Precedence diagram maker
Type your activities, their durations and what each one depends on. The precedence diagram draws as you type, an activity on each node, with finish-to-start, start-to-start, finish-to-finish and start-to-finish links and their lags.
How to type a link: predecessors are row numbers, finish to start unless you add SS, FF or SF, with a lag in working days (2SS+2d) or a lead as a negative lag (4-2d). The example below uses all four types. What you type is drawn in this browser and is not sent anywhere.
Export the diagram as a PNG or a PDF from its toolbar. Save as Project XML keeps the plan you typed: import it into a free Onplana workspace, or open it in Onplana Schedule, the free Windows and Mac app, to keep editing it.
What is the precedence diagramming method?
The precedence diagramming method (PDM) draws a project as a network: each activity is a box, a node, and each arrow says one activity depends on another. That is why the result is also called an activity-on-node (AON) diagram. Each arrow carries one of four relationship types, and a lag or a lead in working days.
| Type | Name | Rule, from A to B | Example |
|---|---|---|---|
| FS | Finish to start | B starts once A finishes. | Pour the slab, then build the walls. |
| SS | Start to start | B starts once A starts. | Writing the test plan starts two days after the build starts (SS+2d). |
| FF | Finish to finish | B finishes once A finishes. | The user guide cannot be finished before the build is. |
| SF | Start to finish | B finishes once A starts. | The old system keeps running until the new one goes live. |
Finish to start is by far the most common. Start to start and finish to finish let work overlap, and start to finish is rare. More on each, with worked numbers, in dependency types.
Activity on node or activity on arrow?
There are two ways to draw a project network. In activity on node, the precedence diagramming method, the activities are the boxes and the arrows are only dependencies. In activity on arrow, the arrow diagramming method (ADM), the activities are the arrows and the circles between them are events, the moments one activity ends and the next begins.
- Activity on arrow shows only finish to start. Overlapping work has to be split into pieces.
- Activity on arrow needs dummy activities, dashed arrows of zero duration, to draw some dependencies without tying two activities together that are not.
- Activity on node shows all four relationship types, lags and leads, and needs no dummies.
That is why scheduling tools use activity on node: Microsoft Project calls it the Network Diagram, and Primavera P6 draws its activity network the same way. This maker draws activity on node.
The worked example
The diagram above opens on eight activities that use every relationship type. Design follows Approve scope (finish to start). Build starts two working days after Design starts (start to start with a lag). The user guide cannot finish before Build does (finish to finish). Test starts two working days before Build finishes (a lead) and after Order equipment. Run the old system keeps going until Go live starts (start to finish). The table under the diagram writes out each link in words; change a row and it follows.
Each box carries the activity's early and late dates and its float, and the critical path is drawn in red. For those numbers as a table, use the free critical path calculator. For the same network named as a PERT chart, with a Microsoft Project or Primavera file opened on it, use the PERT chart maker.
Updated .
Frequently asked questions
What is a precedence diagram?
A precedence diagram is a network diagram of a project in which each activity is a box (a node) and each arrow is a dependency between two activities. It is drawn with the precedence diagramming method (PDM), which is why it is also called an activity-on-node (AON) diagram. It shows the order the work has to happen in and which chain of activities sets the finish date.
What are the four relationship types in the precedence diagramming method?
Finish to start (FS): the successor starts once the predecessor finishes, the most common link. Start to start (SS): the successor starts once the predecessor starts. Finish to finish (FF): the successor finishes once the predecessor finishes. Start to finish (SF): the successor finishes once the predecessor starts, the rarest, used for hand-overs such as an old system running until a new one goes live.
What is the difference between activity on node and activity on arrow?
In activity on node, the precedence diagramming method, the activities are the boxes and the arrows are only dependencies, of any of the four types, with lags and leads. In activity on arrow, the arrow diagramming method, the activities are the arrows and the nodes are events; it can only show finish to start, and it needs dummy activities to draw some dependencies. Scheduling tools, Microsoft Project and Primavera P6 among them, use activity on node.
What are lag and lead?
A lag delays the successor: 2SS+2d means the activity starts two working days after row 2 starts. A lead brings it forward, written as a negative lag: 4-2d means it starts two working days before row 4 finishes.
Is this precedence diagram maker free?
Yes. Type the activities, read the diagram and the relationships under it, and export the diagram as a PNG or a PDF, with no account and nothing to install.
Is what I type uploaded?
No. The diagram is scheduled and drawn in your browser, and the picture, the PDF and the Project XML are made there too. Nothing you type is sent to Onplana.
Can I open the diagram in Microsoft Project?
Yes. Save as Project XML writes the activities, durations and links, with their types and lags, in the format Microsoft Project opens. Onplana Schedule, the free Windows and Mac app, and a free Onplana workspace open it too.