. Or open the Project XML in Onplana Schedule, the free Windows and Mac app, or in Microsoft Project.