Critical path calculator
Type your activities, their durations and what each one waits for. The calculator runs the forward and backward pass as you type and gives the early and late start and finish, the total float and the critical path, as a table and as a network diagram.
How it counts: durations and lags are working days, Monday to Friday; the plan starts today (or on Monday, at a weekend), as day 0; links are finish to start unless you type SS, FF or SF. What you type is calculated in this browser and is not sent anywhere.
Save as Project XML keeps the plan you typed: import it into a free Onplana workspace, or open it in Onplana Schedule, the free Windows and Mac app, to keep editing it. Have a Microsoft Project or Primavera file already? The free MPP viewer shows its critical path.
How does the critical path calculator work?
It uses the critical path method (CPM). The forward pass starts at day 0 and gives each activity its early start, the latest early finish among its predecessors, and its early finish, the early start plus the duration. The backward pass starts from the project finish and gives each activity its late finish, the earliest late start among its successors, and its late start, the late finish less the duration.
Total float is the difference between the late and early start. An activity with zero total float is critical: a day lost on it is a day lost on the project, and the critical activities in order are the critical path. The scheduling is Onplana Schedule's own engine, the same one that schedules a plan in the desktop app.
A worked example
Four activities: A takes 3 days; B takes 2 days and C takes 4, both after A; D takes 2 days after both B and C. Clear the table and type them to check the answer.
| Activity | Days | ES | EF | LS | LF | Total float | Critical |
|---|---|---|---|---|---|---|---|
| A | 3 | 0 | 3 | 0 | 3 | 0 | Yes |
| B | 2 | 3 | 5 | 5 | 7 | 2 | No |
| C | 4 | 3 | 7 | 3 | 7 | 0 | Yes |
| D | 2 | 7 | 9 | 7 | 9 | 0 | Yes |
The critical path is A, C, D, 9 working days. B can slip 2 days before it holds up D.
Critical path table or network diagram?
The table gives the numbers; the network diagram beside it shows the same answer as boxes joined by their links, with the critical activities in red. To draw and export the diagram on its own, use the PERT chart maker. For the method itself, with a longer example and the mistakes that break the path, read what the critical path is. The table shows total float only; how it differs from free float is in total float and free float. For constraints, calendars and a whole plan on the same engine, see critical path method software.
Updated .
Frequently asked questions
How do you calculate the critical path?
With two passes over the network. The forward pass gives each activity its early start (the latest early finish of its predecessors) and its early finish (early start plus duration). The backward pass, from the project finish, gives its late finish (the earliest late start of its successors) and its late start (late finish minus duration). Total float is late start minus early start, and the activities with zero total float form the critical path.
Is this critical path calculator free?
Yes. Type the activities, read the table and the network diagram, and export the diagram as a PNG or a PDF, with no account and nothing to install.
Is what I type uploaded?
No. The table is scheduled and the results are calculated in your browser, and the picture, the PDF and the Project XML are made there too. Nothing you type is sent to Onplana.
What do ES, EF, LS and LF mean?
ES is the early start and EF the early finish: the soonest an activity can begin and end. LS is the late start and LF the late finish: the latest it can begin and end without moving the project finish. Here they are working days counted from day 0, the project start, so EF is ES plus the duration.
Can I use start-to-start links, lags and leads?
Yes. Predecessors are finish to start unless you type SS, FF or SF after the row number, and a lag is written in working days: 3SS+2d starts two days after row 3 starts, and 2-1d starts one day before row 2 finishes.
Does it show free float?
No. The table shows total float, how many working days an activity can slip before it moves the project finish. Free float, how far it can slip before it moves the next activity, is not calculated here.
Can I find the critical path of a Microsoft Project or Primavera file?
Yes, in the free MPP viewer: open your .mpp, Project XML or .xer file and tick View, Critical path to see the chain that sets your finish date.
Can I keep working on the plan?
Yes. Save it as Project XML and open it in Onplana Schedule, the free Windows and Mac app, or import it into a free Onplana workspace, where your team plans together on the Gantt chart.