Critical path
The critical path is the longest chain of linked tasks from the start of a project to its finish, so a delay to any task on it delays the finish by the same amount.
Updated .
The rule
Add up the durations along every chain of links from the first task to the last. The chain with the largest total sets the finish date, and its tasks are critical: they have no float. Every other task has float, the working days it can slip before it joins the critical path.
Scheduling tools find it with two passes. The forward pass gives each task its earliest start and finish; the backward pass, from the finish date, gives its latest. A task whose earliest and latest dates match is critical.
A deadline or a constraint can make a chain critical even when it is not the longest, because it removes the float. And the path moves: as tasks finish early or late, another chain can become the longest.
On a Gantt chart the critical path is the chain of bars, joined by their dependency arrows, that runs from the first task to the last with no gap: tools draw those bars in red. A bar off the path has its float after it, the stretch it can slide right before the finish moves.
Project duration = the largest sum of (duration + lag) along any chain of links from start to finishWorked example
An office fit-out with five tasks, all linked finish to start. Design (5 days) comes first. Order furniture (10 days) and Build partitions (8 days) both follow Design. Electrical (4 days) follows the partitions. Install furniture (3 days) needs both the furniture and the electrical work. Days are working days, counted whole.
| Task | Duration | After | Early start | Early finish | Total float | Critical |
|---|---|---|---|---|---|---|
| Design | 5 days | None | Day 1 | Day 5 | 0 | Yes |
| Order furniture | 10 days | Design | Day 6 | Day 15 | 2 | No |
| Build partitions | 8 days | Design | Day 6 | Day 13 | 0 | Yes |
| Electrical | 4 days | Build partitions | Day 14 | Day 17 | 0 | Yes |
| Install furniture | 3 days | Order furniture, Electrical | Day 18 | Day 20 | 0 | Yes |
Design, partitions, electrical, furniture install: 5 + 8 + 4 + 3 = 20 days. The other chain, Design, order, install: 5 + 10 + 3 = 18 days. The longer one is the critical path, and the furniture order has the 2 days of difference as float.
If the partitions take 3 days longer, the finish moves 3 days, to day 23. If the furniture arrives 2 days late, nothing moves; if it arrives 3 days late, the finish moves to day 21 and the furniture order joins the critical path.
What goes wrong in practice
- Missing links: a task with no successor drops out of every chain, so the critical path looks shorter and safer than the work is.
- Hard constraints (Must Start On, Finish No Later Than) that pin a task and break the chain, so a delay before it never reaches the finish.
- Watching only the critical path: a chain with a day or two of float, the near-critical path, can overtake it after one late delivery.
- Reading summary tasks as the path. The path runs through the work under them.
- Not rescheduling after recording progress, so the path on screen is last month's.
See this in your own file
Open an .mpp or Project XML file in the free viewer, with View > Critical path ticked, to see the chain of tasks that sets your finish date.
See the critical path in your own fileLonger read: CPM in Project Management: Forward and Backward Pass
Questions
Can a project have more than one critical path?
Yes. When two chains add up to the same length, both are critical, and a delay on either one moves the finish.
Is the critical path the same as the most important tasks?
No. It is the chain that sets the finish date. A task can matter a great deal to the client and still have float, and a small task can be critical because of where it sits in the chain.
How do you show the critical path on a Gantt chart?
Link the tasks with dependencies, then let the tool calculate: it runs the forward and backward pass and colours the bars with no float, usually red. In Microsoft Project it is the Critical Tasks box on the Gantt chart's Format tab, in Onplana Schedule View > Critical path, and in Onplana the Gantt chart highlights it by itself. A chart whose dates are typed in, with no links, has no critical path to show.