DCMA check 1 of 14: LogicThrough November 21, 2026

80% of plans checked against the 14 DCMA points fail the check for missing logic links

Of 35 free and anonymous plans checked in Onplana Schedule and the online MPP viewer. A plan the check could not run on, such as one with no baseline for the baseline checks, counts as not failing it.

80%

of checked plans fail this check

n = 35 plans

At most 5%

More than 5% of open tasks have no predecessor, no successor, or neither. Summary tasks are left out, and the task that finishes the plan may have no successor.

The threshold is the one Onplana's checks use, in the web app and in Onplana Schedule alike. How each check is measured.

Why it matters

Links are what make a schedule move. When a task has nothing leading into it, a late start upstream never reaches it, and when nothing follows it, its own slip never reaches the finish date. A plan with missing links can look on time while the work behind it is already late, because the dates on screen are typed in rather than worked out from the work.

How to fix it in Onplana Schedule

  1. Open the plan in Onplana Schedule, the free desktop app, and choose Plan > Schedule quality. The checks run on your computer.
  2. On the Logic check, press Show N tasks. The chart narrows to the tasks missing a link, and each one says whether it lacks a predecessor, a successor or both.
  3. For a task with no predecessor, type the row number of the task it waits on in its Predecessors cell, or draw a link from that task's bar to its bar on the chart.
  4. For a task with no successor, add its row number to the Predecessors cell of the task that waits on it. A finish milestone at the end of the plan gives the last pieces of work something to lead into.
  5. A link on a summary task does not give the tasks inside it a predecessor, so link the tasks themselves.
  6. Choose Plan > Schedule quality again to confirm the check passes, then save.

Read more in the Onplana docs. See all 14 DCMA checks by fail rate.

For tenders and client submissions

Every page of the PDF report prints a line, "Verify this report at onplana.com/verify/" with the report's own code, and a QR code of the same address. When the report goes with a tender or a client submission, the reader can open that address to see the health score, the date Onplana checked the schedule and, when the report includes them, how many of the DCMA 14-point checks passed and failed. They can type the file name they were sent to see whether the report was made from it. Nothing else about the plan is shown. Onplana checks the schedule against a public standard; it does not approve the schedule or vouch for it.

How we counted: free and anonymous uploads to the Schedule Health Check, the MPP viewer, Onplana Schedule and the Schedule Risk Analyzer. Paying customers’ plans are never included. We read counts only, never file, task or company names. Any figure from fewer than 20 schedules is left out. Read the Privacy Policy section.