Free template

Microsoft Project Migration Plan Template (30-Day Cutover)

Move your Microsoft Project or Project Online portfolio with a plan, not a prayer. This migration plan template sequences a 30-day cutover, inventory and stakeholder sign-off, data export and cleanup, staging import, reconciliation and pilot UAT, then the production cutover, and it ships with a pre-logged risk about legacy custom-field mapping so the most common surprise is already on your radar.

No credit card. Opens as a real project on the Free plan.

What’s inside

The full plan is below, every task with its description, duration, and priority. Open the template and all of it is scheduled from today, ready to edit.

10

Scheduled tasks

5

Phases

2

Milestones

~4

Weeks end to end

The plan, phase by phase

Audit2 tasks

Inventory source projects + custom fields

Count of projects, tasks, resources, enterprise custom fields.

3 daysHigh

Identify stakeholders + sign-off owners

Programme sponsor, PMO lead, per-portfolio project managers.

2 daysMedium

Data Prep3 tasks

Export .MPP + ProjectOnline OData feeds

One export per project. Stash in secure shared folder.

3 daysHigh

Clean + normalise source data

Drop cancelled projects, fix orphaned tasks, deduplicate resources.

5 daysMedium

Map custom fields to Onplana equivalents

Field-by-field mapping doc, sign-off from PMO before import.

5 daysHigh

Import1 task

Run staging import + smoke test

Import into staging org. Spot-check 10% of projects.

3 daysHigh

Validation2 tasks

Reconcile staging vs source (counts + totals)

Task counts, planned hours, assignees, dependencies.

4 daysHigh

UAT with 3 pilot project managers

Each PM walks through their portfolio. Log + fix issues.

5 daysHigh

Cutover2 tasks

Run production import

Full import into prod. Freeze source edits for the window.

2 daysCritical

Decommission read-only access to MS Project

Flip source system to read-only, notify users, update SSO.

2 daysMedium

Milestones

Milestones land on the timeline automatically and show as diamonds on the Gantt chart, so the dates that matter stay visible.

Staging ready

Day 15 of the plan

Production cutover

Day 28 of the plan

Frequently asked

Does this template import my actual .mpp files?

The template is the cutover plan itself, the tasks, phases, and milestones that take you from inventory to production import. The importing happens inside Onplana, which reads .mpp, MSPDI XML, and Project Online OData natively, preserving tasks, dependencies, milestones, custom fields, and costs. The plan tells you when to run each import and what to check afterwards.

How long does a Microsoft Project migration take?

This plan schedules a 30-day cutover: about a week of audit and data prep, a staging import in week 2, reconciliation and pilot UAT in week 3, and the production cutover in week 4, with staging-ready and production-cutover milestones built in. Small portfolios finish faster; large PMOs often run the validation phase longer. Either way, the structure stays the same.

What about enterprise custom fields and resources?

The plan dedicates a task to field-by-field custom-field mapping with PMO sign-off, and it ships with a pre-logged risk: legacy MS Project custom fields that use formulas or enterprise resource types may not map cleanly and can need manual recreation. Surfacing that risk on day one is exactly what keeps a cutover on schedule.

Start with the plan already built

Open the Migration from MS Project template free and your phases, tasks, and milestones are scheduled before the kickoff meeting. No credit card, no time limit.