Free Event Planning Template (90-Day Plan)
Run your event on a 90-day countdown instead of a sticky-note wall. This event planning template sequences everything from venue tours and speaker outreach to badge printing, volunteer briefings, and the day-of run sheet, 14 scheduled tasks across five phases, each timed backwards from event day.
No credit card. Opens as a real project on the Free plan.
The spreadsheet is a 14-task plan with phases, durations and milestones, ready for Excel or Google Sheets. It carries no dates, so set your own start, or paste it into the Gantt chart generator to have the schedule built for you. Want to compare the plans side by side first? Every one of them is on the project plan template page, with the rows shown before you download.
The Microsoft Project file (.xml) is the same plan with its dates worked out: every task is scheduled from Monday 4 January 2027. Open it in Microsoft Project, or open it free in Onplana Schedule, the desktop app that edits Project files without Microsoft Project.
What’s inside
The full event plan is below, all 14 tasks across Venue, Speakers, Marketing, Logistics, and Day-of, each with its description, duration, and priority, timed backwards from event day. Open the template and every date is scheduled from today, ready to shift to your date.
14
Scheduled tasks
5
Phases
1
Milestone
~13
Weeks end to end
How to run an event with this plan
An event has one immovable date, and every task in this plan is timed backwards from it. Event day lands at day 89 of the 90-day countdown, and the two tasks that can sink the whole thing if they slip, signing the venue contract and running the day itself, are the only CRITICAL work in the plan. Lock the venue first: capacity, AV, and catering constrain everything downstream, from how many badges you print to which speakers you can host, so the Venue phase runs before the others even though promotion and speaker outreach feel more urgent.
The long-lead items hide in plain sight. Confirming the speaker lineup is a 20-day task and promotion runs for 60 days, so both start early and overlap the rest of the plan rather than waiting their turn. That is the point of laying the event out on a timeline instead of a checklist: you can see that the marketing push has to be live while you are still coordinating speaker run-of-show, and that catering headcount cannot wait until the final week. The Logistics phase is where the plan converges, printing, volunteer briefings, and the 72-hour headcount reconciliation, and it only works if the phases before it stayed on their dates.
Scale the tasks, not the structure. A 50-person meetup keeps all five phases but shrinks each task to a day or two; a multi-track conference duplicates the speaker tasks per track and stretches the marketing runway. Running a party or an internal offsite with no external speakers? Drop the Speakers phase entirely and the countdown still holds. The five phases are the constants, Venue, Speakers, Marketing, Logistics, Day-of, and the backward-timed dates keep the dependencies visible whatever the size.
The plan, phase by phase
Venue3 tasks
Shortlist + tour 3 venues
Capacity fit, AV, catering options, accessibility checklist.
Sign venue contract + pay deposit
Legal review, insurance, cancellation terms.
Confirm catering + dietary requirements
Menu selection, headcount buffer, allergen handling.
Speakers3 tasks
Draft speaker wishlist + outreach
Prioritize 10 targets, personalised outreach emails.
Confirm speaker lineup + contracts
Travel + accommodation, talk titles, abstracts, headshots.
Coordinate speaker run-of-show + AV checks
Tech rider, slide templates, pre-event rehearsal slots.
Marketing3 tasks
Build event landing page + registration
Agenda, speakers, CTA, ticket tiers, GDPR-compliant signup.
Launch promotion: email + social + partners
Announcement sequence, partner cross-promo, referral codes.
Design event collateral
Lanyards, signage, deck templates, photo backdrop, swag.
Logistics3 tasks
Print + ship materials
Badges, programs, signage. Buffer for last-minute registrations.
Brief volunteers + event staff
Run-of-show, FAQs, incident escalation, comms channels.
Final headcount + dietary reconciliation
Confirm numbers with caterer 72h out. Buffer +5%.
Day-of2 tasks
Event day - registration + session support
Doors, check-in, session timekeeping, AV fixes, Q&A mics.
Post-event survey + thank-you comms
NPS survey, session recordings, speaker thanks, photo recap.
Milestones
Event day sits at the end of the 90-day countdown as a diamond on the Gantt chart, the one fixed date every other task is scheduled backwards from.
Event day
Day 89 of the plan
Frequently asked
What size of event does this template fit?
The structure suits anything from a 50-person meetup to a multi-track conference. The five phases (Venue, Speakers, Marketing, Logistics, Day-of) are the constants; scale the individual tasks up or down, for example duplicate the speaker tasks per track, or drop the speaker phase entirely for a party or offsite.
Can I change the 90-day timeline?
Yes. Dates are scheduled automatically from the day you create the project, with event day landing at day 89. If your event is closer or further out, drag tasks on the Gantt chart or edit dates directly; the milestone moves with you and dependent work stays visible.
Does the template include a day-of run sheet?
The Day-of phase covers registration, session timekeeping, AV support, and the post-event survey and thank-you communications, and the volunteer briefing task in Logistics carries the run-of-show. Expand those tasks with subtasks and checklists in Onplana to build out your minute-by-minute schedule.
What are the long-lead tasks I should start first?
Two tasks gate everything else: signing the venue contract (the only early CRITICAL item, because capacity and AV constrain the rest of the plan) and confirming the speaker lineup, a 20-day task with travel and contracts attached. Promotion also runs long, 60 days, so it starts early and overlaps the middle of the plan. The Gantt view makes these overlaps visible, so you can see what has to be in motion before the task that depends on it comes due.
Can I run this for a virtual or hybrid event?
Yes, with light edits. Swap the Venue phase for platform setup and streaming checks, keep Speakers and Marketing as they are, and turn the Day-of phase into moderation, tech support, and chat management. The 90-day backward countdown and the five-phase rhythm carry over; you are changing what a few tasks mean, not the shape of the plan.
Start with the plan already built
Open the Event Planning template free and your phases, tasks, and milestones are scheduled before the kickoff meeting. No credit card, no time limit.