DCMA check 8 of 14: High durationThrough November 21, 2026
37% of plans checked against the 14 DCMA points fail the check for high duration
Of 35 free and anonymous plans checked in Onplana Schedule and the online MPP viewer. A plan the check could not run on, such as one with no baseline for the baseline checks, counts as not failing it.
37%
of checked plans fail this check
n = 35 plans
At most 5%
More than 5% of open tasks that are not milestones are longer than 44 working days. A task's baseline duration is used when it has one, and its current duration otherwise.
The threshold is the one Onplana's checks use, in the web app and in Onplana Schedule alike. How each check is measured.
Why it matters
A task that runs for more than two months is hard to track. Its percent complete is a guess for most of its life, problems inside it surface late, and its single bar cannot show which part is running behind. Breaking long work into pieces that finish on their own gives the plan dates someone can check.
How to fix it in Onplana Schedule
- Open the plan in Onplana Schedule, the free desktop app, and choose Plan > Schedule quality. The checks run on your computer.
- On the High duration check, press Show N tasks.
- Shorten each long task to its first piece, then add the rest as tasks below it with the insert button beside its name, each with its own duration, and link them in order.
- To keep one row for the whole stretch, put the pieces under a summary task with Edit > Indent. Summary tasks are left out of the check.
- On a plan with a baseline the check reads each task's baseline duration, so the split counts once a new baseline is saved with Plan > Set baseline…, after the change is agreed.
- Choose Plan > Schedule quality again to confirm the check passes, then save.
Read more in the Onplana docs. See all 14 DCMA checks by fail rate.
For tenders and client submissions
Every page of the PDF report prints a line, "Verify this report at onplana.com/verify/" with the report's own code, and a QR code of the same address. When the report goes with a tender or a client submission, the reader can open that address to see the health score, the date Onplana checked the schedule and, when the report includes them, how many of the DCMA 14-point checks passed and failed. They can type the file name they were sent to see whether the report was made from it. Nothing else about the plan is shown. Onplana checks the schedule against a public standard; it does not approve the schedule or vouch for it.
How we counted: free and anonymous uploads to the Schedule Health Check, the MPP viewer, Onplana Schedule and the Schedule Risk Analyzer. Paying customers’ plans are never included. We read counts only, never file, task or company names. Any figure from fewer than 20 schedules is left out. Read the Privacy Policy section.
How does your schedule compare?
Run the same DCMA checks on your own plan in the browser, see how likely it is to finish on time with the Schedule Risk Analyzer, or open it on Windows and Mac with Onplana Schedule. All three are free.