Schedule health reportThrough November 6, 2026
100% of plans checked against the 14 DCMA points fail at least one
Of 37 free and anonymous plans checked in Onplana Schedule and the MPP viewer up to November 6, 2026, out of 807 schedules analyzed in all.
What does a schedule health check find in real project schedules?
82% of 768 schedules uploaded to our free tools have no baseline saved, so their progress cannot be measured against a plan. 67% of 770 have at least one task with no links in or out.
- No baseline saved82%n = 768
- Fail one or more DCMA checks100%n = 37
- Tasks with no links in or out67%n = 770
- Milestones with nothing leading in48%n = 770
- Date constraints the links cannot meet39%n = 770
What this means for your plan
A plan with no baseline and loose links shows a slip only after it has happened. Save a baseline before work starts, give every task a predecessor and a successor, and check the file again before each status update.
Check your own schedule free807
Schedules analyzed
100%
Fail one or more DCMA checks
n = 37
88
Median tasks per plan
n = 769
82%
No baseline saved
n = 768
What file types people upload
Of 307 files opened in Onplana Schedule that name their format.
- Microsoft Project .mpp50%
- Primavera .xer3%
- Project XML41%
- Primavera XML0%
- Other7%
Questions
What is a schedule health check?
A schedule health check reads a project schedule and tests its logic, dates, constraints and baseline against rules such as the 14 DCMA points. Of 768 schedules uploaded to our free tools, 82% had no baseline saved.
Which schedule health metrics fail most often?
In schedules uploaded to our free tools: tasks with no links in or out (67% of 770), milestones with nothing leading in (48% of 770), date constraints the links cannot meet (39% of 770).
Can I run a schedule health check on a Microsoft Project file?
Yes. The free Schedule Health Check reads .mpp, Project XML, Primavera .xer and Primavera XML files in the browser. 86% of the 522 uploads whose format was recorded were Microsoft Project files.
Is there free schedule health check software for construction schedules?
Yes. The Schedule Health Check is free in the browser, and Onplana Schedule, a free download for Windows and Mac, runs the 14 DCMA checks on .mpp and .xer files whatever the industry. Of 37 plans checked against those 14 points, 100% failed at least one.
Where do these figures come from?
From 807 free and anonymous schedules analyzed by our free tools. Paying customers' plans are never included, we read counts only, and any figure from fewer than 20 schedules is left out.
How we counted: free and anonymous uploads to the Schedule Health Check, the MPP viewer, Onplana Schedule and the Schedule Risk Analyzer. Paying customers’ plans are never included. We read counts only, never file, task or company names. Any figure from fewer than 20 schedules is left out. Read the Privacy Policy section.
How does your schedule compare?
Run the same DCMA checks on your own plan in the browser, see how likely it is to finish on time with the Schedule Risk Analyzer, or open it on Windows and Mac with Onplana Schedule. All three are free.