Critical path method software
Onplana is critical path method software: give it the tasks, their durations and the links between them, and its scheduling engine works out every task's early and late dates, its total float and the critical path, and does it again every time a task moves. Try it free in the browser, keep editing in Onplana Schedule on Windows and Mac, and plan with your team in the web app.
What does the engine calculate?
Early and late dates, and total float
A forward pass gives each task its early start and early finish; a backward pass from the finish gives its late start and late finish. Total float is the gap between them: the working days a task can slip before the project finish moves. Tasks with no total float are the critical path. Free float is not calculated.
All four link types, with lag and lead
- Finish to start (FS): B starts when A finishes. Most links are this one.
- Start to start (SS): B starts when A starts, often with a lag: partitions start 2 days into the strip out.
- Finish to finish (FF): B finishes when A finishes: the ceilings close a day after the wiring is done.
- Start to finish (SF): B finishes when A starts: the temporary lighting runs until decorating begins.
A lag delays the next task by working days; a negative lag, a lead, lets it overlap.
All eight constraint types, and deadlines
| Constraint | What it does |
|---|---|
| As Soon As Possible (ASAP) | Starts as early as its links allow. The default. |
| As Late As Possible (ALAP) | Sits as late as it can without moving what follows it. |
| Must Start On (MSO) | Pinned to start on the date, and flagged when its links reach past it. |
| Must Finish On (MFO) | Pinned to finish on the date, and flagged when its links reach past it. |
| Start No Earlier Than (SNET) | Waits for the date, then follows its links. |
| Start No Later Than (SNLT) | Follows its links, and is flagged when they push its start past the date. |
| Finish No Earlier Than (FNET) | Cannot finish before the date. |
| Finish No Later Than (FNLT) | Follows its links, and is flagged when they push its finish past the date. |
A deadline is softer: it pins nothing, it limits the task's float and warns when the task finishes after it.
Working calendars
Durations, lags and float count working time on the plan's calendar: which weekdays are worked, the hours of each day, and the holidays and other exceptions, including ones that repeat every year. A Microsoft Project file keeps its own calendar when it is opened.
A worked example, scheduled by the engine
An office fit-out with nine tasks that use all four link types. Durations are working days, Monday to Friday, counted from day 0. Every number in the table is the answer the engine gives; type the same rows into the calculator to check it.
| # | Task | Days | After | ES | EF | LS | LF | Total float | Critical |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Design sign-off | 5 | None | 0 | 5 | 0 | 5 | 0 | Yes |
| 2 | Strip out | 4 | 1, finish to start | 5 | 9 | 5 | 9 | 0 | Yes |
| 3 | Build partitions | 6 | 2, start to start + 2 days | 7 | 13 | 7 | 13 | 0 | Yes |
| 4 | Electrical first fix | 5 | 3, start to start + 2 days | 9 | 14 | 9 | 14 | 0 | Yes |
| 5 | Ceilings | 4 | 4, finish to finish + 1 day | 11 | 15 | 11 | 15 | 0 | Yes |
| 6 | Order furniture | 10 | 1, finish to start | 5 | 15 | 8 | 18 | 3 | No |
| 7 | Decorate | 3 | 5, finish to start | 15 | 18 | 15 | 18 | 0 | Yes |
| 8 | Install furniture | 2 | 6 and 7, finish to start | 18 | 20 | 18 | 20 | 0 | Yes |
| 9 | Temporary site lighting | 8 | 7, start to finish | 7 | 15 | 12 | 20 | 5 | No |
The plan finishes at the end of day 20. The critical path is Design sign-off, Strip out, Build partitions, Electrical first fix, Ceilings, Decorate and Install furniture.
Strip out is critical through its start, not its finish: the partitions wait for it to begin, so a day lost before it starts is a day lost at the end. The ceilings start on day 11 because the finish to finish link with a 1-day lag ties their finish to the wiring's, not their start.
Ordering the furniture has 3 days of total float, and the temporary lighting, which must run until decorating starts, has 5. Neither moves the finish unless it slips by more than that.
Where to run it
Free, in the browser
The critical path calculator: type the tasks and get the table and the network diagram. No account, and nothing you type leaves the browser.
On your computer
Onplana Schedule, the free Windows and Mac app, on the same engine: open a Microsoft Project file, edit the plan, see the critical path, and save it as Project XML.
With your team
The Onplana web app shows the critical path on the Gantt chart, with float on each bar, on every plan, including Free.
What it does not do
It calculates total float only, not free float. The web app schedules in whole working days, so a lag of a few hours moves a task by the nearest whole day; Onplana Schedule schedules to the minute.
New to the method? Read what the critical path is, the forward and backward pass, or total float and free float. For the wider scheduling picture (baselines, leveling, imports), see project scheduling software.
Updated .
Frequently asked questions
What is critical path method software?
Software that schedules a plan with the critical path method: you give it the tasks, their durations and how they depend on each other, and it runs a forward and a backward pass to give every task its early and late dates and its float. The tasks with no float are the critical path, the chain that sets the finish date. Good CPM software recalculates all of it whenever a task moves.
Is there free critical path software?
Yes. The critical path calculator on this site is free in the browser with no account. Onplana Schedule is a free Windows and Mac app that opens and edits Microsoft Project files and shows the critical path. In the Onplana web app the critical path is on every plan, including Free.
Which float does Onplana calculate?
Total float: how many working days a task can slip before it moves the project finish. A task with zero total float is critical. Free float, how far a task can slip before it moves the next task, is not calculated.
Does it handle constraints and deadlines?
Yes. All eight Microsoft Project constraint types are scheduled, and a task whose links reach past a Must or No Later Than date is flagged rather than moved silently. A deadline does not pin a task; it limits its float and warns when the task finishes after it.
Can I open a Microsoft Project or Primavera file and see its critical path?
Yes. Onplana Schedule and the free MPP viewer open .mpp and Project XML files, the viewer also opens Primavera .xer, and both show the chain that sets the finish date.
What is the difference between the desktop app and the web app?
Onplana Schedule is one person editing a plan on their own computer, scheduled to the minute. The web app is the team working on the same plan, with the Gantt chart, comments and status, scheduled in whole working days. Baselines with variance in the web app are on the Professional plan and up.