RIBA stages
The RIBA stages are the eight stages, numbered 0 to 7, into which the RIBA Plan of Work 2020 divides a building project, from Strategic Definition before any design to Use after handover.
Updated .
The rule
Each stage ends with an outcome the next one relies on, and in most appointments the client signs off the end of Stages 1 to 4. The eight stages are:
- Stage 0, Strategic Definition
- Stage 1, Preparation and Briefing
- Stage 2, Concept Design
- Stage 3, Spatial Coordination
- Stage 4, Technical Design
- Stage 5, Manufacturing and Construction
- Stage 6, Handover
- Stage 7, Use
Worked example
The Plan of Work is published by the Royal Institute of British Architects as the UK model for briefing, designing, building and running a building. A stage is finished when its outcome is agreed, not when its weeks run out. Stages can overlap, and on a design and build project the contractor takes over the design part of the way through, but the order of the outcomes stays the same. The fee is usually quoted stage by stage.
The table sets each stage beside what is decided in it, who usually signs it off and what the architect hands over at its end. The last column is how the fee tends to fall across the stages in practice: it is not RIBA guidance, and the real split is whatever your appointment says.
| Stage | What is decided | Signed off by | What the practice hands over | Share of the fee, in practice |
|---|---|---|---|---|
| 0, Strategic Definition | Whether a building is the right answer to the client's need | The client | A strategic brief and the business case | Small, often a separate commission |
| 1, Preparation and Briefing | The brief, the budget, the programme and the team | The client | The project brief and site information | Small |
| 2, Concept Design | The concept: massing, layout and look | The client | The concept design and a cost plan | Moderate |
| 3, Spatial Coordination | A design every discipline has coordinated | The client | Coordinated drawings, usually the planning application | Large |
| 4, Technical Design | Everything needed to build it | The client, then the contract is let | Technical drawings, specifications, tender documents | Usually the largest |
| 5, Manufacturing and Construction | The building is built | Practical completion is certified | Site inspections and instructions, if appointed | Large |
| 6, Handover | The building is handed over and defects are put right | The client, at the final certificate | As-built information and the final account | Small |
| 7, Use | How the building performs in use | The client, if this stage is in the appointment | A post-occupancy evaluation, when commissioned | Often outside the core fee |
In the template below, the client sign-offs at the end of Stages 1 to 4 are milestones, so the fee quoted for each stage has a date it becomes due.
Stage 0, Strategic Definition
Before any design, the client's need is tested: is a new building, an extension or a refit the right answer, or none of them? The outcome is a business case and a strategic brief. Many practices do this as a separate, smaller commission, or the client does it before an architect is appointed.
Stage 1, Preparation and Briefing
The project brief is written: what the building must hold and achieve, the budget, the programme and the team. Site surveys and constraints are gathered, and the procurement route is chosen, because it decides who designs what later. The client signs off the brief at the end.
Stage 2, Concept Design
The architectural concept is developed and tested against the brief, with the structural and services engineers setting out their strategies alongside. A cost plan follows the concept. The client signs off the concept; changes after this point are priced and programmed, not absorbed.
Stage 3, Spatial Coordination
Every discipline's design is brought together and checked until it fits, so the building is coordinated before the detail is drawn. The planning application is normally made at the end of this stage. In the 2013 Plan it was called Developed Design.
Stage 4, Technical Design
The design is completed to the level needed to build it: details, specifications and schedules, including the design of specialist subcontractors. Tender documents are prepared and the building contract is let at or near its end, which is why this stage often carries the largest share of the fee.
Stage 5, Manufacturing and Construction
The building is made and built. If the architect is appointed for this stage, the work is inspecting, answering the contractor's questions and instructing changes. It ends at practical completion. The 2020 name adds manufacturing because more of a building is now made off site.
Stage 6, Handover
The building is handed to the client with its as-built information, defects are put right during the defects period, and the contract closes with the final certificate and account. The 2013 Plan called it Handover and Close Out.
Stage 7, Use
The building is in use. This is where its performance is checked against the brief, through a post-occupancy evaluation, and the lessons go into the next project's Stage 0. It is often outside the architect's core appointment.
2013, 2020 and the stage names
The eight stages and their numbers have been the same since the 2013 Plan of Work, which replaced the lettered work stages A to L. The 2020 edition renamed five of them (Stages 1, 3, 5, 6 and 7; the questions below give the old names) and added the project strategies that run through every stage. It is the current edition: RIBA's Plan of Work page, read on November 15, 2026, offers it and no later one.
Source: the RIBA Plan of Work 2020, published by the Royal Institute of British Architects. RIBA's Plan of Work page
The eight stages as a plan
The free RIBA Plan of Work template lays the stages out as phases: 22 tasks with estimated hours, and a client sign-off ending each of Stages 1 to 4 as a milestone. Open it in the viewer to see the stages as a Gantt chart with their dates and links; the viewer reads the file in your browser, so nothing is uploaded.
What goes wrong in practice
- Starting Stage 4 work before the Stage 3 design is signed off, so coordination problems are found by the tenderers.
- Absorbing a client's change to the concept during Stage 3 without a variation, so the hours for a redesign come out of the fee for coordination.
- Quoting one fee for the whole job, so there is no point at which part of it is clearly earned.
- Leaving the planning application undated in the programme; in the 2020 Plan it is normally made at the end of Stage 3, and its decision time sits on the critical path.
- Using the 2013 stage names in a 2020 appointment, so the client and the practice mean different things by "Stage 3".
- Assuming Stage 7 is in the fee: post-occupancy work is often a separate commission.
See this in your own file
Stages 0 to 7 as phases with 22 tasks and the client sign-offs as milestones, for Excel, Google Sheets or Onplana.
Get the free RIBA Plan of Work templateQuestions
What are the 8 RIBA stages?
Stage 0 Strategic Definition, Stage 1 Preparation and Briefing, Stage 2 Concept Design, Stage 3 Spatial Coordination, Stage 4 Technical Design, Stage 5 Manufacturing and Construction, Stage 6 Handover and Stage 7 Use. Those are the names in the RIBA Plan of Work 2020.
What is RIBA Stage 3?
Spatial Coordination: the architectural, structural and services designs are worked together until they fit, and the planning application is normally made at its end. In the 2013 Plan the same stage was called Developed Design.
What changed between the 2013 and 2020 Plan of Work?
The eight stages and their order stayed. Stage 1 became Preparation and Briefing, Stage 3 became Spatial Coordination instead of Developed Design, Stage 5 became Manufacturing and Construction instead of Construction, Stage 6 became Handover instead of Handover and Close Out, and Stage 7 became Use instead of In Use. The 2020 Plan also adds project strategies, such as sustainability and fire safety, that run through every stage.
Is there a RIBA Plan of Work 2025?
Not as a new edition. RIBA's own Plan of Work page, read in November 2026, offers the 2020 Plan of Work with overlays added since (the most recent dated 2024), and the eight stages in it are the ones on this page.
At which RIBA stage is planning permission applied for?
In the 2020 Plan the application is normally made at the end of Stage 3, once the design is spatially coordinated, so fewer changes are needed after consent. Some projects apply earlier; the appointment and the programme say which.