What the Schedule Health Check findsThrough November 14, 2026

66% of schedules uploaded to our free tools have at least one task with no links in or out

Of 1,100 free and anonymous schedules uploaded to our free tools (the Schedule Health Check, the MPP viewer and Onplana Schedule), each run through the Schedule Health Check's analyzers. Each finding is counted on its own: a plan with several is counted under each.

Which schedule health metrics fail most often?

The most common problem is at least one task with no links in or out: 66% of 1,100 schedules uploaded to our free tools have it. Next come milestones with nothing leading in (47%) and more than 10% of tasks pinned to a date (37%).

The five most common findingsEach bar is the share of uploaded schedules with at least one finding of that kind, with its n.
  • Tasks with no links in or out66%
    n = 1,100
  • Milestones with nothing leading in47%
    n = 1,100
  • More than 10% of tasks pinned to a date37%
    n = 1,100
  • A resource booked over 150% of capacity30%
    n = 1,100
  • Links to tasks missing from the file30%
    n = 1,100

What this means for your plan

Most of these come from missing or broken links. Fix the links first: a task with a predecessor and a successor moves when the work before it slips, so the finish date the plan shows stays honest.

Check your own schedule free

Findings, by how often they appear

Each bar is the share of uploaded schedules with at least one finding of that kind, out of its own n. A finding with fewer than 20 schedules behind it is left out. Summaries every report carries, such as the critical path itself, are not counted as findings. To see which of these your own plan has, run it through the free Schedule Health Check.

  • Tasks with no links in or out66%
    A task that is not a milestone has no predecessor and no successor, so it floats free of the schedule and a slip on it moves nothing. n = 1,100
  • Milestones with nothing leading in47%
    A milestone has no predecessor, so its date is typed in rather than driven by the work before it. n = 1,100
  • More than 10% of tasks pinned to a date37%
    More than one task in ten carries a date constraint other than as soon as possible, which usually means the links are not trusted to set the dates. n = 1,100
  • A resource booked over 150% of capacity30%
    At its busiest point, a person or resource is booked on more than one and a half times what they can do. n = 1,100
  • Links to tasks missing from the file30%
    A task names a predecessor that does not exist in the schedule. n = 1,100
  • Date constraints the links cannot meet28%
    A task carries a date constraint, such as finish no later than, that the dates worked out from its links fall outside. n = 1,100
  • An outline six or more levels deep28%
    The task outline nests six or more levels, which makes the plan hard for anyone but its author to read. n = 1,100
  • Tasks waiting on more than five others26%
    A task has more than five predecessors, so any one of them running late holds it up. n = 1,100
  • Tasks a day or less from the critical path23%
    Tasks with some float, but one working day or less, so a short slip makes them critical. n = 1,100
  • More than half the tasks on the critical path20%
    Over 50% of tasks are critical, so the plan has almost no slack to absorb a delay. n = 1,100
  • Milestones over 15% of tasks18%
    More than 15% of tasks are milestones, which often means the real work is not broken down. n = 1,100
  • Critical work over 60% of all task hours17%
    The work on the critical path adds up to more than 60% of the task hours in the plan, so one slip moves the whole delivery. n = 1,100
  • Tasks over 10 working days behind baseline15%
    A task now finishes more than 10 working days after its baseline finish. n = 1,100
  • More than 30% and up to half the tasks on the critical path12%
    Over 30% of tasks are critical, but no more than half: a thin margin for a delay. n = 1,100
  • Tasks over 3 and up to 10 working days behind baseline7%
    A task now finishes more than 3, and no more than 10, working days after its baseline finish. n = 1,100
  • A resource booked over capacity, up to 150%6%
    At its busiest point, a person or resource is booked above their capacity, but no more than one and a half times it. n = 1,100
  • No task finishing on its baseline date5%
    A baseline is saved, but not one task still finishes within half a day of its baseline finish. n = 1,100
  • Costs with no currency set4%
    The file carries planned costs but names no currency for them. n = 1,100
  • Deadlines the scheduled finish overruns2%
    A task finishes, by its links, after the deadline set on it. n = 1,100
  • Tasks costing 30% or more over baseline1%
    A task's current cost is at least 30% above its baseline cost. n = 1,100
  • No critical path at all1%
    A plan of more than five tasks has none on the critical path, which usually means its links are missing. n = 1,100
  • Tasks costing 15% to under 30% over baseline1%
    A task's current cost is at least 15%, and under 30%, above its baseline cost. n = 1,100
  • Links that loop back on themselves1%
    Tasks are linked in a circle, so each waits on another and their dates cannot be worked out. n = 1,100

How each analyzer rates the plans it runs on

An analyzer runs only on plans that carry what it reads: resources for the overallocation check, a saved baseline for the baseline check, date constraints for the constraint check. So each n is the plans it ran on, not every upload.

AnalyzerRated criticalRated warning
Dependency health1% n = 1,09981% n = 1,099
Baseline variance79% n = 2091% n = 209
Constraint violations44% n = 70632% n = 706
Resource overallocation69% n = 4814% n = 481
Complexity3% n = 1,09961% n = 1,099
Critical path20% n = 1,09912% n = 1,099
Schedule risk1% n = 1,09923% n = 1,099
Cost coverage1% n = 1,0990% n = 1,099

Questions

What are the most common problems in a project schedule?

In 1,100 schedules uploaded to our free tools, the most common are tasks with no links in or out (66%), milestones with nothing leading in (47%), more than 10% of tasks pinned to a date (37%).

What does a task with no links mean in a schedule health check?

A task that is not a milestone has no predecessor and no successor, so it floats free of the schedule and a slip on it moves nothing. 66% of 1,100 uploaded schedules have at least one.

How do I check my own schedule for these problems?

Upload it to the free Schedule Health Check, which runs the same analyzers in the browser. 1,100 schedules have been through them so far.

How we counted: free and anonymous uploads to the Schedule Health Check, the MPP viewer, Onplana Schedule and the Schedule Risk Analyzer. Paying customers’ plans are never included. We read counts only, never file, task or company names. Any figure from fewer than 20 schedules is left out. Read the Privacy Policy section.

Back to all insights

How does your schedule compare?

Run the same analyzers on your own plan in the browser with the free Schedule Health Check, see how likely it is to finish on time with the Schedule Risk Analyzer, or open it on Windows and Mac with Onplana Schedule. All three are free.