DCMA check 5 of 14: Hard constraintsThrough November 21, 2026

11% of plans checked against the 14 DCMA points fail the check for hard constraints

Of 35 free and anonymous plans checked in Onplana Schedule and the online MPP viewer. A plan the check could not run on, such as one with no baseline for the baseline checks, counts as not failing it.

11%

of checked plans fail this check

n = 35 plans

At most 5%

More than 5% of open tasks carry a Must start on, Must finish on, Start no later than or Finish no later than constraint with a date. Start no earlier than and Finish no earlier than are not counted, and neither is a deadline.

The threshold is the one Onplana's checks use, in the web app and in Onplana Schedule alike. How each check is measured.

Why it matters

A hard constraint pins a task to a date whatever happens to the work before it. When an earlier task slips, the pinned task does not move, so the plan keeps showing a date the logic can no longer reach. Used widely, hard constraints turn a schedule back into a list of typed dates and stop it from warning anyone.

How to fix it in Onplana Schedule

  1. Open the plan in Onplana Schedule, the free desktop app, and choose Plan > Schedule quality. The checks run on your computer.
  2. On the Hard constraints check, press Show N tasks. The Constraint column shows each task's constraint and date.
  3. Select the tasks and choose Edit > Clear the constraint. For many at once, select them with Ctrl-click or Shift-click and use Edit > Change N tasks… and Clear constraint, which one Undo takes back.
  4. Link each task to the work it really waits on, so the logic sets its date.
  5. For a date someone outside the project has promised, open Task details (Shift+F2) and set a deadline instead. A deadline is watched rather than pinned, and this check does not count it.
  6. Choose Plan > Schedule quality again to confirm the check passes, then save.

Read more in the Onplana docs. See all 14 DCMA checks by fail rate.

For tenders and client submissions

Every page of the PDF report prints a line, "Verify this report at onplana.com/verify/" with the report's own code, and a QR code of the same address. When the report goes with a tender or a client submission, the reader can open that address to see the health score, the date Onplana checked the schedule and, when the report includes them, how many of the DCMA 14-point checks passed and failed. They can type the file name they were sent to see whether the report was made from it. Nothing else about the plan is shown. Onplana checks the schedule against a public standard; it does not approve the schedule or vouch for it.

How we counted: free and anonymous uploads to the Schedule Health Check, the MPP viewer, Onplana Schedule and the Schedule Risk Analyzer. Paying customers’ plans are never included. We read counts only, never file, task or company names. Any figure from fewer than 20 schedules is left out. Read the Privacy Policy section.