A construction programme is the contractor's time plan for the works: activities, logic, durations and key dates. See what it must show and how to build one.

Onplana Team4 min read

A construction programme is the contractor's time plan for the works, and it answers one question before any other: in what order, and by what dates, will this job be built? Programme is the UK, Irish and Australian word for what a US general contractor calls the construction schedule, and "programme of works" means the same document.

In short. A construction programme (programme of works) is the contractor's time plan for the works: a Gantt chart of activities with logic links, durations, key dates and a calculated critical path. It exists in three versions that matter: the tender programme, the accepted baseline programme, and the updated programme that tracks the real job.

Start from a free construction schedule template if you would rather edit than draw: it is a 20-task plan from preconstruction through closeout, in Excel CSV and Microsoft Project XML.

Why the logic matters more than the drawing: Glenn Ballard's 2000 University of Birmingham thesis reports that earlier research "revealed substantial improvement in productivity for those who improved plan reliability to the 70% level" (Ballard, 2000). A programme with linked activities is one you can check against what happened.

What does a construction programme show?

A construction programme shows the sequence of the works, how long each activity takes, and the dates that cannot move. A programme that is only a picture of bars cannot tell you what a delay costs; one with logic can.

Element What it tells the reader
Activities The work, broken into pieces a person can own and measure
Logic links Which activity must finish (or start) before the next can begin
Durations How long each takes, in working days or weeks
Key dates and milestones Possession, completion, sectional completion and other dates the contract fixes
Critical path The longest chain; any delay on it moves completion
Float How far an activity can slip before it moves completion
Resources (if asked) Crews or plant, where the contract requires them

The diagram below shows a small programme: five activities, the order they follow, and the one chain that sets the finish.

A five-activity construction programme with its critical path Week 1 3 5 7 9 11 Groundworks Frame Roof First fix Drainage float Completion Critical path Has float

The red chain, groundworks then frame then roof then first fix, runs end to end across ten weeks. Drainage takes two weeks, starts with the frame and has two weeks of float, so it can slip that far without moving completion.

What are the tender, baseline and updated programmes?

A construction programme changes role across a job, and the same word covers all three versions.

  1. Tender programme. Submitted with the bid to show the contractor can build the job in the time asked. It is often broad: major phases, key dates and the main logic.
  2. Baseline (accepted) programme. The detailed programme agreed once the contract starts. Under NEC-style contracts the contractor submits a programme to the project manager for acceptance, and the accepted programme is the reference later changes are measured against. Read the contract text for how yours works; this is not legal advice.
  3. Updated programme. The baseline with actual progress recorded and the remaining work re-planned. Keep the baseline unchanged beside it, so the gap is visible; planned vs actual schedule shows how to read that gap task by task.

How do you build a construction programme?

  1. List the work by trade or work package. Break the job into groundworks, frame, roof, services and finishes, then into activities. The construction schedule by trade post walks through this structure.
  2. Link the activities. Join each to the one it depends on with a finish-to-start link, and add lag where work must cure, dry or be inspected.
  3. Set durations. Use working days or weeks from production rates or past jobs, not from the date you hope to finish.
  4. Add the fixed dates. Possession, sectional completion and any weather or access windows go in as milestones or constraints.
  5. Calculate the critical path and float. Critical path method explained shows the forward and backward pass by hand.
  6. Save the baseline. Freeze the agreed dates before the first update, so later changes have something to be compared with.

The same plan is called a construction schedule in North America; how Onplana handles contractors' plans shows the software side.

Program or programme?

Programme is the spelling in the UK, Ireland and most Commonwealth countries; program is the US spelling. Use the one the contract uses. People searching in either spelling are looking for the same document, and "programme of works" is the phrase that most clearly means the time plan rather than a software program or a programme of several projects.

Where do you go next?

Start from the free construction schedule template and edit it to your job, or load your own file into a scheduling tool and check the logic before you submit it.

Start from a free construction schedule template A 20-task construction plan from preconstruction and permits through foundations, structure, envelope, MEP and closeout, with 5 milestones, as a CSV for Excel and an XML file for Microsoft Project. Edit the durations to your job. → Open the construction schedule template

Microsoft Project™ is a trademark of Microsoft Corporation. Onplana is not affiliated with Microsoft.

construction programmeprogramme of worksconstruction schedulecritical pathbaselineGantt chartScheduling

Frequently asked questions

What is a construction programme?

It is the contractor's time plan for the works: the activities, the order they follow, how long each takes and the dates that matter, usually drawn as a Gantt chart. In the UK, Ireland and Australia it is the everyday word for what North American teams call the construction schedule.

What is the difference between a construction programme and a programme of works?

In everyday use there is none; both mean the time plan for the works. Some teams use programme of works for the full plan and programme for any single version of it, such as the tender or the updated programme.

Is it program or programme in construction?

Programme is the spelling in the UK, Ireland and most of the Commonwealth; program is the US spelling. The document is the same, and the term in the contract you are working under is the one to use.

Is a construction programme a contract document?

It depends on the contract. Under NEC-style contracts the contractor submits a programme for the project manager to accept, and the accepted programme is then used to assess changes; other forms treat it differently, so read the contract text and take advice rather than assuming.

What should a construction programme show?

At minimum the sequence of activities, their durations, the key dates and milestones, and the critical path with float. Where the contract asks, it also shows resources, access dates and the information the contractor needs from others.

Can I build a construction programme in a spreadsheet?

For a small job yes, but a spreadsheet will not move later activities when an earlier one slips and will not calculate the critical path. Once activities depend on each other, use a scheduling tool with linked tasks.