Asana Gantt chart with the critical path
Yes, you can see your Asana project as a Gantt chart in about a minute. Export the project as CSV, drop the file on the viewer below, and every task with dates appears as a bar, subtasks under their parents, with the links between tasks and the critical path drawn for you.
- Start Date and Due Date become the bars; a task with only a due date is a one-day bar on that date
- Subtasks sit under their parent task
- Blocked By dependencies become links, and the critical path follows them
- The assignee shows on each task
Export your Asana project as CSV
- Open the project in Asana.
- Click the drop-down menu next to the project's title.
- Hover over Export/Print and choose CSV.
Asana's help page on importing and exporting projects lists the export on Personal and on every paid plan. A task with a start date and a due date is a bar between them, and a task with only a due date is a one-day bar ending on its due date, so a Personal project opens too (Asana's help puts start dates on its paid plans). Asana's own Gantt view is on Starter and above, and its critical path on Advanced and above (Asana's help pages, read November 2026).
Drop the CSV here
Drop the file anywhere on this window, or choose Open a file. Leave the column names as Asana wrote them: the viewer recognises them.
A CSV is uploaded and converted on Onplana's servers to open it, and the viewer asks first. The uploaded copy is deleted within 3 days, and removed from backups 7 days after that.
The viewer reads the plan and changes nothing in Asana. To move dates and save the plan, use Onplana Schedule, free for Windows and Mac
What the Gantt here shows
Each task is a bar from its start to its due date (one day, when it has only a due date), subtasks are indented under their parent, and the links from Blocked By are drawn between the bars. The chain of tasks that sets the finish date is in red, with the slack of every other task beside its bar. The same plan opens as a task sheet and as a network diagram from the tabs above the chart, and you can download the chart as PNG or PDF.
Want a second opinion on the plan itself? The Schedule Health Check reviews it for missing links, open ends and dates that cannot hold. In the viewer it is Analyze > Check health, on the plan you just opened.
Weighing a move instead? Onplana and Asana compared.
Updated .
Frequently asked questions
Does Asana have a Gantt chart?
Yes, on its paid plans: Asana's help pages put Gantt view on Starter and above and the critical path on Advanced and above. The viewer on this page needs only the CSV export: tasks with due dates become bars on any plan that exports.
Do I need an Asana add-on or an integration?
No. Export the project as CSV from Asana and drop the file on the viewer on this page. Nothing connects to your Asana account, and nothing in Asana changes.
Why are some bars only one day long?
Those tasks have a due date and no start date, so each is drawn as one day ending on its due date. Give the task a start date in Asana and export again to see its full length; Asana's help puts start dates on its paid plans.
Do my dependencies come through?
Yes. The CSV's Blocked By (Dependencies) column becomes links between the tasks, and the critical path is worked out from them and the dates.
Is my file uploaded when I drop it on the viewer?
Yes. A CSV is converted on Onplana's servers to open it, and the viewer asks first. The uploaded copy is deleted within 3 days, and removed from backups 7 days after that.
Keep the plan as a Gantt
The viewer forgets the file when you close the page. A free Onplana workspace keeps the plan online with your team: dependencies, the critical path, baselines and progress that rolls up. No credit card.