Earned value calculator
Enter four figures from your project: the budget, planned value, earned value and actual cost. The calculator gives the cost and schedule variances, CPI and SPI, the estimate at completion, the estimate to complete, the variance at completion and TCPI, each with its formula and what it means.
The figures start with a worked example. Type your own in any currency; nothing you type is sent anywhere.
The total budget for all the work.
The budget for the work that should be done by now.
The budget for the work actually done by now.
What the work done by now has cost.
| Measure | Formula | Value |
|---|---|---|
| SV Schedule variance Less work is done than planned by now. | EV - PV | -52,500 |
| CV Cost variance The work done cost more than its budget. | EV - AC | -38,500 |
| SPI Schedule performance index Work is getting done at 83% of the planned rate: behind schedule. | EV / PV | 0.8333 |
| CPI Cost performance index Each dollar spent earns 87 cents of planned work: over budget. | EV / AC | 0.8721 |
| EAC Estimate at completion What the whole project will cost if the cost performance so far continues. | BAC / CPI | 860,000 |
| ETC Estimate to complete What the remaining work is expected to cost from here. | EAC - AC | 559,000 |
| VAC Variance at completion The project is heading over its budget by this much. | BAC - EAC | -110,000 |
| TCPI To-complete performance index The remaining work must be done more efficiently than planned to finish on the budget. | (BAC - EV) / (BAC - AC) | 1.0857 |
Two other ways to estimate at completion
- EAC at the budgeted rate AC + (BAC - EV) 788,500
When the overrun so far was a one-off and the rest of the work will go as budgeted.
- EAC with cost and schedule AC + (BAC - EV) / (CPI x SPI) 971,800
When a late project will also have to spend to catch up.
What to enter
- Budget at completion (BAC): the approved budget for all the work, the total of every task's budget.
- Planned value (PV): the budget of the work that should be finished by today (or by the status date), from the baseline schedule.
- Earned value (EV): each task's budget times its percent complete, added up.
- Actual cost (AC): what that work has cost so far, from timesheets, invoices and expenses.
All four must be in the same currency and measured on the same date. For the method itself, with a longer worked example, read earned value management explained.
What is the schedule performance index?
The schedule performance index (SPI) is earned value divided by planned value: how much of the work planned by now is actually done. In the example above, EV 262,500 over PV 315,000 gives an SPI of 0.8333, so the project is getting work done at 83% of the planned rate. An SPI of 1 is on schedule, above 1 is ahead and below 1 is behind.
Its partner is the cost performance index (CPI), earned value divided by actual cost. Here 262,500 over 301,000 gives 0.8721: each dollar spent has earned about 87 cents of planned work, which is why the estimate at completion, 750,000 / 0.8721, comes to 860,000, an overrun of 110,000. SPI drifts back to 1 as a late project finishes, because all the work is eventually earned, so read it beside the critical path, never on its own. How a baseline sets the planned value is covered in baselines and variance.
Have a Microsoft Project file?
Two ways to get these figures from the plan itself, without adding them up by hand:
- Open the .mpp or Project XML file in Onplana Schedule, the Windows and Mac app. Plan, Insights, Earned value reads planned value, earned value and the variances from the file's baseline cost and percent complete; it is a Professional command (how it works).
- Import the file into an Onplana workspace. The Finance tab computes the standard earned value figures with an S-curve on every plan, including Free (reading the EVM dashboard).
Not sure the file carries the costs earned value needs? The migration preview says whether it does.
Updated .
Frequently asked questions
How do you calculate earned value?
Earned value is the budget for the work actually done: the percent complete of each task times its budget, added up. If a 100,000 task is 40% done, it has earned 40,000, whatever it has cost so far. Compare it with planned value (the work that should be done by now) for the schedule, and with actual cost for the budget.
What is the schedule performance index?
SPI is earned value divided by planned value. Below 1 the project is behind schedule, above 1 it is ahead. In the example above, 262,500 / 315,000 gives an SPI of 0.8333: work is getting done at 83% of the planned rate.
What is a good CPI?
A CPI of 1 means the work done cost exactly its budget. Above 1 is under budget and below 1 over budget. Many teams treat a CPI under 0.9 as a warning, because cost performance seldom recovers once a project is about a fifth complete.
Which EAC formula should I use?
BAC / CPI is the usual one: it assumes the cost performance so far continues. AC + (BAC - EV) assumes the rest of the work goes as budgeted. AC + (BAC - EV) / (CPI x SPI) assumes a late project will also spend to catch up. The calculator shows all three.
What does a TCPI above 1 mean?
TCPI is the cost efficiency the remaining work needs to finish on the original budget. Above 1, the rest of the work has to be done better than it has been so far; a TCPI well above the current CPI says the budget is unlikely to hold.
Is what I type uploaded?
No. The figures are calculated in your browser as you type, and nothing you enter is sent to Onplana.
Can I get these figures from a Microsoft Project file?
Yes. Open the .mpp or Project XML file in Onplana Schedule, the Windows and Mac app, and Plan, Insights, Earned value reads them from the file's baseline cost and percent complete (on the Professional plan). Or import the file into an Onplana workspace, where the Finance tab computes earned value with an S-curve on every plan, including Free.