Type the deadline, then the tasks, how long each takes and what each one waits for. You get the date every task must start and finish to make the deadline, worked backward, with the day the work must begin.

How it counts: durations and lags are working days, Monday to Friday; the last task finishes on your deadline and every task sits as late as it can; links are finish to start unless you type SS, FF or SF. The plan is worked out in this browser.

Loading the workback schedule…

Download the table as CSV under the results, and the chart as a PNG or a PDF with the diagram's Export PNG and Export PDF buttons. Save as Project XML keeps the plan you typed: import it into a free Onplana workspace, or open it in Onplana Schedule, the free Windows and Mac app, to keep editing it.

What is a workback schedule?

A workback schedule starts from the date that cannot move, a launch, an event, a submission or a handover, and works backward to today. The last task finishes on the deadline. Each task before it has to finish by the time the tasks that wait for it start, so you read the plan from the end: the day each task must start, and the day the whole job must begin.

Every task here sits at its latest safe start, the latest day it can begin and still let the deadline hold. That is what makes the plan honest: there is no hidden spare time, so a day lost on any task is a day lost on the deadline, and you know it the day it happens.

When does planning backward beat planning forward?

  • When the date is fixed and the start is the question: an event with a booked venue, a launch with an announced date, a bid or a grant with a closing day.
  • When starting too early costs something: catering ordered before the numbers are in, print run before the speakers are confirmed, stock bought months before it is needed.
  • When you need to know if the plan fits at all. Planning forward tells you when you would finish; planning backward tells you whether you have already missed the day to start.

Plan forward instead when the start is fixed and the finish is the question. The PERT chart maker does that with the same table, and the critical path calculator shows how much each task can slip.

A worked example

Four tasks and a deadline of Friday, November 13, 2026: A takes 3 days; B takes 2 days and C takes 4, both after A; D takes 2 days after both B and C. Worked backward, D runs Thursday and Friday, C must finish the Wednesday before, and A the Thursday before C starts. B is shorter than C, so it sits as late as it can, against D.

The four-task example worked back from Friday, November 13, 2026
TaskDaysLatest safe startFinish by
A3Tue, Nov 3Thu, Nov 5
B2Tue, Nov 10Wed, Nov 11
C4Fri, Nov 6Wed, Nov 11
D2Thu, Nov 12Fri, Nov 13

The work must begin on Tuesday, November 3: 9 working days. Clear the table and type the four tasks with that deadline to check it.

Updated .

Frequently asked questions

What is a workback schedule?

A plan built backward from a date that cannot move. You start with the deadline, list the tasks that must be done before it, and work out from the last task back to the first when each one has to start. The answer is the latest safe start of every task and the day the work must begin.

How do you make a workback schedule?

Write the deadline, then each task with its duration in working days and the tasks it waits for. The last task finishes on the deadline; each task before it must finish by the time the tasks after it start. Here that is done for you as you type, and a task that runs beside a longer one is placed as late as it can go.

Is this workback schedule maker free?

Yes. Type the plan, read the dates, and download the table as CSV and the chart as a PNG or a PDF, with no account and nothing to install.

Is what I type sent anywhere?

No. The plan is scheduled in your browser, and the CSV, the picture, the PDF and the Project XML are made there too. Nothing you type is sent to Onplana.

What if my deadline falls on a weekend?

The tool counts Monday to Friday as working days and asks for a weekday deadline. It will not quietly move your date to the Friday before, because a deadline that moved without you knowing is the mistake a workback schedule exists to prevent.

What if the start date is already past?

Then the plan does not fit before the deadline. The tool says so under the date. Shorten a task, or let more of them run side by side, and the start moves later.

Can I keep working on the plan?

Yes. Save it as Project XML and open it in Onplana Schedule, the free Windows and Mac app, or import it into a free Onplana workspace, where your team works the plan together. The file keeps every task as late as possible, the way Microsoft Project writes it.