Microsoft Project Online retires September 30, 2026, migrate to a modern platform before it's too late.Start migration
Free template

Free Software Product Launch Template (with Task Plan)

Ship your next product on a plan that already exists. This launch template lays out the full arc, customer discovery, MVP build, closed beta, and GA day, as 12 scheduled tasks with priorities, effort estimates, and two launch milestones. Open it in Onplana and you start from a working plan instead of a blank board.

No credit card. Opens as a real project on the Free plan.

What’s inside

The full plan is below, every task with its description, duration, and priority. Open the template and all of it is scheduled from today, ready to edit.

12

Scheduled tasks

3

Phases

2

Milestones

~9

Weeks end to end

The plan, phase by phase

Discovery4 tasks

Run customer discovery interviews

Talk to 8-10 target customers to validate the problem space.

7 daysHigh

Define success metrics & KPIs

North-star metric, activation + retention targets.

4 daysHigh

Technical spike: feasibility assessment

De-risk the two biggest unknowns before committing to build.

7 daysMedium

Write product requirements doc

Scope, non-goals, user stories, open questions.

5 daysHigh

Build4 tasks

Design core user flows

Wireframes for onboarding + primary value-moment screens.

8 daysHigh

Build MVP backend + data model

API endpoints, schema, auth, minimal deploy pipeline.

18 daysCritical

Build MVP frontend

Core screens wired to the API. Unit tests on critical paths.

18 daysCritical

QA pass + bug bash

Cross-browser + mobile, accessibility audit, perf baseline.

5 daysHigh

Launch4 tasks

Draft launch announcement + press kit

Blog post, email to list, social cards, hero screenshots.

6 daysMedium

Run closed beta with 20 customers

Invite, onboard, collect structured feedback, triage issues.

10 daysHigh

Set up analytics + monitoring dashboards

Product analytics, error tracking, uptime alerts.

4 daysMedium

Execute GA launch day

Flip the feature flag, publish the post, monitor the firehose.

1 dayCritical

Milestones

Milestones land on the timeline automatically and show as diamonds on the Gantt chart, so the dates that matter stay visible.

Beta release

Day 44 of the plan

General availability

Day 58 of the plan

Frequently asked

Can I customize the phases and tasks?

Yes. The template opens as a normal project in Onplana, so everything is editable: rename or recolor the Discovery, Build, and Launch phases, add or delete tasks, change priorities and estimates, and drag dates on the Gantt chart. The template is a starting point, not a locked structure.

Is this software product launch template really free?

Yes. Click "Use this template free", create a free Onplana account (no credit card), and the launch plan opens as a real project with all 12 tasks, three phases, and both milestones already scheduled. The Free plan has no time limit.

How long does the launch plan run?

The template schedules roughly 9 weeks (60 days) from the first discovery interview to GA launch day, with a closed beta milestone around week 7. Dates are set automatically from the day you create the project, and you can stretch or compress the timeline on the Gantt chart to match your release date.

Start with the plan already built

Open the Software Product Launch template free and your phases, tasks, and milestones are scheduled before the kickoff meeting. No credit card, no time limit.