Schedules by plan sizeThrough November 14, 2026
35% of uploaded schedules have 50 to 199 tasks
Of 872 free and anonymous schedules whose task count was recorded, grouped into bands, never exact sizes.
How many tasks does a typical project schedule have?
Half of the 1,099 schedules uploaded to our free tools have 85 tasks or fewer. The most common size is 50 to 199 tasks, at 35% of 872 uploads with a recorded task count.
- 1 to 49 tasks30%n = 872
- 50 to 199 tasks35%n = 872
- 200 to 999 tasks24%n = 872
- 1,000 to 4,999 tasks9%n = 872
What this means for your plan
Size on its own is not the risk; the links are. The more tasks a plan holds, the more links can go missing unnoticed, so a plan past a few hundred tasks is worth checking before each update rather than once at the start.
Check your own schedule free85
Median tasks per plan
n = 1,099
Task counts across the plans
Each row is a point across the plans: at the 25th percentile, a quarter of them have that many tasks or fewer. A set drawn from fewer than 20 plans is left out.
Uploads to our free tools
n = 1,099
| Point across the plans | Tasks or fewer |
|---|---|
| 10th percentile | 16 |
| 25th percentile | 35 |
| Median (50th percentile) | 85 |
| 75th percentile | 307 |
| 90th percentile | 858 |
Uploaded schedules by task count
Of 872 uploads whose task count was recorded. A band holding fewer than 20 schedules is left out, not shown as zero.
- 1 to 49 tasks30%
- 50 to 199 tasks35%
- 200 to 999 tasks24%
- 1,000 to 4,999 tasks9%
How we counted: free and anonymous uploads to the Schedule Health Check, the MPP viewer, Onplana Schedule and the Schedule Risk Analyzer. Paying customers’ plans are never included. We read counts only, never file, task or company names. Any figure from fewer than 20 schedules is left out. Read the Privacy Policy section.
How does your schedule compare?
Run the same DCMA checks on your own plan in the browser, see how likely it is to finish on time with the Schedule Risk Analyzer, or open it on Windows and Mac with Onplana Schedule. All three are free.