DCMA check 10 of 14: ResourcesThrough November 21, 2026

54% of plans checked against the 14 DCMA points fail the check for resources

Of 35 free and anonymous plans checked in Onplana Schedule and the online MPP viewer. A plan the check could not run on, such as one with no baseline for the baseline checks, counts as not failing it.

54%

of checked plans fail this check

n = 35 plans

None allowed

Any open task that is not a milestone has no resource assigned. DCMA sets no percentage, so the check passes only when every one has a resource.

The threshold is the one Onplana's checks use, in the web app and in Onplana Schedule alike. How each check is measured.

Why it matters

A task with no one assigned has no one accountable for it and no one who will report its progress. It also leaves the plan unable to show who is overloaded, because the work is invisible to every resource view. Assigning every open task is the first step toward a plan whose dates someone has agreed to.

How to fix it in Onplana Schedule

  1. Open the plan in Onplana Schedule, the free desktop app, and choose Plan > Schedule quality. The checks run on your computer.
  2. On the Resources check, press Show N tasks.
  3. In a task's Resource names cell, start typing a name and pick it from the list, or choose Create to add a person or team the plan does not have yet.
  4. To give many tasks the same resource, select them with Ctrl-click or Shift-click and set Resources in Edit > Change N tasks….
  5. Milestones are not counted, so they need no resource.
  6. Choose Plan > Schedule quality again to confirm the check passes, then save.

Read more in the Onplana docs. See all 14 DCMA checks by fail rate.

For tenders and client submissions

Every page of the PDF report prints a line, "Verify this report at onplana.com/verify/" with the report's own code, and a QR code of the same address. When the report goes with a tender or a client submission, the reader can open that address to see the health score, the date Onplana checked the schedule and, when the report includes them, how many of the DCMA 14-point checks passed and failed. They can type the file name they were sent to see whether the report was made from it. Nothing else about the plan is shown. Onplana checks the schedule against a public standard; it does not approve the schedule or vouch for it.

How we counted: free and anonymous uploads to the Schedule Health Check, the MPP viewer, Onplana Schedule and the Schedule Risk Analyzer. Paying customers’ plans are never included. We read counts only, never file, task or company names. Any figure from fewer than 20 schedules is left out. Read the Privacy Policy section.

Back to all insights

How does your schedule compare?

Run the same DCMA checks on your own plan in the browser, see how likely it is to finish on time with the Schedule Risk Analyzer, or open it on Windows and Mac with Onplana Schedule. All three are free.