DCMA check 9 of 14: Invalid datesThrough November 21, 2026

66% of plans checked against the 14 DCMA points fail the check for invalid dates

Of 35 free and anonymous plans checked in Onplana Schedule and the online MPP viewer. A plan the check could not run on, such as one with no baseline for the baseline checks, counts as not failing it.

66%

of checked plans fail this check

n = 35 plans

None allowed

Any task has a planned date before the status date on unfinished work, or an actual date after the status date. DCMA allows none.

The threshold is the one Onplana's checks use, in the web app and in Onplana Schedule alike. How each check is measured.

Why it matters

The status date is the line between what has happened and what is forecast. Unfinished work planned before it is a forecast that has already passed, and an actual date after it records something that has not happened yet. Either way the plan has not been brought up to date, so its finish date is not one anyone can rely on.

How to fix it in Onplana Schedule

  1. Open the plan in Onplana Schedule, the free desktop app, and choose Plan > Schedule quality. The checks run on your computer.
  2. On the Invalid dates check, press Show N tasks. Each task says what is wrong: not done with a finish before the status date, not started with a start before it, or an actual date after it.
  3. For work that is done, type 100 in its percent complete.
  4. For work not yet done, move its dates past the status date: type a new start or finish, or drag the bar. To shift a whole plan nobody has updated, Plan > Move project… moves every task without actual work at once.
  5. For a task marked started that has not begun, set its percent complete to 0, which clears its actual start.
  6. Onplana Schedule reads the status date saved in the file and uses today when the file sets none; the drawer says which. If almost every task is flagged, check that date in the tool that set it.
  7. Choose Plan > Schedule quality again to confirm the check passes, then save.

Read more in the Onplana docs. See all 14 DCMA checks by fail rate.

For tenders and client submissions

Every page of the PDF report prints a line, "Verify this report at onplana.com/verify/" with the report's own code, and a QR code of the same address. When the report goes with a tender or a client submission, the reader can open that address to see the health score, the date Onplana checked the schedule and, when the report includes them, how many of the DCMA 14-point checks passed and failed. They can type the file name they were sent to see whether the report was made from it. Nothing else about the plan is shown. Onplana checks the schedule against a public standard; it does not approve the schedule or vouch for it.

How we counted: free and anonymous uploads to the Schedule Health Check, the MPP viewer, Onplana Schedule and the Schedule Risk Analyzer. Paying customers’ plans are never included. We read counts only, never file, task or company names. Any figure from fewer than 20 schedules is left out. Read the Privacy Policy section.