RACI chart template for Excel, free

A RACI chart says who does each task (Responsible), who owns it (Accountable), who is asked first (Consulted) and who is told (Informed). This one checks itself: a task with no Accountable, two of them, or nobody doing the work is flagged in red.

RACI chart example: a software release: one version of a web app, from scope to support
TaskPMELDVQADSRMSLCheck
Agree the release scopeARCCCII
Design the screens and flowsACICR-I
Break the work into tickets and estimateCARCCI-
Build the featuresIARCC--
Test against the acceptance criteriaCACRCI-
Fix the bugs that block the releaseIARC-I-
Write the release notesACCI-RC
Make the go or no-go callACICIRC
Deploy to productionIACI-RI
Brief the support teamAI-I-CR

PM product manager, EL engineering lead, DV developers, QA QA engineers, DS designer, RM release manager, SL support lead.

Download for Excel (.xlsx)raci-chart-template.xlsx: the chart with its Check column and counts, and a sheet on the four letters

The four letters

  • RResponsible

    Does the work. At least one per task; several people can share it.

  • AAccountable

    Owns the result and signs it off. Exactly one per task, so there is always one person to ask.

  • CConsulted

    Gives input before the work is done or decided. A two-way conversation: their view can change the result.

  • IInformed

    Is told when the work is done or decided. One-way: they need to know, not to agree.

One Accountable per task

The rule that makes a RACI chart useful: every task has exactly one A and at least one R. Many people can do the work, but only one owns the result. The Check column in the template tests each row for the three mistakes that break the rule:

  • No Accountable. Nobody owns the result, so nobody signs it off and a late task has no one to answer for it.
  • More than one Accountable. Two owners means two answers to every question. Pick one; the other is usually Consulted.
  • No Responsible. Someone approves the work but nobody is named to do it.

Read the counts too

Under the chart, the template counts each letter per role. In the example the engineering lead is Accountable for 5 of the 10 tasks and the product manager for 5: between them they own every task, which is normal for a release. A role with many more Rs than the others is a role that will be late.

Letters per role in the example
LetterProduct managerEngineering leadDevelopersQA engineersDesignerRelease managerSupport lead
R0131131
A5500000
C2346412
I3123143

RACI matrix or RACI chart?

The same thing. RACI matrix, RACI chart, RACI table and responsibility assignment matrix all name one grid of tasks against roles with a letter in each cell. This template works under any of the names.

There are variants that add letters, such as RASCI (with S for Support) and DACI (Driver, Approver, Contributors, Informed). For how they compare, read RAM, RACI and RASCI compared.

How to fill in a RACI chart

  1. List the tasks or deliverables down column A, at the level people are asked about (not every sub-step).
  2. Rename the roles across row 1 to the people or teams on the project.
  3. Go row by row: first the one A, then the Rs, then the Cs and Is. Leave a cell empty when the role has no part.
  4. Fix every red cell in the Check column, then read the counts for overloaded roles.
  5. Share it at kick-off and change it when a role changes hands.

Updated .

Frequently asked questions

What does RACI stand for?

Responsible, Accountable, Consulted and Informed. Responsible people do the work, the Accountable person owns the result, Consulted people give input before it is done, and Informed people are told when it is.

Can one person be both Responsible and Accountable?

Yes, on a small team it is common. This sheet takes one letter per cell and its Check column asks for an R on every task, so mark that person A and give the R to whoever does the hands-on work. If the person truly works alone, the flag is a fair reminder that the task has no second pair of hands.

Is this RACI template free?

Yes. It is an Excel workbook (.xlsx) you download from this page, with no sign-up and no email. There are no macros: the drop-down lists, colours, check and counts are plain Excel features.

Does it work in Google Sheets?

Yes. Open a blank spreadsheet, choose File > Import > Upload, pick the file and choose Replace spreadsheet. The drop-down lists, colours, Check column and counts come with it.

How many people should be Consulted?

As few as the decision needs. Every C is a conversation that has to happen before the work moves, so a row full of Cs is a slow row. If someone only needs to know the outcome, they are Informed.

Give every task one owner

In Onplana each task has one owner and can list the people who work on it with them. The RACI chart itself stays in the spreadsheet.