RACI and RASCI

RACI is a chart that names, for each task, who is Responsible for doing it, who is Accountable for the result, who is Consulted before it is done and who is Informed after, and RASCI is the same chart with a fifth role, Supportive, for people who help with the work without owning it.

Updated .

The rule

The tasks are the rows and the people or roles are the columns, with one letter in each cell that applies. Responsible (R) does the work, and several people can share it. Accountable (A) owns the result and signs it off. Consulted (C) gives input before the work is done or decided, a two-way conversation. Informed (I) is told afterwards, one way.

Every row needs exactly one Accountable, so there is always one person to ask, and at least one Responsible, so someone is named to do the work. A row that breaks either rule is the chart's finding, not a formatting slip.

RASCI adds Supportive (S): people who put effort into the task under the Responsible person's lead, such as a platform team that sets up an environment or a designer who answers questions during the build, without owning it and without being asked for a view. The rule on A and R does not change. RASCI earns its extra letter when there is a real layer of support work to plan; on a small team RACI is enough.

Each row: exactly one A, at least one R. Any number of C and I (and S in RASCI).

Worked example

A software release, the example in the free RACI chart template: seven roles and, below, four of its ten tasks as the template fills them in. Under those are two rows as they are often first written, and one row written as RASCI.

Four rows of the template's software release, two first drafts and one RASCI row
TaskProduct managerEngineering leadDevelopersQA engineersDesignerRelease managerSupport leadCheck
Agree the release scopeARCCCIIOK
Build the featuresIARCC--OK
Deploy to productionIACI-RIOK
Brief the support teamAI-I-CROK
Deploy to production (first draft)IACI-AIMore than one Accountable
Fix the bugs that block the release (first draft)IACC-I-No Responsible
Build the features (as RASCI)IARCS--OK

The first draft of the deploy has two Accountables, the engineering lead and the release manager, so when the deploy goes wrong each assumes the other signs it off; the template gives the release manager the R and keeps one A. The first draft of the bug fixes has an owner and nobody named to do the work; in the template the developers are R.

The RASCI row moves the designer from C to S: during the build the designer supplies assets and answers to the developers, which is effort to plan, not an opinion to collect. The row still has one A and one R, so it passes the same check.

What goes wrong in practice

  • More than one Accountable on a row, so the result has two owners and in practice none.
  • A whole department as Responsible, so no one person knows the work is theirs.
  • Consulted on every row: each C is a conversation that has to happen before the work moves, and a chart full of them is a queue.
  • S used for people who really do part of the task, to spread the credit or the blame. If they do the work, they are R.
  • Filling the chart at kickoff and never again, so it names people who have left and misses tasks added since.
  • Handing the chart to people instead of agreeing it with them, so the Accountable person learns it from a spreadsheet.

See this in your own file

An Excel workbook, also for Google Sheets, with this software release filled in and a Check column that flags a row with no Accountable, more than one, or no Responsible.

Get the free RACI chart template

Longer read: RASCI vs RACI vs DACI: Which Responsibility Matrix Helps

Questions

What is the difference between RACI and RASCI?

RASCI adds one role, Supportive (S), for people who put effort into a task without owning it and without being consulted on it. Responsible, Accountable, Consulted and Informed mean the same in both, and each row still has exactly one Accountable.

Can a row have more than one Responsible?

Yes. Several people can share the work, so several Rs on a row is normal. It is the Accountable that must be one person, so there is one answer when the work is late or wrong.

Does the free RACI template take an S?

No. Its drop-downs offer the four RACI letters, and its check counts the A and the R on each row. For RASCI, keep the same rule and note the Supportive people beside the row.