Schedule risk
The typical simulated schedule finishes 11 days past its planned date at even odds, and 16 days at 80% confidence
Median P50 slip 11 days, median P80 slip 16 days (n = 277).
n = 277 free and anonymous schedules simulated in the Schedule Risk Analyzer; medians across the schedules.
Every chart is free to republish, in print or online, under Creative Commons Attribution 4.0 (CC BY 4.0). Keep the credit that is inside the image, or write it beside the chart:
Source: Onplana schedule insights, onplana.com/insights
Online, please link the credit to onplana.com/insights.
Embed it
<figure> <img src="https://onplana.com/press/charts/typical-slip.png" width="1200" height="630" alt="The typical simulated schedule finishes 11 days past its planned date at even odds, and 16 days at 80% confidence"> <figcaption>Source: <a href="https://onplana.com/insights">Onplana schedule insights</a>, <a href="https://creativecommons.org/licenses/by/4.0/">CC BY 4.0</a></figcaption> </figure>